Four Elyria Co., L.L.C. v. Brexton Constr., L.L.C.

2025 Ohio 1778
Ohio Court of Appeals·Decided May 19, 2025·No. 24CA012089·Published

Opinion

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF LORAIN )

FOUR ELYRIA COMPANY, LLC C.A. No. 24CA012089 Appellant/Cross-Appellee

v. APPEAL FROM JUDGMENT ENTERED IN THE

BREXTON CONSTRUCTION, LLC, et al. COURT OF COMMON PLEAS COUNTY OF LORAIN, OHIO

Appellee/Cross-Appellant CASE No. 17CV192092

DECISION AND JOURNAL ENTRY Dated: May 19, 2025

HENSAL, Judge.

{¶1} Appellant/Cross-Appellee, Four Elyria Company, LLC (“Four Elyria”), appeals from the judgment of the Lorain County Common Pleas. Additionally, Appellee/Cross-Appellant, Brexton Construction, LLC (“Brexton”), cross-appeals. This Court affirms in part, reverses in part, and remands the matter for additional proceedings.

I.

{¶2} This is the second time this matter has come before the Court. Our first opinion outlined the factual and procedural history of this case in great detail. See Four Elyria Co., LLC v. Brexton Constr., LLC, 2022-Ohio-2989 (9th Dist.). It is unnecessary for us to repeat that entire history herein because this appeal involves fewer parties and issues. Accordingly, we limit our discussion to that which is necessary to resolve the appeal.

{¶3} Four Elyria sought to build a shopping plaza on commercial real estate property it owned in Elyria. The plaza would be named Chestnut Commons. It would consist of four leased

retail stores, one of which would be a Petco. Four Elyria hired an architect (“the Architect”) to design the project and a construction manager to oversee its construction. Brexton is the construction manager Four Elyria hired.

{¶4} The Architect provided Brexton with plans for Chestnut Commons. The plans he provided Brexton included plans he had designed himself and Prototype Plans he had received directly from Petco. The Architect did not prepare the Petco Prototype Plans. The Prototype Plans showed tenant improvement work for a typical Petco store, but they were not site-specific to Chestnut Commons. They included the following disclaimer:

THIS DRAWING IS FOR DESIGN INTENT ONLY AND SHALL NOT BE USED FOR CONSTRUCTION PURPOSES. CONSTRUCTION DOCUMENTS MUST BE PREPARED BY AN AUTHORIZED, LICENSED DESIGN PROFESSIONAL FOR EACH INDIVIDUAL PROJECT.

The plans the Architect prepared himself included a section for “PROJECT NOTES.” Relevant to this appeal, that section included the following note:

THIS PROJECT CONSISTS OF SHELL BUILDING AND LANDLORD’S T.I.

WORK. TENANT’S INTERIOR T.I. WORK TO BE SUBMITTED UNDER SEPARATE CONTRACT. THIS CONSTRUCTION SET NOT FOR OCCUPANCY.

(Emphasis in original.) It is undisputed that “T.I. WORK” meant tenant improvement work.

{¶5} Brexton sent Four Elyria pricing information for the construction of Chestnut Commons. The tendered price was termed the guaranteed maximum price (“GMP”). The parties then executed a GMP contract (“the Contract”). The Contract and its attachments defined the scope of work and total price for the Chestnut Commons project. Per the Contract, Brexton would be “responsible for paying all costs of completing the Work which exceed the GMP, as adjusted in accordance with this Agreement.” “Work” was a defined term under the Contract. The Contract

addressed potential changes to the Work that might impact the GMP. It required any such changes to be formalized by Change Order.

{¶6} Several months after the parties executed the Contract, Four Elyria sent Brexton additional drawings. The drawings, designed by Petco’s architects, were for site-specific tenant improvement work at the Petco in Chestnut Commons (“the Site-Specific Work”). Brexton accepted the drawings. It substantially completed Chestnut Commons, including the Site-Specific Work, by November 2016. In late November, Brexton submitted two pay applications to Four Elyria. The first was for the balance due under the Contract. The second was for the retainage. Each pay application included an unconditional waiver and release of liens. Each unconditional waiver/release provided:

[Brexton] has completed the work performed and the materials supplied to date represent the fair and actual value of work accomplished under the terms of the Contract and has been paid, receipt and sufficiency of which is hereby acknowledged, and does hereby waive, release and quitclaim in favor of [Four Elyria] . . . all rights that [Brexton] may have to a lien upon [Chestnut Commons]

and improvements thereon by reason of or on account of any work, labor, services equipment and materials furnished by [Brexton] whether fully described and identified herein or not through the release date.

It is undisputed that Four Elyria paid Brexton the GMP under the Contract.

{¶7} After Four Elyria paid Brexton, Four Elyria learned that several of Brexton’s subcontractors had not been paid for work they performed in connection with the Site-Specific Work. Brexton then contacted Four Elyria directly and demanded further payment. It became clear that the parties did not agree as to whether the Site-Specific Work was part of the Contract. According to Four Elyria, that work was part of the Contract and there were never any discussions about it causing an increase in the GMP. According to Brexton, the Site-Specific Work was never part of the Contract and Four Elyria specifically instructed it not to submit a Change Order for the work because Four Elyria did not want its lender to learn of the additional cost. Brexton expected

Four Elyria to pay it separately for the Site-Specific Work, which amounted to almost $500,000. The unresolved dispute led Brexton and several of its subcontractors to file mechanic’s liens against Chestnut Commons.

{¶8} Four Elyria filed suit against Brexton and two of its officers. Its complaint included causes of action for breach of contract, fraud, and slander of title. Four Elyria alleged that Brexton breached the Contract by failing to pay its subcontractors. Four Elyria further alleged that Brexton committed fraud when its officers, to secure final payment from Four Elyria, executed unconditional releases and lien waivers with knowledge that Brexton and its subcontractors intended to seek more money from Four Elyria. Finally, Four Elyria alleged that Brexton slandered its title by filing a lien for money Brexton knew it was not owed.

{¶9} Brexton and its officers answered the complaint and filed counterclaims against Four Elyria. The counterclaims were for breach of contract, unjust enrichment, declaratory judgment, and foreclosure of its mechanic’s lien. Brexton alleged that Four Elyria breached the Contract by failing to pay it in full for the Site-Specific Work. Alternatively, Brexton alleged that it was entitled to payment from Four Elyria under a theory of unjust enrichment. Brexton also asked the court to declare its lien valid and order foreclosure.

{¶10} Brexton moved for summary judgment on Four Elyria’s complaint. It also moved for summary judgment on its own counterclaim for unjust enrichment. Four Elyria moved for summary judgment on its complaint. It also moved for summary judgment on each of Brexton’s counterclaims. Each party filed responsive briefs as well as replies. The trial court ruled on the pending motions for summary judgment in a single judgment entry.

{¶11} The trial court found the parties had one written contract. It found the Site-Specific Work was not part of the Contract, so it was not included in the GMP. Those findings led the court

to conclude that no breaches of contract had occurred. Thus, it awarded summary judgment (1) to Brexton on Four Elyria’s breach of contract claim, and (2) to Four Elyria on Brexton’s counterclaim for breach of contract.

{¶12} The trial court next addressed Four Elyria’s claims for fraud and slander of title.

Free access — add to your briefcase to read the full text and ask questions with AI

Four Elyria Co., L.L.C. v. Brexton Constr., L.L.C., 2025 Ohio 1778 (Ohio Ct. App. 2025).

2025 Ohio 1778 (Four Elyria Co., L.L.C. v. Brexton Constr., L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sunoco, Inc. (R & M) v. Toledo Edison Co.
2011 Ohio 2720 (Ohio Supreme Court, 2011)
JPMorgan Chase Bank, Natl. Assn. v. Burden
2014 Ohio 2746 (Ohio Court of Appeals, 2014)
Kallas v. Manor Care of Barberton, OH, L.L.C.
2017 Ohio 76 (Ohio Court of Appeals, 2017)
Woodside Mgt. Co. v. Bruex
2020 Ohio 4039 (Ohio Court of Appeals, 2020)
Temple v. Wean United, Inc.
364 N.E.2d 267 (Ohio Supreme Court, 1977)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Village of Grafton v. Ohio Edison Co.
77 Ohio St. 3d 102 (Ohio Supreme Court, 1996)
Four Elyria Co., LLC v. Brexton Constr., L.L.C.
2022 Ohio 2989 (Ohio Court of Appeals, 2022)
Tera, L.L.C. v. Rice Drilling D, L.L.C.
2024 Ohio 1945 (Ohio Supreme Court, 2024)