FOPCO, Inc.

CourtUnited States Bankruptcy Court, D. Hawaii
DecidedJanuary 18, 2022
Docket18-01084
StatusUnknown

This text of FOPCO, Inc. (FOPCO, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FOPCO, Inc., (Haw. 2022).

Opinion

Date Signed: January 18, 2022 ky & XD SO ORDERED.

ety Robert J. Faris ier OF ge United States Bankruptcy Judge

UNITED STATES BANKRUPTCY COURT

DISTRICT OF HAWAII

In re: Case No. 18-01084 Chapter 7 FOPCO, INC.,

Debtor. Dkt. No. 192

FINDINGS OF FACT, CONCLUSIONS OF LAW, AND ORDER ON OBJECTION TO CLAIM OF NAN, INC.

Dennis C. McElrath objected to the proof of claim filed by Nan, Inc. An

evidentiary hearing on the objection was held on November 9-10, 2021.

Richard E. Wilson appeared for Nan, Inc., and Jordan S. Blask, Jillian Nolan

Snider, Daniel F. Edwards, Sloane B. O’Donnell, and Johnathan C. Bolton

appeared for Mr. McElrath.

Based on the evidence, I make the following FINDINGS OF FACT: A. The MACC

In 2009, the United States Naval Facilities Division (“NAVFAC”) solicited bids from small contractors as part of a $200,000,000.00 Design-

Build/Design-Bid-Build HubZone Multiple Award Construction Contract (“MACC”). A MACC is a type of government contract where the government

establishes a short list of prequalified contractors who may bid on individual jobs, called task orders.

Contractors certified by the United States Small Business Administration as “HUBZone contractors” were given certain preferences

under the MACC. At the time10 both FOPCO and Nan operated as building contractors, FOPCO was certified as a HUBZone contractor, and Nan was not.

B. The Agreements between FOPCO and Nan Before NAVFAC decided which contractors would be prequalified

under the MACC, FOPCO and Nan entered into a Teaming Agreement, dated August 3, 2010 (Ex. A-2). The Teaming Agreement provides that, if NAVFAC awarded a prime contract to FOPCO, Nan would “perform [FOPCO’s] scope

of work under the Prime Contract,” “assume all duties, obligations, and responsibilities” of FOPCO under the prime contract and related agreements

between FOPCO and NAVFAC, and “obtain, pay for, furnish, and provide all labor, services, materials . . . and other facilities of every kind and description

required for the prompt and efficient performance of all of the Work . . . .” Nan also agreed to provide all bonding required by NAVFAC. Thus, the Teaming

Agreement shifted to Nan essentially all of FOPCO’s obligations under the prime contract with NAVFAC.

After NAVFAC qualified FOPCO to bid for task orders under the MACC, Nan and FOPCO entered into two more agreements. These

agreements “further defined” the parties’ relationship but did not supersede the Teaming Agreement.

The first such agreement, entitled “Agreement” and referred to as the “Profit and Coefficient Agreement” (Ex. A-1), includes several relevant

provisions. (1) The parties agreed to enter into a master subcontract agreement applicable to all awarded task orders. (2) The parties agreed to split any profits on each completed task order, with forty percent payable to FOPCO and sixty

percent to Nan. (3) If the parties realized a loss on any task order, the loss would be offset against and recoverable from the profits on any other “open

and on-going” task order, but not against profits from any completed task order, and Nan would bear any remaining losses. (4) All estimates and bids

submitted to NAVFAC and “all material decisions necessary of execution of each Task Order” would be made by mutual agreement. But if the parties

could not agree, Nan had the final say based on Nan’s view of what was “in the best interest of the teaming arrangement.” (5) Each party was entitled to a

“coefficient” to cover overhead and similar costs. FOPCO’s coefficient was 1% of each payment and Nan’s was 2.5%. (6) FOPCO had the option to “bid, bond,

and self-perform” specific task orders, in which case Nan would not share any profits or bear any losses.

The second agreement is entitled “Subcontractor Agreement” and referred to as the “Master Subcontract” (Ex. A-3). The Master Subcontract

states that it “shall apply to all Task Orders under the Prime Contract excluding those Task Orders that are bid, bonded and performed by [FOPCO] independently.”

The parties intended that all three agreements, taken together, would govern their relationship.

Both parties offered testimony that they did not intend to form a joint venture. But the three agreements created a relationship that was similar to a

joint venture in many respects: the parties agreed to work together to develop the bids to NAVFAC and to carry out the work, with Nan having the final say

if the parties could not agree; and they agreed on an allocation of profits and losses. The arrangement is also different from the typical prime

contractor/subcontractor relationship, because usually the prime contractor controls the subcontractor’s work, while the Profit and Coefficient Agreement

gave the subcontractor Nan the final say on many important matters. FOPCO and Nan worked together on thirty-two task orders. (In

addition, FOPCO self-performed nine task orders without Nan’s involvement.) As to seventeen of those task orders, FOPCO and Nan

completed the work, NAVFAC paid what it owed, and FOPCO and Nan resolved the division of the costs and profits. As to the remaining fifteen task orders, the parties have completed the work and NAVFAC has paid FOPCO

the full contract price, but Nan and FOPCO never agreed on the division of the proceeds and FOPCO has not paid the full amount that Nan claims.

C. Change Orders Mr. McElrath contends that much of Nan’s claim must be disallowed

because Nan failed to process formal change orders under the Master Subcontract. The evidence does not bear out this contention.

The Master Subcontract is a standard form contemplating that the subcontractor would propose a firm fixed price for a specified scope of work,

and that the price or scope could change only pursuant to a formal change order process. But the Master Subcontract does not specify either the scope of

or price for Nan’s work. There is a space for a description of the scope of Nan’s work. The parties left this blank, presumably because the scope of the job

could not be known until a particular task order was awarded, and because the Teaming Agreement required Nan to do all work under the task order.

Similarly, the Master Subcontract refers to a “Subcontract Amount” and a “Schedule of Prices,” but it does not define or specify either of these items. Mr. McElrath points out that Nan provided estimates to FOPCO that

FOPCO used to bid for task orders. He argues that these estimates should be treated as Nan’s firm fixed price for the relevant task order under the Master

Subcontract. There is no evidence that either FOPCO or Nan intended at the time that the estimates would be treated in that fashion. Further, treating the

estimates this way disregards the fact that, under the Profit and Coefficient Agreement, the parties agreed to split the profits on each task order. In a

typical prime contractor/subcontractor relationship, the subcontractor’s bid to the prime contractor includes the subcontractor’s profit but does not account

for the prime contractor’s profit. However, FOPCO took Nan’s estimates and simply included them in its bid to NAVFAC. Nan’s estimates must have

included a profit for both FOPCO and Nan. Treating Nan’s estimates as a firm fixed price under the Master Subcontract disregards the fact that those

estimates must have included, not only Nan’s profit, but also FOPCO’s profit share.

Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
FOPCO, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/fopco-inc-hib-2022.