Florida State Turnpike Authority v. Michael Baker, Jr., Inc.

156 So. 2d 198
CourtDistrict Court of Appeal of Florida
DecidedAugust 30, 1963
DocketNos. 3680, 3700
StatusPublished
Cited by5 cases

This text of 156 So. 2d 198 (Florida State Turnpike Authority v. Michael Baker, Jr., Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida State Turnpike Authority v. Michael Baker, Jr., Inc., 156 So. 2d 198 (Fla. Ct. App. 1963).

Opinion

TROWBRIDGE, C. PFEIFFER, Associate Judge.

The Plaintiff below, an engineering firm, filed suit against the Defendant below, the Florida State Turnpike Authority (Hereinafter referred to as the Authority) for breach of contract. A Final Judgment and successive nunc pro tunc final judgments for the engineering firm -were appealed by the Authority and ordered consolidated by this Court.

Suit was instituted by the Plaintiff in January 1961. In April 1962, the cause had reached the posture in the lower court which is significant on this appeal. At that time, the cause stood on an Amended Complaint, an Answer thereto, the Answers to Interrogatories by Defendant Hammer and Plaintiff’s president, a copy of the subject contract, and a certain trust indenture of [200]*200the Authority. There was before the court Defendants’ motion for decree on the pleadings and motion for summary judgment and Plaintiff’s motion for summary judgment.

Upon hearing, the court, on April 30, 1962, denied both of Defendants’ motions and granted Plaintiff a partial summary judgment as to liability. The question of damages was tried by a jury and a judgment for $72,504.52 was entered consequent upon the verdict for the Plaintiff.

The points presented on appeal are all directed to alleged error in the denial of Defendants’ motions and the entry of the partial summary judgment for Plaintiff on the issue of liability.

The pleadings and other papers before the court at the time it granted the partial summary judgment disclose the following facts: In February 1956, the engineering firm entered into a contract in writing with the Authority wherein it was agreed that the Plaintiff was to perform certain comprehensive engineering services subject to the terms and conditions set forth in the contract. In June of 1956, the Authority assigned to the Plaintiff additional work which was designated as a part of Section 16. The Plaintiff entered upon the performance assigned and expended considerable money thereon until the events occurred which brought about this suit. Plaintiff alleged that it “has duly performed all the conditions of said contract on its part at the time and in the manner therein specified, except insofar as Plaintiff has been prevented from performing by the acts or failure to act of the Defendants, and Plaintiff on its part remains ready and willing to perform all the obligations of said contract as originally agreed.” According to the contract, the Plaintiff was to be paid from funds as follows:

“10. SOURCE OF FEE PAYMENTS — The Authority anticipates that it will finance construction of the project by issue and sale of revenue bonds. To date, the Authority has not issued any such revenue bond. It is expressly understood that all payments for Section Engineer services performed under this Agreement shall be made solely from the proceeds of revenue bonds when sold by the Authority to finance construction of Sunshine State Parkway, Project No. 2., Fort Pierce to Jacksonville, or from other funds, if any, which may be or which may have been legally made available to the Authority for such purpose, and the Authority shall be under no liability under this Agreement to make payments to the Section Engineer from any other source. The payment of said fees is contingent upon the availability of funds derived from the proceeds of said revenue bonds, or from such other funds as are mentioned in the preceding sentence, and the liability of the Authority is limited thereto.”

During the course of the work the Authority made a partial payment to the Plaintiff in the amount of $Z3,000.00. No further payments were made by the1 Authority and, after repeated requests by the Plaintiff for payment, suit was instituted for breach of contract.

The Authority in its answer denied that the Plaintiff had performed all of the conditions of the contract and set forth the affirmative defense that under Section 10 of the contract the payment of fees was contingent upon funds derived from the sale of revenue bonds to finance construction of the Sunshine State Parkway, Project No. 2, Fort Pierce to Jacksonville; that the Authority has not sold and is not now anticipating selling any revenue bonds to finance the construction of an extension of the Sunshine State Parkway from Fort Pierce to Jacksonville; and that, therefore, under Section 10 of the contract, which is the basis of this suit, there is no liability on the part of the Authority and no justiciable cause on which the Court could render a judgment.

The Plaintiff directed certain interrogatories to John M. Hammer, Chairman of the Authority, who answered under oath that [201]*201the Authority is not now anticipating- selling any revenue bonds to finance the extension of the Sunshine State Parkway from Fort Pierce to J acksonville, but admitted that his answer was based solely upon the fact that any revenue bonds which were anticipated to be sold would not carry the tumike any further north than Ocala or Wildwood rather than going all the way to Jacksonville. He testified that the bonds which had been sold to finance the extension of the turnpike covered an area which either paralleled or is directly upon or adjacent to Section 16 of Project No. 2, which had previously been contracted to the Plaintiff. He further testified that the Authority presently had under contract a man to do the engineering for the equivalent of Section 16, Project No. 2, who was the superintendent of the Plaintiff during the time it was likewise working on Section 16, Project 2. In response to a question as to why the Authority had completely disregarded the contract with the Plaintiff, Mr. Hammer answered :

"A. 20. Shortly after I became Chairman I was informed by the traffic and earnings engineers that it was not feasible to extend the Turnpike from Fort Pierce to Jacksonville, and therefore the Authority abandoned the project that was formerly under way by the prior administration. I considered all work done under that project as part of it and therefore abandoned. It was my understanding that there was no liability under any of the contracts of the Section Engineers because they were contingent contracts based upon the Authority’s selling the bonds to finance the project for which they were working. It was my belief at that time, and it is my belief now, that these engineering firms took and did any work, on a theory that they would not be paid unless the bonds were sold for that project. Therefore, I feel that all the contracts were in nullity when the project was determined unfeasible.”
Mr. Hammer also testified that it is still not clear that the turnpike will not in fact go to Jacksonville, while at the same time he stated that he cannot truthfully say that the Sunshine State Parkway will ultimately end in Jacksonville, as the final decision on that matter has not been made by the Authority. He stated that the preliminary alignment for the location of Section 16 of Project No. 2 prepared by the Plaintiff was approved by the Authority, that the Plaintiff had notified the Authority on one or more occasions of its willingness to complete the contract, and that the Authority had never replied to any such notifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mainor v. Hobbie
238 So. 2d 499 (District Court of Appeal of Florida, 1970)
Hart v. Tucker
237 So. 2d 772 (District Court of Appeal of Florida, 1970)
Starkenstein v. City of Daytona Beach
229 So. 2d 274 (District Court of Appeal of Florida, 1969)
First Bank & Trust Co. v. Duval Development Co.
229 So. 2d 299 (District Court of Appeal of Florida, 1969)
Florida State Turnpike Authority v. Michael Baker, Inc.
159 So. 2d 650 (Supreme Court of Florida, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
156 So. 2d 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-state-turnpike-authority-v-michael-baker-jr-inc-fladistctapp-1963.