Florida Rock Industries, Inc. v. United States

21 Cl. Ct. 161, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21201, 31 ERC (BNA) 1835, 1990 U.S. Claims LEXIS 281, 1990 WL 103774
CourtUnited States Court of Claims
DecidedJuly 23, 1990
DocketNo. 266-82L
StatusPublished
Cited by26 cases

This text of 21 Cl. Ct. 161 (Florida Rock Industries, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Rock Industries, Inc. v. United States, 21 Cl. Ct. 161, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21201, 31 ERC (BNA) 1835, 1990 U.S. Claims LEXIS 281, 1990 WL 103774 (cc 1990).

Opinion

OPINION

SMITH, Chief Judge.

This regulatory taking claim is before the court on remand from the United States Court of Appeals for the Federal Circuit, which affirmed in part and vacated in part the opinion of the first trial court.1 After considering evidence presented at the original trial and additional evidence presented after remand, the court finds that the Army Corps of Engineers’ denial of a permit to fill plaintiff’s property resulted in a taking, and accordingly awards just compensation as mandated by the fifth amendment.

FACTS

The facts underlying this case have been succinctly set forth by the appellate court, [164]*164Florida Rock Indus. v. United States, 791 F.2d 893, 895-96 (Fed.Cir.1986), and are recited briefly below for the reader’s convenience. The court relies on the findings of the district engineer of the Army Corps of Engineers (the Corps), as did the Federal Circuit.

Plaintiff, a large-scale miner of limestone, purchased a tract of 1,560 acres in Dade County, Florida in 1972, paying $2,964,000. The sole purpose for the acquisition was the mining of limestone; no other use or sale was ever considered. Because of a slump in the construction industry in South Florida, plaintiff did not attempt to mine the subject property until 1978, nor did it attempt to put the property to other use.

Shortly after the plaintiff's acquisition of the property but prior to the commencement of mining in 1978, Congress passed Public Law 95-217, 91 Stat. 1567 (Dec. 27, 1977), amending the Clean Water Act, 33 U.S.C. § 1251(a) (1988) and expanding the jurisdiction of the Corps to regulate activity affecting navigable waters. At the same time, § 404 of this law established a mechanism for applying for permits to discharge dredged or fill material into waters covered by the Clean Water Act. 33 U.S.C. § 1344 (1988).

Upon learning of plaintiff’s mining activities, and in the belief that a § 404 permit was required, the Corps issued a cease and desist order, with which plaintiff complied. Plaintiff then applied to the Corps for a permit which would enable it to mine 98 acres. This would have fulfilled its needs for a three-year period. Although plaintiff would have preferred a permit to mine the entire 1,560 acre tract, the Corps had indicated it would consider applications covering no more than a three-year need.

On October 2, 1980, the Corps denied plaintiff’s application covering the 98 acres, finding the permit would not be in the public interest. No appeal was taken under the Administrative Procedure Act, 5 U.S.C. §§ 701, ff (1988), and no further applications were submitted.2

PRIOR PROCEEDINGS

The history of the prior proceedings in this case has been laid out at length in Senior Judge Nichols’ opinion for the Federal Circuit, 791 F.2d at 896-97, and is summarized briefly below.

Following the district engineer’s denial of plaintiff’s permit application, plaintiff filed suit in the Claims Court, seeking just compensation for a regulatory taking, under the fifth amendment. The liability and damages aspects were bifurcated, and separate trials were held before Chief Judge Kozinski. At the conclusion of the trial on liability, the Chief Judge delivered an oral opinion, which later was modified and memorialized in a written opinion. Florida Rock Indus. v. United States, 8 Cl.Ct. 160 (1985). An order on valuation was issued after a trial on damages.

Chief Judge Kozinski found that, contrary to the Corps’ finding, the activities proposed by plaintiff would not have polluted the water; he also found that there was no economically viable use for the property other than as a site for mining limestone. Based on these findings, he held that the government’s action had resulted in a taking requiring just compensation. In fixing the amount of compensation to which plaintiff was entitled, Chief Judge Kozinski was persuaded by plaintiff’s argument that the proper measure of damages was the immediate use value that had been lost, and in a subsequent order determined that the 98 acres in dispute were worth $10,500 per acre, or $1,029,000 for the tract.3

[165]*165The Federal Circuit affirmed Chief Judge Kozinski’s finding that the most that could have been taken was the 98-acre parcel, but vacated much of the remainder of the opinion and remanded for further proceedings. In doing so, the Federal Circuit Court noted:

The trial judge failed to apply the evidence in a manner correct in all respects to determine whether he had an actual instance of a taking before him____ We remand for determination of the taking question according to right principles, as it would be improper for us to constitute ourselves fact finders and weigh the evidence ourselves.

791 F.2d at 894.

In addition to these general principles, the Federal Circuit found several aspects of the trial court’s opinion contrary to the law. In particular, the Federal Circuit held that the trial court’s inquiry into whether the proposed activity actually would have polluted the waters was an improper exercise of jurisdiction over a matter appropriate for review only by a district court under the Administrative Procedure Act. Id. at 898.

The appellate court also disapproved of the trial court’s method of valuing the property potentially taken by looking at an immediate use value, as opposed to a fair market value. Specifically, the court ruled that it was clear error for the trial judge to exclude from consideration defendant’s evidence of a potential investment market for the property. The court stated:

Indeed, if there is found to exist a solid and adequate fair market value (for the 98 acres) which Florida Rock could have obtained from others for that property, that would be a sufficient remaining use of the property to forestall a determination that a taking had occurred or that any just compensation had to be paid by the government.

Id. at 903.

Defendant for the most part is correct that the Federal Circuit vacated Chief Judge Kozinski’s findings. However, there are at least two exceptions. The Federal Circuit expressly affirmed the trial court’s determination that the 98-acre parcel is the only property in dispute. Additionally, the appellate court did not disturb his finding that the pre-“taking” value of the property was $10,500 per acre, and this court must accept that figure for determining both liability and damages.4 See, e.g., Fidelity & Deposit Co. v. USAFORM Hail Pool, 523 F.2d 744, 759 (5th Cir.1975), cert. denied, 425 U.S. 950, 96 S.Ct. 1725, 48 L.Ed.2d 194 (1976) (a trial court, when conducting proceedings following a remand, cannot disregard its previous factual findings if those findings were not disturbed on appeal). The court disagrees with defendant that no further evidence may be introduced on remand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Flowers
423 F. Supp. 2d 1273 (S.D. Florida, 2006)
El-Shifa Pharmaceutical Industries Co. v. United States
55 Fed. Cl. 751 (Federal Claims, 2003)
Florida Rock Industries, Inc. v. United States
45 Fed. Cl. 21 (Federal Claims, 1999)
Walcek v. United States
44 Fed. Cl. 462 (Federal Claims, 1999)
Palm Beach Isles Associates v. United States
42 Fed. Cl. 340 (Federal Claims, 1998)
Osprey Pacific Corp. v. United States
41 Fed. Cl. 150 (Federal Claims, 1998)
Good v. United States
39 Fed. Cl. 81 (Federal Claims, 1997)
Store Safe Redlands Associates v. United States
35 Fed. Cl. 726 (Federal Claims, 1996)
Moore v. United States
943 F. Supp. 603 (E.D. Virginia, 1996)
Hage v. United States
35 Fed. Cl. 147 (Federal Claims, 1996)
City National Bank v. United States
33 Fed. Cl. 759 (Federal Claims, 1995)
Florida Rock Industries, Inc. v. United States
115 S. Ct. 898 (Supreme Court, 1995)
Florida Rock Industries, Inc. v. United States
18 F.3d 1560 (Federal Circuit, 1994)
Bowles v. United States
31 Fed. Cl. 37 (Federal Claims, 1994)
City National Bank of Miami v. United States
30 Fed. Cl. 715 (Federal Claims, 1994)
West Jefferson Levee Dist. v. Coast Quality Const. Corp.
620 So. 2d 319 (Louisiana Court of Appeal, 1993)
Perry v. United States
28 Fed. Cl. 82 (Federal Claims, 1993)
Formanek v. United States
26 Cl. Ct. 332 (Court of Claims, 1992)
Bowles v. United States
23 Cl. Ct. 443 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
21 Cl. Ct. 161, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21201, 31 ERC (BNA) 1835, 1990 U.S. Claims LEXIS 281, 1990 WL 103774, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-rock-industries-inc-v-united-states-cc-1990.