Fonalledas v. United States

107 F. Supp. 1019, 123 Ct. Cl. 483
CourtUnited States Court of Claims
DecidedNovember 4, 1952
Docket47703-47703-C
StatusPublished
Cited by17 cases

This text of 107 F. Supp. 1019 (Fonalledas v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fonalledas v. United States, 107 F. Supp. 1019, 123 Ct. Cl. 483 (cc 1952).

Opinion

MADDEN, Judge.

These three actions were brought to recover for the alleged talcing of lands in Puerto Rico belonging to the plaintiffs. The actions were consolidated for the purposes of the trial, and this opinion will cover all three actions.

An Act of Congress of October 17, 1940, 54 Stat. 1198-1199, authorized the dredging of an additional channel in San Juan Harbor, Puerto Rico. The Act provided that the project should be prosecuted subject to the conditions set forth in H.Doc.No.364, 76th Cong., 1st sess. One of those conditions was :■

“that local interests furnish, free of cost to the United States, when and as required, all lands, easements, and rights of way and spoil disposal areas for the initial work and for subsequent maintenance, and hold and save the United States free from claims for damages resulting from the improvement.”

*1021 The Government of Puerto Rico conveyed to the United States two areas for the placing of spoil. The conveyance provided that these areas were to revert to the Government of Puerto Rico when" they were no longer necessary for national defense.

The Secretary of War made a contract with the Standard Dredging Corporation for the dredging of the channel. Of the two spoil areas specified in the contract, spoil area A was immediately north of the lands of the plaintiffs. It was an area of mangrove swamps and submerged lands located, on the eastern shore of San Juan Bay. Spoil area A was mapped by the Navy in accordance with the description contained in the deed from the Government of Puerto Rico'. The Standard Dredging Corporation, as it was required by the contract to do, constructed sand bag dikes on the east and west sides of the area, but none on the south side, where the spoil area adjoined the lands of the plaintiffs.

As the dredging of the harbor proceeded, the mud, silt and salt water, dredged from the bay and carried by a pipe line from the dredges to the center' of the spoil1 area, raised the level of the surface in thé center of the area and flowed off in all directions. Finally it raised the level of the surface in the area above that of the plaintiffs’ lands to the south and began to flow over those lands. The plaintiffs protested in writing to various Government officials and finally brought a suit in the United States District Court to enjoin the Standard Dredging Corporation from continuing its, harmful operation. Prior to the return day of the suit, counsel for the United States advised counsel for the plaintiffs that dredging operations which would overflow the plaintiffs’ lands would stop, that a drainage canal would be dug to drain off the salt water already accumulated on the plaintiffs’ lands and afford future . drainage. The canal was to run in a general east-west direction and a part of it would have to. pass through the plaintiffs’ lands. The plaintiffs’ counsel gave the Government a letter of authorization to construct the canal. That letter, which is quoted in finding 11, contained this paragraph:

“It is' expressly understood that this permit is granted without prejudice to any and all rights of our clients, or, in other words, it is expressly understood that our clients waive no rights whatsoever by reason of this permit.”

The canal was thereupon constructed and the injunction suit was dismissed.

As shown in the findings, lands of the plaintiffs both north and south of the canal were covered with spoil, those to the north, of course, being buried the deepest. The digging of the canal, which' was some 14 meters wide, not only submerged the land occupied by the canal, but made the plaintiffs’ lands north of the canal inaccessible, and they will remain so until a bridge is built over the canal. The lands were pas■ture- lands, worth about $650 per cuerda, on which plaintiffs maintained, in 1941, one . 'thousand head of cattle. A cuerda is ninety-seven one hundredths of an acre.

Prior to the'placing of the dredged materials on the spoil area, the lands of the plaintiffs had a natural drainage into and through the mangrove swamp into the bay. This drainage was permanently blocked by thé deposit of the spoil. But the canal will afford drainage to the lands, if ditches are dug to the canal.

.Possible methods of reclaiming the plaintiffs’ lands from the effects of their permeation with salt are described in finding 23. The only method practically feasible is that of ditching, manuring, and waiting for the salt to be washed out and drained away by .rainfall. Expert testimony, and the experience of the plaintiffs themselves in reclaiming their lands south of the canal, indicate that lands so affected can be reclaimed in about four years. The lands north of the canal were much more seriously affected and it will take about twelve years to reclaim them. The actual expense of reclaiming the lands south of the canal, and the probable expense of reclaiming those north of the canal, is shown in finding 28.

The Government urges that the history recited above does.not spell out a taking for which the plaintiffs may recover in this court under the Tucker Act, 28 U.S.C.A. § *1022 1491. It says that the provision in the statute authorizing the dredging that local interests furnish the spoil area negatives any authority on the part of agents of the United States to take land for the project. Therefore, it says, whatever the Government did, through the agency of the Standard Dredging Company or others beyond the lands furnished by the Government of Puerto Rico was a tort, over which this court has no jurisdiction and for which, we suppose, no right of action in any court existed at the time of the events here involved.

As we have pointed out elsewhere, earlier decisions required that, in order for a talcing to be the basis for a suit under the Tucker Act, the circumstances of the taking had to be such as to create a contract implied in fact 'by the Government, to pay for the thing taken. This doctrine in effect read out of the Tucker Act the provision added by that Act giving this court jurisdiction of “claims founded upon the Constitution”. But recent authority gives that provision full effect. United States v. Causby, 328 U.S. 256, 267, 66 S.Ct. 1062, 90 L.Ed. 1206; United States v. Dickinson, 331 U.S. 745, 748, 67 S.Ct. 1382, 91 L.Ed. 1789. The problem is discussed in Foster v. United States, 98 F.Supp. 349, 120 Ct.Cl. 93, and in Cotton Land Company v. United States, 75 F.Supp. 232, 109 Ct.Cl. 816, 829 ff. We think, therefore, that if the Government, through the agency of the dredging contractor took the lands of the plaintiffs, the .absence of statutory authority to do so would not put the citizen thus imposed upon beyond reach of relief. In addition, we do not construe the language of the document referred to in the authorizing statute as disabling the Government from doing what might be necessary to complete the projected work, but rather as requiring that the ■Government of Puerto Rico indemnify it .against claims for damages resulting from the doing of the work. What rights the ■Government may have against the Government of Puerto Rico, and how it might enforce them, we do not consider.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hansen v. United States
65 Fed. Cl. 76 (Federal Claims, 2005)
Linda Vaizburd and Arkady Vaizburd v. United States
384 F.3d 1278 (Federal Circuit, 2004)
Vaizburd v. United States
Federal Circuit, 2004
Janowsky v. United States
37 Cont. Cas. Fed. 76,148 (Court of Claims, 1991)
Berenholz v. United States
1 Cl. Ct. 620 (Court of Claims, 1982)
Tektronix, Inc. v. United States
552 F.2d 343 (Court of Claims, 1977)
Castro v. United States
500 F.2d 436 (Court of Claims, 1974)
Anderson v. United States
174 F. Supp. 945 (Court of Claims, 1959)
Bydlon v. United States
175 F. Supp. 891 (Court of Claims, 1959)
Columbia Basin Orchard v. United States
132 F. Supp. 707 (Court of Claims, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
107 F. Supp. 1019, 123 Ct. Cl. 483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fonalledas-v-united-states-cc-1952.