Fought & Co. v. Steel Engineering & Erection, Inc.

951 P.2d 487, 87 Haw. 37, 1998 Haw. LEXIS 8
CourtHawaii Supreme Court
DecidedFebruary 11, 1998
Docket19103
StatusPublished
Cited by81 cases

This text of 951 P.2d 487 (Fought & Co. v. Steel Engineering & Erection, Inc.) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fought & Co. v. Steel Engineering & Erection, Inc., 951 P.2d 487, 87 Haw. 37, 1998 Haw. LEXIS 8 (haw 1998).

Opinion

LEVINSON, Justice.

The plaintiff-appellee Fought & Company (Fought) and the defendants/cross-claimants/cross-claim defendants-appellants/cross-claim defendants-appellees Steel Engineering and Erection, Inc., Continental Casualty Corporation (Continental), which is Steel’s surety, (collectively Steel) and Kiewit Pacific Company (Kiewit) prevailed in Supreme Court No. 19103, 1 which affirmed (1) the circuit court’s order granting (a) Steel’s motion for summary judgment against Kiewit *41 and the defendant/cross-claim defendant/cross-claim defendant-appellant/cross-elaim defendant-appellee Department of Transportation, State of Hawai'i (the DOT) and (b) Kiewit’s motion for summary judgment against the DOT, filed on May 8, 1995, (2) the judgment filed on May 30, 1995, (3) the order denying the DOT’s motion for reconsideration, filed on June 26, 1995, (4) the order granting and directing entry of final judgment on Fought’s motion for summary judgment against Steel, filed on May 4,1995, and (5) the judgment filed on May 23, 1995. Fought, Steel, and Kiewit seek attorneys’ fees and costs pursuant to Hawai'i Revised Statutes (HRS) § 607-14 (Supp.1997) 2 and Hawai'i Rules of Appellate' Procedure (HRAP) Rule 39 (1996). 3 Fought asserts an additional ground for recovery against Continental in HRS § 431:10-242 (1993). 4 Steel and Kiewit, respectively, also seek indemnification from Kiewit and the DOT, respectively, for any attorneys’ fees and costs for which Steel and Kiewit may be deemed hable.

For the reasons set forth below, we award: (1) attorneys’ fees in the amount of $39,-888.93 and costs in the amount of $163.20 in favor of Fought and against Steel; (2) attorneys’ fees in the amount of $22,005.58 and" costs in the amount of $16,271.76 in favor of Steel and against Kiewit, as well as indemnification in the amount of $40,052.03, representing the costs and fees that Steel is ordered to pay to Fought; and (3) attorneys’ fees in the amount of $30,919.89 and costs in the amount of $11,305.34 in favor of Kiewit and against the DOT, as well as indemnification in the amount of $78,329.37, representing the costs and fees that Kiewit has been ordered to pay to Steel.

L BACKGROUND

The lawsuit underlying the present requests for attorneys’ fees and costs arose out of the construction of a new terminal building, phase I, unit 2, at the Kahului Airport, Kahului,' Maui, designated as project No. AM1042-13 (the project). Kiewit was general contractor for the project. Kiewit subcon *42 tracted with Steel for the supply and erection of structural steel components for the project. Steel in turn contracted with Fought to supply materials pursuant to Steel’s subcontract with Kiewit.

After a dispute arose pertaining to the correct interpretation of provisions in the project specifications, the DOT claimed that Fought, Steel, and Kiewit had all breached their respective contracts by providing and/or utilizing nonconforming steel and, accordingly, withheld $312,000.00 in compensation for the alleged breach from its payments to Kiewit. As a result, Kiewit withheld $312,000.00 under its subcontract with Steel, and Steel withheld the same amount from its payment to Fought.

Fought then filed suit, seeking payment of the $312,000.00 from Steel. Steel cross-claimed against Kiewit, and Kiewit cross-claimed against the DOT. As a result of motions for summary judgment filed by Fought, Steel, and Kiewit, judgments were entered in favor of Fought and against Steel, in favor of Steel and against Kiewit, and in favor of Kiewit and against the DOT. In an order filed on May 8, 1995, the circuit court ruled:

1. Steel Engineering is entitled to judgment against Kiewit for whatever amount Steel Engineering is ultimately held liable to Fought. The Court has already ruled that Steel Engineering is liable to Fought for $312,000 plus interest at the legal rate of 10% per annum as provided in Section 478-2(4) of the Hawaii Revised Statutes. Accordingly, Steel Engineering is entitled to a judgment against Kiewit for $312,000 plus interest at the legal rate of 10% per annum.
[[Image here]]
2. Kiewit is entitled to judgment against the State for whatever amount Kiewit is ultimately held liable to Steel Engineering. Accordingly, Kiewit is entitled to judgment against the State for $312,000 plus interest at the legal rate of 10% per annum.

On May 30, 1995, judgments in the amount of $312,000.00 plus interest at the rate of ten percent per annum, were entered against Kiewit and the DOT and were certified for appeal pursuant to Hawai'i Rules of Civil Procedure (HRCP) Rule 54(b). 5 The DOT filed a motion to reconsider in order to raise the jurisdictional issue of sovereign immunity. However, the circuit court denied the motion in an order filed on June 26, 1995. The DOT then filed a notice of appeal from the two orders and the judgment.

On appeal, the DOT argued that: (1) the claims asserted against it by Fought, Steel, and Kiewit were barred by the doctrine of sovereign immunity; 6 (2) if the claims *43 against the DOT were not barred by sovereign immunity, then summary judgment had been erroneously granted because there remained genuine issues of material fact regarding the provisions of the contracts at issue; or (3) if the claims against'the DOT were not barred by sovereign immunity and the contract terms were subject to only one reasonable interpretation, then HRS § 661-8 (1993) 7 prohibited an award of prejudgment interest against the DOT. Kiewit and Steel argued on cross-appeal that, if the DOT had no liability on the contracts, then there was no independent basis for imposing liability on Kiewit and Steel in favor of Fought. Finding no merit in the DOT’S argument, this court affirmed all of the orders and judgments of the circuit court in a summary disposition order, which was filed on July 28, 1997. Having been mooted, Kiewit’s and Steel’s cross-appeals were not addressed.

On September 12,1997, Fought, Steel, and Kiewit each filed requests for costs and attorneys’ fees pursuant to HRAP Rule 39, see supra note 3, and HRS § 607-14, see supra note 2. Fought requests attorneys’ fees in the amount of $44,235.83 and $163.20 in photocopying costs. Steel requests attorneys’ fees in the amount of $22,005.58 and costs totaling $16,271.76. 8 Kiewit requests attorneys’ fees in the amount of $30,919.89 and costs totaling $11,305.34. 9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chiang v. The Ritz-Carlton Hotel Co
Hawaii Intermediate Court of Appeals, 2025
KRB, LLC v. State
155 Haw. 253 (Hawaii Intermediate Court of Appeals, 2024)
Blangiardi v. Hawaii Fire Fighters Association
558 P.3d 1054 (Hawaii Intermediate Court of Appeals, 2024)
Title Guaranty Escrow Services, Inc v. Wailea Resort Company, LTD.
554 P.3d 566 (Hawaii Intermediate Court of Appeals, 2024)
Loyalty Development Company, LTD. v. Ching
549 P.3d 341 (Hawaii Intermediate Court of Appeals, 2024)
Adelman v. Steely
543 P.3d 1088 (Hawaii Intermediate Court of Appeals, 2024)
Public Access Trails Hawai'i v. Haleakala Ranch Company
526 P.3d 526 (Hawaii Supreme Court, 2023)
Cowan v. Pauoa Bay Properties, LLC
523 P.3d 1076 (Hawaii Intermediate Court of Appeals, 2023)
Alexander & Baldwin , LLC v. Armitage.
508 P.3d 832 (Hawaii Supreme Court, 2022)
Sheveland v. Wells Fargo Bank, N.A..
436 P.3d 1175 (Hawaii Supreme Court, 2019)
Barranco v. 3D Sys. Corp.
307 F. Supp. 3d 1075 (D. Hawaii, 2018)
Gold Coast Neighborhood Association v. State.
403 P.3d 214 (Hawaii Supreme Court, 2017)
Hussey v. Say.
384 P.3d 1282 (Hawaii Supreme Court, 2016)
Estate of St. Martin v. Hixson
145 So. 3d 1124 (Mississippi Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
951 P.2d 487, 87 Haw. 37, 1998 Haw. LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fought-co-v-steel-engineering-erection-inc-haw-1998.