Florida Lemark Corporation v. Secretary, U.S. Department of Labor

634 F. App'x 681
CourtCourt of Appeals for the Eleventh Circuit
DecidedDecember 14, 2015
Docket15-10445
StatusUnpublished
Cited by1 cases

This text of 634 F. App'x 681 (Florida Lemark Corporation v. Secretary, U.S. Department of Labor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Lemark Corporation v. Secretary, U.S. Department of Labor, 634 F. App'x 681 (11th Cir. 2015).

Opinion

PER CURIAM:

This is a petition for review of a final order of the Occupational Safety and Health Review Commission (“Commission”) finding that Petitioner Florida Le-mark Corporation (“Florida Lemark”) violated its general duty to keep its worksite free of hazards. On appeal, Florida Le-mark contends that the finding of a work-site hazard is not supported by substantial evidence in the record. Florida Lemark also argues that it did not have constructive knowledge of the hazard, pursuant to this Court’s decision in ComTmn Group, Inc. v. U.S. Department of Labor, 722 F.3d 1304 (11th Cir.2013), because the hazard was created by supervisor misconduct. After careful review, we deny the petition and affirm the Commission’s decision.

I.

This case arises out of a tragic incident involving the partial collapse of a nearly finished, six-story parking- garage under construction on Miami Dade College’s campus in Doral, Florida, on October 10, 2012. 1 The collapse killed four employees of three different employers and injured several others, including a Florida Lemark employee. It is undisputed that the collapse occurred due to catastrophic structural failure of one of the garage’s supporting columns.

The garage was a “precast” structure, meaning the structural pieces of the building were manufactured off-site and erected on-site. After the foundation was poured *683 on-site, precast columns were moved into position on the foundation by a crane. The columns were placed on metal shims— small pieces of metal used to adjust the elevation of the column—and then bolted to the foundation with four anchor bolts through a metal base plate embedded in the bottom of the column. This process left a two- to three-inch gap between the bottom of the column and the foundation. The gap was then filled with grout cement, which has a greater weight-bearing capacity than concrete. The shim stacks and anchor bolts could support the weight of only the column itself, but were insufficient to support the weight of the other structural pieces placed on the column later in construction. To address this situation, the grout was to allow the column to transfer weight more effectively to the foundation and to hold the subsequent loads. The engineering drawings for the parking garage required grout to be placed no later than forty-eight hours after each column was erected.

The construction of the parking garage was managed by Ajax Building Corp. (“Ajax”). Other companies were hired to. complete specific parts of the project, including (a) MEP Structural Engineering and Inspection, Inc. (“MEP”), which inspected construction and ensured compliance with construction plans; (b) Solar Erectors, Inc. (“Solar”), which erected the precast pieces at the construction site; and (c) Florida Lemark, the petitioner in this case, which grouted the various pieces that made up the structure.

Following the collapse of the parking garage, the Occupational Safety and Health Administration (“OSHA”) investigated the worksite and then issued Florida Lemark, among others, a citation alleging that it failed to keep its worksite free- of hazards. OSHA specifically alleged a “serious” violation of the “general duty clause,” which requires employers to keep their worksites “free from recognized hazards that are causing or are likely to cause death or serious physical harm” to their employees. See 29 U.S.C. § 654(a)(1). According to the citation, Florida Lemark exposed its employees to a recognized hazard—being struck by and caught in between collapsing pre-cast structural members—by not performing grouting on the bases of two columns, identified as columns “B3” and “A3.3.”

II.

The Occupational Safety and Health Act (the “Act”), 29 U.S.C. § 651, et seq., gives the Secretary of Labor (“Secretary”), and by extension OSHA, the authority to commence enforcement actions against employers to ensure compliance with the Act. The overarching purpose of the Act is “to assure so far as possible every working man and woman in the Nation safe and healthful working conditions.” 29 U.S.C. § 651(b). Once OSHA issues a. citation to an employer, the employer may contest the citation and request a hearing before an administrative law judge (“ALJ”). See generally ComTran Grp., Inc., 722 F.3d at 1306-07 (explaining the statutory and regulatory scheme under the Act).

Florida Lemark contested its citation, and an ALJ held an evidentiary hearing to resolve the contest. The ALJ heard testimony from OSHA investigators and various persons involved in the construction of the parking garage. Notably, the ALJ heard from the following persons: Mohammad Ayub, who headed OSHA’s investigation into the collapse; MEP’s director of engineering, who testified about MEP’s inspection records; and Ajax’s director of risk management, who indicated that an engineering firm hired by Ajax found evidence of grout under column B3.

*684 Ayub, an expert in the field of forensic structural engineering, testified about his investigation of the worksite for OSHA and his conclusions that columns B3 and A3.3 had not been grouted. He explained that the lack of grout under column B3 led to that column’s failure and the partial collapse. He also stated that the lack of grout under column A3.3 posed a similar risk of collapse, though it was not the cause of the collapse in this case.

MEP’s director of engineering testified about MEP’s inspection records, which indicated that MEP inspected column B3 after it was erected on September 13, 2012. The report prepared for that inspection noted that grouting would be inspected at a future date, which meant, according to the director, that grout was “not present” at the time of the inspection. The director also testified that he could find no inspection report showing that column B3 had been grouted. .

Ajax’s director of risk management, Marc Reeves, testified that he was privy to emails discussing the work of an engineering firm that Ajax had hired to investigate the collapse. According to Reeves, the engineering firm’s testing had indicated the presence of grout under column B3. The firm purportedly determined that the grout had a high water content, which potentially could have caused the collapse. The purported engineering report was not introduced at the hearing, nor did someone with the engineering firm testify about the report.

Following the hearing, the ALJ issued a decision affirming the citation and assessing a penalty of $6,300.00. The ALJ conducted a five-step analysis to determine whether the Secretary had met its burden of showing a violation of the general duty clause. First, the ALJ found that an activity or condition at the site constituted a “hazard” under the Act. Crediting Ayub’s testimony, the ALJ found that the Secretary had proved by a preponderance of the evidence that columns B3 and A3.3 had not been grouted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
634 F. App'x 681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-lemark-corporation-v-secretary-us-department-of-labor-ca11-2015.