Four Elyria Co., LLC v. Brexton Constr., L.L.C.

2022 Ohio 2989, 195 N.E.3d 1083
CourtOhio Court of Appeals
DecidedAugust 29, 2022
Docket20CA011694 & 20CA011695
StatusPublished
Cited by4 cases

This text of 2022 Ohio 2989 (Four Elyria Co., LLC v. Brexton Constr., L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Four Elyria Co., LLC v. Brexton Constr., L.L.C., 2022 Ohio 2989, 195 N.E.3d 1083 (Ohio Ct. App. 2022).

Opinion

[Cite as Four Elyria Co., LLC v. Brexton Constr., L.L.C., 2022-Ohio-2989.]

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF LORAIN )

FOUR ELYRIA COMPANY, LLC C.A. Nos. 20CA011694 20CA011695 Appellants/Cross-Appellees

v. APPEAL FROM JUDGMENT BREXTON CONSTRUCTION, LLC, et al. ENTERED IN THE COURT OF COMMON PLEAS Appellees/Cross-Appellants COUNTY OF LORAIN, OHIO CASE No. 17CVI92092

DECISION AND JOURNAL ENTRY

Dated: August 29, 2022

HENSAL, Judge.

{¶1} Four Elyria Company, LLC (“Four Elyria”) and David Thomas appeal from the

judgments of the Lorain County Court of Common Pleas. Brexton Construction, LLC

(“Brexton”), cross-appeals. This Court affirms in part, reverses in part, and remands the matter

for further proceedings.

I.

{¶2} This case primarily involves a contract dispute between the owner of a shopping

plaza and the construction manager the owner hired to oversee construction of the plaza. More

specifically, it involves a dispute as to whether certain work the construction manager performed

was within the scope of the contract between the construction manager and the owner, or whether

the construction manager was entitled to compensation for that work outside of the contract.

{¶3} The underlying record is voluminous, involving multiple parties, claims,

counterclaims, cross-claims, a third-party complaint, and several motions for summary judgment. 2

This Court will limit its discussion of the facts and procedural history to those relevant to the

disposition of this appeal.

{¶4} We begin our discussion with a review of the parties followed by a timeline of the

relevant events. Four Elyria is the owner of a shopping plaza called Chestnut Commons, a

shopping center located in Elyria, Ohio that contains four retail stores. David Thomas and Grant

Giltz, among others, are members of Four Elyria. Mr. Thomas, an attorney, handled some of the

legal issues for Four Elyria, and Mr. Giltz was responsible for managing the construction on

Chestnut Commons. At his deposition, Mr. Giltz testified as the Civil Rule 30(B)(5) witness on

behalf of Four Elyria. David Pontia is the architect Four Elyria hired for the Chestnut Commons

project. Mr. Pontia is not a party to the underlying lawsuits.

{¶5} Brexton is the construction manager Four Elyria hired to oversee the construction

of Chestnut Commons. Timothy Galvin is the founder, past president, and current CEO of

Brexton. At his deposition, Mr. Galvin testified as the Rule 30(B)(5) witness on behalf of Brexton.

At all relevant times, Mary Beatty was the CFO, then executive vice president, then president of

Brexton.1

{¶6} Protective Life Insurance Company (“Protective”) is the lender that refinanced

Chestnut Commons. Mr. Thomas is the member of Four Elyria who signed the loan documents

on behalf of Four Elyria, as well as a personal guaranty and a borrower’s affidavit, in connection

with the refinancing.

{¶7} In November 2015, Four Elyria and Brexton engaged in discussions regarding the

construction of Chestnut Commons, which included the construction of a Petco. As part of those

1 Subsequent references to Brexton may include Brexton, Ms. Beatty, and Mr. Galvin, collectively. 3

discussions, Four Elyria’s architect, Mr. Pontia, provided Brexton with Petco’s prototype tenant

improvement plans (“Prototype Plans”), among other documents, which were not site-specific.

The Prototype Plans contained a disclaimer stating: “For Design Intent Only and Shall Not be Used

for Construction Purposes.” According to Mr. Pontia’s deposition testimony, the Prototype Plans

were sent to Brexton for pricing purposes because Petco had not issued the final, site-specific

tenant improvement plans yet. Mr. Pontia was not involved in preparing the Prototype Plans, nor

the final, site-specific tenant improvement plans, both of which were provided by Petco.

{¶8} Brexton also received Mr. Pontia’s drawings for the project. On the cover page of

the drawings, Mr. Pontia included a “Project Note[]” stating: “The Project Consists of Shell

Building and Landlords T.I. Work. Tenants Interior T.I. Work to be Submitted under Separate

Contract * * *.” At his deposition, Mr. Pontia explained that this language meant that he expected

there to be a separate set of construction documents for the Petco tenant improvement work. He

also explained that the reference to the “Contract” in the “Project Note[]” referred to the contract

between Pontia Architecture and Four Elyria, not a contract between Brexton and Four Elyria.

{¶9} In early January 2016, Brexton emailed Four Elyria its “all-in” price for the work

Brexton was to perform at Chestnut Commons. Days later, Four Elyria and Brexton executed a

construction manager at-risk guaranteed maximum price agreement (the “Contract”). The

Contract and its attachments defined the scope of the work, listed the maximum guaranteed price

as $2,475,508, and provided that Brexton would be “responsible for paying all costs of completing

the Work which exceed the [guaranteed maximum price], as adjusted in accordance with this

Agreement.”

{¶10} The Contract provided that any changes in the work that impacted the guaranteed

maximum price were to be formalized in a change order, and that Brexton was not obligated to 4

perform such work until a change order had been executed. The Contract also provided that, if

there was a dispute as to whether any work was within the scope of the Contract, Brexton was to

furnish Four Elyria with an estimate of the costs to perform the disputed work. The Contract

further provided that Brexton was to submit any claim for an increase in the guaranteed maximum

price to Four Elyria in writing.

The Contract contained an integration clause, stating that the Contract represented the entire

agreement between the parties, and superseded all prior negotiations, representations, or

agreements, either written or oral. “Contract Documents” was defined to include the “existing

Contract Documents listed in section 15.1, drawings, specifications, [and] addenda issued and

acknowledged prior to the execution of this Agreement[.]” Section 15.1 addressed the “Existing

Contract Documents” and referenced five exhibits labeled A, B, C, D, and F. 2 Exhibit A was the

list of drawings. Exhibit A did not include the Protype Plans, nor did it include the final, site-

specific drawings for the Petco tenant improvement work, which were not in existence at the time

the parties executed the Contract. At his deposition, Mr. Galvin acknowledged that the drawings

contained in Exhibit A did contain some Petco tenant improvement work, albeit limited.

According to Four Elyria, the “Contract Documents” included the Prototype Plans because those

drawings were “issued and acknowledged” by Brexton prior to the execution of the Contract.

Brexton disputes this, claiming that the only drawings incorporated into the Contract are those

contained in Exhibit A. Exhibit C to the Contract was captioned “Assumptions & Clarifications”

and provided: “[c]ompletion date for Petco to be 08/27/16.”

2 While inconsequential to this matter, we note that Exhibit D, the construction schedule, was not attached to the Contract. 5

{¶11} Section 3.4.2 of the Contract addressed the “Basis of Guaranteed Maximum Price”

and required Brexton to “include with the [guaranteed maximum price] proposal a written

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Four Elyria Co., L.L.C. v. Brexton Constr., L.L.C.
2025 Ohio 1778 (Ohio Court of Appeals, 2025)
Crockett Homes, Inc. v. Tracy
2024 Ohio 1464 (Ohio Court of Appeals, 2024)
Lucas v. Eclipse Cos., L.L.C.
2023 Ohio 4728 (Ohio Court of Appeals, 2023)
Jones v. Brentwood Health Care Ctr.
2023 Ohio 1655 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 2989, 195 N.E.3d 1083, Counsel Stack Legal Research, https://law.counselstack.com/opinion/four-elyria-co-llc-v-brexton-constr-llc-ohioctapp-2022.