Four Seasons Environmental, Inc. v. Westfield Companies

638 N.E.2d 91, 93 Ohio App. 3d 157, 1994 Ohio App. LEXIS 313
CourtOhio Court of Appeals
DecidedFebruary 2, 1994
DocketNo. C-920899.
StatusPublished
Cited by13 cases

This text of 638 N.E.2d 91 (Four Seasons Environmental, Inc. v. Westfield Companies) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Four Seasons Environmental, Inc. v. Westfield Companies, 638 N.E.2d 91, 93 Ohio App. 3d 157, 1994 Ohio App. LEXIS 313 (Ohio Ct. App. 1994).

Opinion

Per Curiam.

This cause came on to be heard upon the appeal, the transcript of the docket, journal entries and original papers from the Hamilton County Court of Common Pleas, and the briefs and arguments of counsel.

FACTS/PROCEEDINGS

The Thomas J. Dyer Company (“Dyer”) contracted to do construction work on the Convention Center Project in Cincinnati, Ohio. To complete a portion of its duties, Dyer engaged Weldcraft, Inc. as a subcontractor to do sheetmetal ductwork on the project. Weldcraft, in turn, entered into a contract with Ohio Farmers Insurance Company of the Westfield Companies (“Westfield”) for it to act as a surety on the contract with Dyer. Under that contract, Westfield held a bond for $219,000, from which the performance of the Weldcraft/Dyer contract was guaranteed. Seeking to protect itself as surety, Westfield contracted with Weldcraft, Clem Turner, Fred B. DeBra Company, Fred E. DeBra, Donna DeBra, Daniel H. Tarkington, Sandra Tarkington, David A. DeBra, and Diane L. DeBra (“third-party defendants”) to indemnify Westfield for any loss it incurred in its agreement with Weldcraft.

Before its obligations on the convention center were complete, Weldcraft defaulted on its contract with Dyer. To complete Weldcraft’s work, Westfield entered into an additional $24,000 contract with a second subcontractor, Four Seasons Environmental (“Four Seasons”). When it completed the project, Four Seasons sued Westfield for the amount due on the contract. Westfield then impleaded third-party defendants for indemnity. Subsequently, in response to Westfield’s motion, the trial court entered a summary judgment against the third- *159 party defendants for the amount due on the Four Seasons contract. From that judgment, Fred B. DeBra Company, Fred E. DeBra, Donna DeBra, Daniel H. Tarkington, Sandra Tarkington, David A. DeBra, and Diane L. DeBra (“De-Bra/indemnitors”) bring this appeal.

ASSIGNMENT OF ERROR: FAILURE TO MITIGATE

In their single assignment of error, DeBra/indemnitors argue that the trial court incorrectly entered summary judgment because a question of material fact remained, ie., had Westfield mitigated its damages? Specifically, DeBra/indem-nitors claim that Dyer was holding approximately $5,000 for work that Weldcraft had completed, but for which it had not been paid. They argue that if Westfield, as a surety, had mitigated its damages by collecting the $5,000, their liability as indemnitors would have been reduced.

The trial court may enter summary judgment when no genuine issue of material fact remains to be litigated and the moving party is entitled to judgment as a matter of law. Civ.R. 56(C). Indemnity arises from contract, either express or implied, and is the right of a person who has been compelled to pay what another should have paid to require complete reimbursement. Travelers Indemn. Co. v. Trowbridge (1975), 41 Ohio St.2d 11, 70 O.O.2d 6, 321 N.E.2d 787, paragraph two of the syllabus. An indemnity agreement, such as the one between Westfield and DeBra/indemnitors, is interpreted like any contract to conform to the intent of the parties. Worth v. Aetna Cas. & Sur. Co. (1987), 32 Ohio St.3d 238, 240-241, 513 N.E.2d 253, 256. When the terms of a contract are clear and unambiguous, no genuine issue of material fact remains, and the trial court may enter judgment as a matter of law. Davis v. Loopco Industries, Inc. (1993), 66 Ohio St.3d 64, 65, 609 N.E.2d 144, 145, citing Alexander v. Buckeye Pipe Line Co. (1978), 53 Ohio St.2d 241, 7 0.0.3d 403, 374 N.E.2d 146.

The indemnity contract here provides that the DeBra/indemnitors “unconditionally agree to indemnify and reimburse Sureties [Westfield] against any and all loss * * * in connection with the performance of [Weldcraft/Dyer] contract.” DeBra/indemnitors argue, however, that, even though they were obligated to indemnify the sureties, Westfield was required to mitigate its damages by pursuing the $5,000 held by Dyer.

In Ohio, under the mitigation doctrine of avoidable consequences, a party who makes a claim on a contract cannot receive damages that it could have prevented by “reasonable affirmative action.” F. Enterprises v. Kentucky Fried Chicken Corp. (1976), 47 Ohio St.2d 154, 1 O.O.3d 90, 351 N.E.2d 121, paragraph three of the syllabus. The doctrine of avoidable consequences is a rule “arising from the cardinal principle that the damage award should put the injured party in *160 as good a position had the contract not been breached at the least cost to the defaulting party.” Id. at 159-160, 1 0.0.3d at 93, 351 N.E.2d at 125. One possible affirmative action available to a surety is to assert the defenses that the principal has against its creditor. See, generally, Holben v. Interstate Motor Freight Sys. (1987), 31 Ohio St.3d 152, 156-157, 31 OBR 318, 321-322, 509 N.E.2d 938, 941; Mut. Fin. Co. v. Politzer (1970), 21 Ohio St.2d 177, 183-184, 50 O.O.2d 397, 401-402, 256 N.E.2d 606, 611; Am. Ins. Co. v. Ohio Bur. of Workers’ Comp. (1991), 62 Ohio App.3d 921, 925, 577 N.E.2d 756, 759. Therefore, in a suit between creditor, Dyer, and surety, Westfield may have had the right to assert Dyer’s nonpayment of the $5,000 to Weldcraft, the principal, as a partial defense or setoff to a claim that Dyer had on the surety bond.

Concerning indemnitee mitigation generally, some courts in other states have held that indemnitees have a duty to take reasonable actions to avoid passing on unnecessary losses to indemnitors. See, e.g., Internatl. Minerals & Chem. Corp. v. Avon Products, Inc. (1991), 817 S.W.2d 903, 910; Fed. Ins. Co. v. Walker (1981), 53 N.Y.2d 24, 34, 439 N.Y.S.2d 888, 892, 422 N.E.2d 548, 552; Town Pump, Inc. v. Diteman (1981), 191 Mont. 98, 104-105, 622 P.2d 212, 216. By contrast, other courts have found no duty for indemnitees to mitigate damages of their indemnitors. See, e.g., Moya v. Fid. & Cas. Co. of New York (1965), 75 N.M. 462, 466, 406 P.2d 173, 176.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harsh v. NHC - Five Points, L.L.C.
2025 Ohio 2904 (Ohio Court of Appeals, 2025)
Benton Village Condominium Owner's Assn. v. Holdings, JRG Ltd.
2024 Ohio 1990 (Ohio Court of Appeals, 2024)
Ladd v. Planchak
2024 Ohio 24 (Ohio Court of Appeals, 2024)
PHH Mtge. Corp. v. Barker
2019 Ohio 5301 (Ohio Court of Appeals, 2019)
United Gulf Marine, L.L.C. v. Continental Refining Co., L.L.C.
2019 Ohio 666 (Ohio Court of Appeals, 2019)
United States Fire Ins. v. Am. Bonding Co., Inc.
2016 Ohio 7968 (Ohio Court of Appeals, 2016)
First Fin. Bank, N.A. v. Cooper
2016 Ohio 3523 (Ohio Court of Appeals, 2016)
Cincinnati Insurance Company v. Stacey, Ca2008-06-019 (12-22-2008)
2008 Ohio 6761 (Ohio Court of Appeals, 2008)
Midam Bank v. Dolin, Unpublished Decision (6-30-2005)
2005 Ohio 3353 (Ohio Court of Appeals, 2005)
Parrish v. MacHlan
722 N.E.2d 529 (Ohio Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
638 N.E.2d 91, 93 Ohio App. 3d 157, 1994 Ohio App. LEXIS 313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/four-seasons-environmental-inc-v-westfield-companies-ohioctapp-1994.