Forte Bros., Inc. v. RONALD M. ASH & ASSOC., INC.

612 A.2d 717, 1992 R.I. LEXIS 182, 1992 WL 165103
CourtSupreme Court of Rhode Island
DecidedJuly 17, 1992
Docket90-179-Appeal
StatusPublished
Cited by18 cases

This text of 612 A.2d 717 (Forte Bros., Inc. v. RONALD M. ASH & ASSOC., INC.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forte Bros., Inc. v. RONALD M. ASH & ASSOC., INC., 612 A.2d 717, 1992 R.I. LEXIS 182, 1992 WL 165103 (R.I. 1992).

Opinion

OPINION

FAY, Chief Justice.

This is an appeal from a judgment of the Superior Court granting the motion to dismiss of Ronald M. Ash & Associates, Inc. and its two principals (Ash), on C.A. No. 89-4900 (1989 action), the complaint filed by Forte Brothers, Inc. (Forte). The Superior Court concluded that res judicata principles barred this action because it was duplicative of a prior pending negligence action. The Superior Court simultaneously imposed sanctions on Forte’s attorneys pursuant to Rule 11 of the Superior Court Rules of Civil Procedure. Forte appeals on the grounds that the Superior Court justice erred in finding the actions duplicative and in imposing Rule 11 sanctions. Ash contends that because the 1989 action was duplicative, the Superior Court correctly dismissed the 1989 action and imposed sanctions for abuse of the pleading process. Because we conclude that the 1989 action is not duplicative of any prior pending action, we find that the Superior Court erred in dismissing the action on res judicata principles and in imposing Rule 11 sanctions on Forte’s attorneys. We therefore sustain Forte’s appeal and reverse the judgment of the Superior Court with respect to both the dismissal of the 1989 action and the imposition of sanctions. The relevant facts are as follows.

On June 25, 1981, Forte and Ash entered into a contract (1981 contract) whereby Ash was to prepare a feasibility study of the Manville Hydroelectric Dam, which study would include its providing economic, financial, and engineering services as well as preparing cost projections and analyses of the proposed project. This agreement did not contain an arbitration clause by which to settle disputes or claims. The feasibility study was completed during the summer of 1981 and concluded that the project was feasible. On September 21, 1981, Forte entered into a contract with Ash instructing Ash to prepare the licensing application with the Federal Energy Regulatory Commission and to prepare 30 percent of the preliminary engineering drawings, specifications, and cost estimates. Ash continued to provide the requested service to Forte. On November 5, 1984, the parties entered into another contract (1984 contract), according to which Ash was to prepare a dam-safety study, equipment-bid proposals, and final plans and specifications, to perform general supervisory tasks and detailed inspections, and to start up operations. The 1984 contract contained an ex *719 press arbitration clause, which stated in pertinent part, “All claims and disputes between the Client and the Engineer arising out of or relating to this Agreement, or the services to be provided herein or breach thereof shall be decided by arbitration.”

Ash continued to provide services and cost projections to Forte’s financial analysts throughout 1984, projecting costs of approximately $2 million. Forte states that on February 5, 1985, Michael DeFrancesco, one of Ash’s principals, disclosed to Forte that the project-cost estimates had increased approximately 50 percent to $3 million. The 1985 financial projections also indicated that the updated increased approximation of cost would result in a negative cash flow and cause projected losses for over twenty years. After having expended over $700,000 on the project, Forte abandoned it because Forte no longer considered the project feasible.

On March 25, 1986, Ash filed a complaint (1986 action) against Forte, alleging that Forte had breached the 1984 contract because it had failed to complete payment as agreed for services rendered. Ash sought $10,972 in damages, the difference between the contract amount and the amount Forte actually paid. In response Forte not only demanded arbitration of the claims alleged in the 1986 action pursuant to the arbitration clause in the 1984 contract but also filed a counterclaim to this complaint. Forte’s counterclaim charged that Ash was negligent and breached the 1984 contract. Forte alleges that Ash was negligent because of its continued reliance on the 1981 contract feasibility study and conclusion that the project was economically feasible and because of Ash’s subsequent representations that the project remained viable. The Superior Court stayed the 1986 action and referred the matter to arbitration. Arbitration was conducted pursuant to the Construction Industry Arbitration Rules of the American Arbitration Association. During arbitration the question arose concerning whether Forte’s evidence of negligence in the preparation of the 1981 contract feasibility study should be considered by the arbitrators in determining whether Ash breached or negligently performed the 1984 contract by relying on the mistakes allegedly made in the 1981 contract feasibility study. Ash asserted that because the 1981 contract did not contain an arbitration clause, no claims arising out of or facts concerning this contract could be submitted to arbitration. The arbitration proceedings were then suspended pending a judicial determination of the proper scope of arbitrable evidence and issues.

On May 15, 1987, Forte filed an action in Superior Court, seeking a declaratory judgment (1987 action). The 1987 action requested the trial court to declare the rights of the parties and to declare that the 1984 contract mandated that the issue of negligent preparation of the 1981 feasibility study and reliance thereon, as it related to the 1984 contract, be submitted to arbitration. Forte moved for summary judgment in the 1987 action, which Ash opposed, requesting that the 1987 action be assigned to the continuous jury trial calendar pursuant to G.L.1956 (1985 Reenactment) § 10-3-5. 1

The justice hearing the motion found that Ash had specifically requested a jury trial pursuant to § 10-3-5. 2 He stated: “In this case the defendant [Ash] contends that it is entitled to a jury trial on the issue of whether the 1981 contract is arbitrable. * * * The making of the arbitration agreement or the failure, neglect, or refusal to perform the same, therefore, is an issue.” The justice concluded that “the defendant [Ash] by its answer raised an issue as to the arbitrability of the 1981 contract or as *720 to the failure, neglect or refusal to perform the same. The parties are, therefore, entitled to a jury trial on these issues.” He then denied Forte’s motion for summary judgment and assigned the action to the continuous jury trial calendar to await resolution of the proper scope of arbitration. Forte subsequently petitioned the Superior Court to lift the stay in the 1986 action requesting termination of arbitration in order to return to court. Ash opposed the motion, and the Superior Court sustained this objection.

On September 11, 1989, Forte filed the 1989 action against Ash and also against its two principals, Ronald M. Ash and Michael DeFrancesco, seeking damages resulting from Ash’s negligent preparation of the 1981 feasibility study. On October 23, 1989, Ash filed a motion to dismiss the 1989 action on the basis that it was “intentionally misleading” and duplicative of the 1987 action. The Superior Court justice dismissed the 1989 action and simultaneously imposed Rule 11 sanctions upon Forte’s attorneys. He found the 1989 action to be duplicative of pending actions and considered the 1989 action to be abusive of the pleading process.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pomon v. Usaa President Davis
Superior Court of Rhode Island, 2009
Cathay Cathay, Inc. v. VINDALU, LLC
962 A.2d 740 (Supreme Court of Rhode Island, 2009)
Ondis v. CITY OF WOONSOCKET EX REL. TREASURER
934 A.2d 799 (Supreme Court of Rhode Island, 2007)
Pleasant Management, LLC v. Carrasco
918 A.2d 213 (Supreme Court of Rhode Island, 2007)
Opella v. Opella
896 A.2d 714 (Supreme Court of Rhode Island, 2006)
Obert v. Republic Western Insurance
398 F.3d 138 (First Circuit, 2005)
360 Thames Street Condominium Ass'n v. Landing Development Co.
838 A.2d 874 (Supreme Court of Rhode Island, 2003)
Renaissance Development Corp. v. Universal Properties Group, Inc.
821 A.2d 233 (Supreme Court of Rhode Island, 2003)
Wayne Cady v. Imc Mtg. Co., 98-5400, (1-31-2002)
Superior Court of Rhode Island, 2002
Town of West Greenwich v. A. Cardi Realty Associates
786 A.2d 354 (Supreme Court of Rhode Island, 2001)
Heal v. Heal
762 A.2d 463 (Supreme Court of Rhode Island, 2000)
D'AMARIO v. State
686 A.2d 82 (Supreme Court of Rhode Island, 1996)
Retirement Board of the Employees' Retirement System v. City of Providence
666 A.2d 810 (Supreme Court of Rhode Island, 1995)
PROVIDENCE RETIREMENT BD. v. City Council of Providence
660 A.2d 721 (Supreme Court of Rhode Island, 1995)
Rosati v. Kuzman
660 A.2d 263 (Supreme Court of Rhode Island, 1995)
O'Malley v. Estate of Ann Marie Dolan, 94-709 (1995)
Superior Court of Rhode Island, 1995
Sherman v. Price, 90-6306 (1994)
Superior Court of Rhode Island, 1994

Cite This Page — Counsel Stack

Bluebook (online)
612 A.2d 717, 1992 R.I. LEXIS 182, 1992 WL 165103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forte-bros-inc-v-ronald-m-ash-assoc-inc-ri-1992.