Foster & Creighton Co. v. Box

66 So. 2d 746, 259 Ala. 474, 1953 Ala. LEXIS 336
CourtSupreme Court of Alabama
DecidedJune 30, 1953
Docket1 Div. 470
StatusPublished
Cited by27 cases

This text of 66 So. 2d 746 (Foster & Creighton Co. v. Box) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foster & Creighton Co. v. Box, 66 So. 2d 746, 259 Ala. 474, 1953 Ala. LEXIS 336 (Ala. 1953).

Opinion

PER CURIAM.

This is a suit on the common counts for certain work done by appellee, Box, for the benefit of appellant, Foster and Creighton Company, in which appellee recovered a judgment on the verdict of a jury.

The parties had a written contract for the work to be done by Box for the company. This was a subcontract. The company had a general contract to furnish all labor, tools, material, equipment, etc., necessary to construct a concrete pile wharf section for berth number 8 of marginal wharf at Alabama State Docks and Terminals at Mobile.

The particular work for which a charge is here made consists in bending the steel reinforcement rods protruding 'up about four feet from the top of concrete piles which supported the structure. The piles were constructed by first producing forms of the proper size and length. In these forms four steel reinforcing rods one and one-fourth inches in diameter were placed and tied with wire forming a cage to stay them in position. The concrete was then poured into and filled the forms with the end of the steel rods protruding out of the top. The piles in that condition had to be driven by the company to proper level. The end of the rods then had to be bent to level position and thereby extended into and reinforced the concrete floor and tied it to the piles. This driving could not be done after the rods were bent, but was done before that occurred. The contract between the company and the State Docks Commission required the company to do it. It was done by Box for which this suit was brought. The work was done at the request of the job superintendent of the company, and accepted by the inspector. No one else for the company authorized or directed Box to do the work.

There was also brought into question a contract between Box and Bernard and Byrd in respect to the transaction, in which it is claimed Box agreed to 'do this bending to be paid for by Bernard and Byrd.

*477 The contract between Box and the company (Foster and Creighton Company) obligated Box “to furnish all labor, tools, equipment, supplies, etc., and unload and' place all reinforcing steel and accessories, as required by plans and specifications, foi a unit price of twenty-seven and 50/100 dollars ($27.50) per net ton for steel in place. All reinforcing steel, accessories and tie wire is to be furnished by others without cost to you” (appellee). It was further stipulated: “All terms of our general contract with the owner dated November 6, 1947, shall apply to your work under this agreement wherever they may be appliable.” Nothing in it obligated Box to do the bending of the steel rods.

Bernard and Byrd also had a subcontract with the company for certain aspects of the work. It stipulated that Bernard and Byrd would “do all the work and furnish all the labor, materials, tools, machinery, equipment, facilities, supplies, etc., except as herein otherwise specified, necessary or proper for performing and completing the following work: unload reinforcing steel from cars and fabricate and tie this reinforcing steel into cages as shown on plans. Bernard and Byrd, Inc., will hoist and place completed cages in forms and when forms are properly adjusted R. E. Box will properly space cages in form, hanging same to forms as directed.” In the contract between Bernard and Byrd and Box reference is made to that feature of the contract between Bernard and Byrd and the company, quoting from it what we have written supra, and then providing as follows: “Subcontractor (Box) shall complete the entire work (of Bernard and Byrd) in the manner and within the time hereinafter specified to the satisfaction of the architect or engineer and in accordance with the plans, specifications and drawings of the architect or engineer.”

It therefore appears that neither the contract of appellant with appellee nor that with Bernard and Byrd, nor the contract of Bernard and Byrd with the company in terms obligated any of them to bend the steel rods after they had been placed and the piles driven, but that the contract between the company and the State Docks Commission required the company to do so.

Counsel for appellant, the company, argues that if the bending of the rods shown on the blue print was called for by either contract, then plaintiff has misconceived his remedy because the law will not imply a promise where there is an express promise, and defendant was entitled to the affirmative charge. If the contract of plaintiff with Bernard and Byrd imposed a duty on plaintiff to bend the rods in compliance with the duty of the company to the State Docks Commission, there would be no implied contract of the company by an acceptance of the work. For one doing work for a contractor under an express contract and on its sole faith is prohibited from claiming thereby an implied contract by the owner to pay him for the work by the acceptance of it by the owner. Alexander v. Alabama Western R. R. Co., 179 Ala. 480, 60 So. 295.

We concede therefore that if the obligation of Box under his contract with Bernard and Byrd was to bend the rods, and thereby included in his compensation payable by Bernard and Byrd, the company by accepting the work would not be obligated to pay for it on an implied promise. The controversy at this point, therefore, depends upon a construction of the contract between Box and Bernard and Byrd with respect to bending the rods.

But before discussing that question we will, by way of parenthesis, answer another argument of appellant’s counsel. It is that the contract between Box and the company obligated Box to do the bending, for which the company expressly promised to pay Box, and therefore the common counts will not lie on an implied promise when there is an expressed one, and that under those circumstances there must be a count specially claiming for a breach of the contract to pay.

It is true that the breach of an executory contract to do an act must be redressed by a special count claiming for the breach, but when the contract has been performed by the plaintiff on his part, and no duty remains but the payment of the money *478 by the defendant, a recovery may be had on the common counts. Beadle v. Graham’s Adm’r, 66 Ala. 99.

“The general rule is that, where there is an express contract, the plaintiff cannot resort to an implied one. An exception to the rule, however, is that he may recover on the common counts, although the evidence discloses a special agreement, where such agreement has been executed and fully performed, and no duty remains but the payment of the price in money by the defendant. But, so long as the contract continues executory, the plaintiff must declare specially.” Jonas v. King, 81 Ala. 285, 1 So. 591, 592; St. Louis & S. F. R. R. Co. v. Hall, 186 Ala. 353, 65 So. 33; Henry v. Jefferson County, 234 Ala. 525, 176 So. 285; Standard Oil Co. v. Myers, 232 Ala. 662, 169 So. 312.

We cannot sustain the argument of counsel on that contention for the reason above stated and also because there was no agreement expressed between Box and the company, and none is claimed whereby Box was to do the bending for the compensation expressed.

We revert then to the question of whether the contract between Box and Bernard and Byrd imposed on Box that duty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alfa Mutual Insurance Co. v. Nationwide Mutual Insurance Co.
684 So. 2d 1295 (Supreme Court of Alabama, 1996)
ALFA MUT. INS. v. Nationwide Mut. Ins.
684 So. 2d 1295 (Supreme Court of Alabama, 1996)
House of Lloyd, Inc. v. Director of Revenue
824 S.W.2d 914 (Supreme Court of Missouri, 1992)
Home Indem. Co. v. EMPLOYERS NAT. INS. CORP.
564 So. 2d 945 (Supreme Court of Alabama, 1990)
Holland v. CONTINENTAL TELEPHONE CO. OF SOUTH
492 So. 2d 998 (Supreme Court of Alabama, 1986)
Hill Air of Gadsden, Inc. v. City of Gadsden
467 So. 2d 230 (Supreme Court of Alabama, 1985)
Upton v. Mississippi Valley Title Ins. Co.
469 So. 2d 548 (Supreme Court of Alabama, 1985)
Alpine Construction Co. v. Water Works Board of the City of Birmingham
377 So. 2d 954 (Supreme Court of Alabama, 1979)
Alpine Const. Co. v. WATER WORKS BD., ETC.
377 So. 2d 954 (Supreme Court of Alabama, 1979)
Hendrix, Mohr & Yardley, Inc. v. City of Daphne
359 So. 2d 792 (Supreme Court of Alabama, 1978)
Green v. Merrill
308 So. 2d 702 (Supreme Court of Alabama, 1975)
Southern Cafeteria Operating Company, Inc. v. Eley
296 So. 2d 743 (Court of Civil Appeals of Alabama, 1974)
Port City Construction Co., Inc. v. Henderson
266 So. 2d 896 (Court of Civil Appeals of Alabama, 1972)
AETNA LIFE INSURANCE COMPANY INC. v. Hare
256 So. 2d 904 (Court of Civil Appeals of Alabama, 1972)
Babcock v. Smith
234 So. 2d 573 (Supreme Court of Alabama, 1970)
Nelson Weaver Mortgage Co. v. Dover Elevator Co.
216 So. 2d 716 (Supreme Court of Alabama, 1968)
Travelers Insurance Company v. Kernachan
214 So. 2d 447 (Supreme Court of Alabama, 1968)
Hoover, Inc. v. McCullough Industries, Inc.
380 F.2d 798 (Fifth Circuit, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
66 So. 2d 746, 259 Ala. 474, 1953 Ala. LEXIS 336, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foster-creighton-co-v-box-ala-1953.