Forks of the Patuxent Improvement Ass'n v. National Waste Managers/Chesapeake Terrace

148 A.3d 36, 230 Md. App. 349, 2016 Md. App. LEXIS 149
CourtCourt of Special Appeals of Maryland
DecidedOctober 25, 2016
Docket0361/15
StatusPublished
Cited by2 cases

This text of 148 A.3d 36 (Forks of the Patuxent Improvement Ass'n v. National Waste Managers/Chesapeake Terrace) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forks of the Patuxent Improvement Ass'n v. National Waste Managers/Chesapeake Terrace, 148 A.3d 36, 230 Md. App. 349, 2016 Md. App. LEXIS 149 (Md. Ct. App. 2016).

Opinion

Opinion by

Kehoe, J.

This judicial review action is the latest episode of a prolonged effort by National Waste Managers/Chesapeake Terrace (“National”) to construct and operate a rubble landfill on a large tract of land near Odenton, Maryland. In 2013, National applied for a variance to extend the time period for obtaining construction permits for the project. The variance application found its way to the Anne Arundel County Board of Appeals. The Forks of the Patuxent Improvement Association, Inc. (the “Association”), as well as several individuals, opposed the variance.

Four members of the Board participated in the hearing. After the hearing, the Board was evenly divided: two members of the Board (the “Approving Members”) were in favor of granting the application and two members (the “Denying Members”) voted to deny it. The Board concluded that the evenly-divided vote constituted a denial and entered an administrative order to that effect.

National filed a petition for judicial review in the Circuit Court for Anne Arundel County. The court concluded that: (1) the evenly-divided Board decision had the effect of denying the application; (2) the court’s focus should be on the reasoning and findings of the Denying Members because their decision was dispositive on the application; and (3) the Denying Members applied erroneous standards to the evidence. The court set out its view of the appropriate legal standards, *353 vacated the Board’s decision, and remanded the matter to the Board for further proceedings consistent with its opinion.

The Association 1 appealed the court’s judgment and poses one issue, which we have re-worded:

Did the Board’s evenly-divided 2-2 vote constitute a denial of National’s application for a variance?

National filed a cross-appeal and presents three questions, which we have consolidated and re-phrased:

Did the circuit court err in vacating and remanding the Board of Appeals’ decision rather than reversing the Board’s decision and ordering the Board to approve the variance application?

As we will explain, we agree with the circuit court’s conclusions that the case must be remanded but see the relevant legal issues somewhat differently than did the circuit court and the members of the Board. Therefore, we will vacate the court’s judgment and remand this case for further proceedings consistent with this opinion.

Background

National owns a 481-acre tract of land in Anne Arundel County (the “Project Site”). In 1993, National applied for and received a special exception and variances from the Board to construct and operate a rubble landfill and a sand and gravel operation on the Project Site. The Board’s approval was affirmed by the Court of Appeals in Halle v. Crofton Civic Ass’n, 339 Md. 131, 661 A.2d 682 (1995). After obtaining the zoning approval, National had 18 months to obtain a construction permit for the project; if it failed to do so, the special exception would lapse, unless it obtained a variance for an *354 extension of time. See Anne Arundel County Code § 18-16-405. 2

In order to obtain a construction permit from the County, National needed a solid waste refuse disposal permit from the Maryland Department of the Environment (the “MDE”). The MDE’s review process for such permits consists of five phases. In summary, the phases are as follows:

1. Phase I centers on gathering basic information, such as the project’s intended objectives, location, etc. This phase also gathers and compiles existing data about the site. The MDE circulates this information to various local, State, and Federal agencies for review and comment and to determine whether the site is suitable for the intended use. See CO-MAR 26.04.07.14.
2. Phase II consists of a hydrogeological investigation. The applicant is required to identify and analyze groundwater and geological conditions on the site. This report is also sent to local, State, and Federal agencies for review and comment. See COMAR 26.04.07.15.
3. Phase III entails engineering design. This phase takes all of the information gathered, especially the hydrogeological information from Phase II, and designs a landfill with these considerations in mind. See COMAR 26.04.07.16.
*355 4. Phase IV is a review stage. The MDE uses this period to review all the information from Phases I—III to ensure that all of the statutory and regulatory requirements have been met. It then begins to prepare any and all documents it will need to present to the public on the proposed permit. During this phase, the MDE also drafts a proposed permit for the site.
5. Phase V is the public comment stage. The MDE advertises and holds a hearing on the draft permit and invites the public to submit comments on the proposal. After the public comments are received, the MDE engages in a final review, and then either issues the permit as is, issues it with modifications, or denies the permit.

National began this process in 1991, in conjunction with its then-pending application for a special exception. In 1994, however, the MDE suspended review because the County had amended its Solid Waste Management Plan to omit any reference to the Project Site. 3 Litigation between National and the County on the amendment culminated in National’s favor by means of an unreported decision of a panel of this Court in National Waste Managers, Inc. v. Anne Arundel County, No. 810, September Term, 1997, filed March 25, 1998 (“National I”). The County then took the position that National’s special exception permit had lapsed pursuant to a prior version of what is now County Code § 18-16-405. This resulted in another lawsuit, which was also finally resolved in National’s favor by our decision in National Waste Managers, Inc. v. Anne Arundel County, 135 Md.App. 585, 763 A.2d 264 (2000) (“National II”). 4 In National II, we held that the 18-month time limit in what is now County Code § 18-16-405 was tolled during the pendency of the litigation between National and the County. Id. at 614, 763 A.2d 264.

*356 In 2001, MDE resumed its process of reviewing National’s proposal. MDE was unable to complete its review within the 18-month period set out in County Code § 18-16-405. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Waste Managers, Inc. v. Forks of the Patuxent Improvement Ass'n
162 A.3d 874 (Court of Appeals of Maryland, 2017)
Priester v. Baltimore County
157 A.3d 301 (Court of Special Appeals of Maryland, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
148 A.3d 36, 230 Md. App. 349, 2016 Md. App. LEXIS 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forks-of-the-patuxent-improvement-assn-v-national-waste-mdctspecapp-2016.