Forman v. Kelly

139 S.E. 708, 104 W. Va. 211, 1927 W. Va. LEXIS 180
CourtWest Virginia Supreme Court
DecidedSeptember 27, 1927
Docket5946
StatusPublished
Cited by4 cases

This text of 139 S.E. 708 (Forman v. Kelly) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forman v. Kelly, 139 S.E. 708, 104 W. Va. 211, 1927 W. Va. LEXIS 180 (W. Va. 1927).

Opinion

Lively, Judge :

The decree appealed from sustained a demurrer to plaintiff’s bill and dismissed the cause.

The controlling question to be determined is upon the sufficiency of the notice of a subcontractor to the owner of the building required by the statute in order to perfect and preserve his lien.

The bill charges in substance that the plaintiff, Forman, entered into a subcontract with Glenn Sheets, who was the general contractor employed by defendant Kelly, in the erection of a certain dwelling house on Kelly’s land; that his contract was to furnish the labor and material for the plastering of the house at the price of 75c per yard; that he performed his contract, and the amount of labor and 'material at the contract price amounted to $446.25, and that the same had not been paid by any one. The bill further charges that plaintiff theretofore had perfected and preserved a lien for said sum against said property; and the notice which he gave *213 to the owner within 60 days after he had ceased to labor and furnish materials, and required by the statute under sub-section (c) of section 3, chapter 75, of the Code, is exhibited with the bill. It is upon the sufficiency of this notice, that is, whether it is a substantial compliance with the statute, upon which the main question turns. The bill further sets up the recordation of the notice within the time prescribed by the statute, and no question is raised upon the sufficiency of the recorded notice. The bill further .charges that defendant lived near the building during the construction thereof, and that he knew plaintiff was doing the plastering in the house and was working therein before he paid the contract price of the house to Sheets.- The bill further avers that defendant Kelly is estopped to deny the validity of plaintiff’s claimed mechanic’s lien for the reason that by a petition theretofore filed in another suit pending against Sheets, he, the defendant Kelly, claimed that certain mechanics’ liens, including that of plaintiff, had been taken against his (Kelly’s) property by reason of the failure of Sheets to perform his contract as general contractor; and that .defendant .Kelly sought in that suit to recover the amount of those liens against Sheets. The prayer of the bill is for the enforcement of plaintiff’s lien against the real estate of the defendant by the sale thereof.

Under subsection (c) of section 3, chapter 75, of the Code, a subcontractor in order to perfect and preserve his lien, is required within 60 days after the completion of his subcontract to give to the owner a notice of his lien in which .he is required to state that he was a subcontractor under the general contractor, naming him, describing the nature of the subcontract, designating therein the property on which the lien is claimed and a description of the real estate on which the claim is situate, the contract price and value of the work and material furnished; that he has not been paid therefor, and that he claims and will claim a lien upon the said building, and the interest of the owner thereof in the land for the payment thereof. The notice served by plaintiff on defendant under this section complies with the requirements of the statute, except that it does not in any way refer to the *214 nature of the subcontract. It simply says that he was subcontractor with Glen Sheets, the general contractor, “for the furnishing of material and doing of the work and labor necessary to the completion of that certain building, to-wit”, (describing it and the land on which it was located), and that the contract price and value of the work and material is $446.25, which has not been paid, and that he claims and will claim a lien upon the building and the interest of defendant in the land on which it is situated. Plaintiff, and appellant here, admits that no reference whatever is made in the notice to the nature of the subcontract, whether for excavation, foundation, carpenter work,' plumbing, roofing, or any other of the various kinds of work which might be subcontracted in the erection of the building, but he argues that the notice given is a substantial compliance with the statute, and that the statute should be liberally construed.

Liens of mechanics and material-men are purely statutory, and it is quite generally held they must show upon their face all of the statutory requisites to their validity. 18 R. C. L.. p. 926, see. 57. The procedure for perfecting and preserving the lien is in the hands of the mechanic or material-man. The land owner has no control over the procedure. The statute entitles the latter to full information, so that he can protect his property from sale; and although the result of the statutory procedure is a lien of as much dignity as that of a judgment of a court, it is generally held that the facts stated in the notice need not be stated with the exactness and defi-nitepess as is required in a declaration, or other pleading at law. A substantial compliance is all that is necessary. Harrison Construction Co. v. Greystone Hotel Co., 99 W. Va. 5, and cases cited. The form of the notice given in the statute above cited need not be followed, but in order to make it sufficient, the effect must be .the same. Among the necessary parts of the notice is the requirement that the nature of the subcontract be described. The notice given by For-man to Kelly says that he “was and is subcontractor with Glenn Sheets, who was and is general contractor, for the furnishing of material and doing of the work and labor necessary to the completion of that certain building”, de *215 scribing the building- and where situate. There is nothing in this language from which the nature of the subcontract can be inferred. The bill tells that the subcontract was for plastering at 75e per yard, and if we could take the aver-ments of the bill in support of the notice, there would be little difficulty in arriving at the nature of the subcontract. But we must look to the notice without aid of the bill, and the most liberal construction which can' be given to the notice will not aid in arriving at the nature of the subcontract. It would serve no useful end to stop to inquire the purpose of the legislature in requiring the subcontractor to state in the notice to the owner the nature of the subcontract. The proceeding is ex parte and summary in its nature, and must be substantially complied with whatever reason may have moved the legislature to require it. In Niswander & Co. v. Black, 50 W. Va. 188, (195), it was said that the chief purpose .of the statute which required a laborer or material-man to file with the owner an itemized account of the labor done or material furnished, is to give notice to the owner so that he may protect himself in his future dealings with the contractor. And that “to serve this purpose the claim should show wha.t it is for, whether work or materials; and a notice which does not show this is defective. Stating a balance due is not sufficient.” And in McVey v. Kaufmann, (Pa.) 72 Atl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gray Lumber Co. v. Devore
112 S.E.2d 457 (West Virginia Supreme Court, 1960)
GRAY LUMBER COMPANY, INC. v. Devore
112 S.E.2d 457 (West Virginia Supreme Court, 1960)
Kendall v. Martin
67 S.E.2d 42 (West Virginia Supreme Court, 1951)
Fireproof Products Co. v. Logan
169 S.E. 400 (West Virginia Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
139 S.E. 708, 104 W. Va. 211, 1927 W. Va. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forman-v-kelly-wva-1927.