Forman v. Kelly

139 S.E. 708, 104 W. Va. 211, 1927 W. Va. LEXIS 180
West Virginia Supreme Court·Decided September 27, 1927·No. 5946·Published·Cited by 4 cases

Opinion

Lively, Judge :

The decree appealed from sustained a demurrer to plaintiff’s bill and dismissed the cause.

The controlling question to be determined is upon the sufficiency of the notice of a subcontractor to the owner of the building required by the statute in order to perfect and preserve his lien.

The bill charges in substance that the plaintiff, Forman, entered into a subcontract with Glenn Sheets, who was the general contractor employed by defendant Kelly, in the erection of a certain dwelling house on Kelly’s land; that his contract was to furnish the labor and material for the plastering of the house at the price of 75c per yard; that he performed his contract, and the amount of labor and 'material at the contract price amounted to $446.25, and that the same had not been paid by any one. The bill further charges that plaintiff theretofore had perfected and preserved a lien for said sum against said property; and the notice which he gave *213 to the owner within 60 days after he had ceased to labor and furnish materials, and required by the statute under sub-section (c) of section 3, chapter 75, of the Code, is exhibited with the bill. It is upon the sufficiency of this notice, that is, whether it is a substantial compliance with the statute, upon which the main question turns. The bill further sets up the recordation of the notice within the time prescribed by the statute, and no question is raised upon the sufficiency of the recorded notice. The bill further .charges that defendant lived near the building during the construction thereof, and that he knew plaintiff was doing the plastering in the house and was working therein before he paid the contract price of the house to Sheets.- The bill further avers that defendant Kelly is estopped to deny the validity of plaintiff’s claimed mechanic’s lien for the reason that by a petition theretofore filed in another suit pending against Sheets, he, the defendant Kelly, claimed that certain mechanics’ liens, including that of plaintiff, had been taken against his (Kelly’s) property by reason of the failure of Sheets to perform his contract as general contractor; and that .defendant .Kelly sought in that suit to recover the amount of those liens against Sheets. The prayer of the bill is for the enforcement of plaintiff’s lien against the real estate of the defendant by the sale thereof.

Under subsection (c) of section 3, chapter 75, of the Code, a subcontractor in order to perfect and preserve his lien, is required within 60 days after the completion of his subcontract to give to the owner a notice of his lien in which .he is required to state that he was a subcontractor under the general contractor, naming him, describing the nature of the subcontract, designating therein the property on which the lien is claimed and a description of the real estate on which the claim is situate, the contract price and value of the work and material furnished; that he has not been paid therefor, and that he claims and will claim a lien upon the said building, and the interest of the owner thereof in the land for the payment thereof. The notice served by plaintiff on defendant under this section complies with the requirements of the statute, except that it does not in any way refer to the *214 nature of the subcontract. It simply says that he was subcontractor with Glen Sheets, the general contractor, “for the furnishing of material and doing of the work and labor necessary to the completion of that certain building, to-wit”, (describing it and the land on which it was located), and that the contract price and value of the work and material is $446.25, which has not been paid, and that he claims and will claim a lien upon the building and the interest of defendant in the land on which it is situated. Plaintiff, and appellant here, admits that no reference whatever is made in the notice to the nature of the subcontract, whether for excavation, foundation, carpenter work,' plumbing, roofing, or any other of the various kinds of work which might be subcontracted in the erection of the building, but he argues that the notice given is a substantial compliance with the statute, and that the statute should be liberally construed.

Free access — add to your briefcase to read the full text and ask questions with AI

Forman v. Kelly, 139 S.E. 708, 104 W. Va. 211, 1927 W. Va. LEXIS 180 (W. Va. 1927).

139 S.E. 708 (Forman v. Kelly) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gray Lumber Co. v. Devore
112 S.E.2d 457 (West Virginia Supreme Court, 1960)
GRAY LUMBER COMPANY, INC. v. Devore
112 S.E.2d 457 (West Virginia Supreme Court, 1960)
Kendall v. Martin
67 S.E.2d 42 (West Virginia Supreme Court, 1951)
Fireproof Products Co. v. Logan
169 S.E. 400 (West Virginia Supreme Court, 1933)