Floor and Decor Outlets of America, Inc. v. Oregon Worsted Company

CourtDistrict Court, D. Oregon
DecidedSeptember 26, 2025
Docket3:24-cv-01262
StatusUnknown

This text of Floor and Decor Outlets of America, Inc. v. Oregon Worsted Company (Floor and Decor Outlets of America, Inc. v. Oregon Worsted Company) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Floor and Decor Outlets of America, Inc. v. Oregon Worsted Company, (D. Or. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF OREGON

FLOOR AND DECOR OUTLETS OF AMERICA, Case No.: 3:24-cv-01262-AN INC.,

Plaintiff, v. OPINION AND ORDER

OREGON WORSTED COMPANY,

Defendant.

Plaintiff Floor and Decor Outlets of America, Inc. filed this action against defendant Oregon Worsted Company on August 2, 2024, alleging claims for breach of contract, breach of the covenant of good faith and fair dealing, and declaratory judgment. Defendant filed its answer on September 6, 2024, alleging counterclaims for express and implied breach of contract and declaratory judgment. On September 27, 2024, plaintiff filed a partial motion to dismiss, seeking to dismiss defendant's counterclaims. After reviewing the parties' pleadings, the Court finds that oral argument will not help resolve this matter. Local R. 7-1(d). For the reasons set forth below, plaintiff's motion is GRANTED. All of defendant's rent-related counterclaims are DISMISSED with prejudice and without leave to amend. Defendant's allegations as to waiver and estoppel are DISMISSED without prejudice. Defendant's remaining counterclaims survive, as outlined in this Opinion and Order. LEGAL STANDARD Courts apply the same standard under the Federal Rules of Civil Procedure when evaluating the sufficiency of a counterclaim. See, e.g., Voltage Pictures, LLC v. Blake, No. 3:14-cv-01875-AC, 2015 WL 9272880, at *2 (D. Or. Dec. 17, 2015). Under Rule 12(b)(6), a motion to dismiss for failure to state a claim may be granted only when there is no cognizable legal theory to support the claim or when the complaint lacks sufficient factual allegations to state a facially plausible claim for relief. Shroyer v. New Cingular Wireless Servs., Inc., 622 F.3d 1035, 1041 (9th Cir. 2010). In evaluating the sufficiency of a complaint's factual allegations, the court must accept as true all well-pleaded material facts alleged in the complaint and construe them in the light most favorable to the non-moving party. Wilson v. Hewlett- Packard Co., 668 F.3d 1136, 1140 (9th Cir. 2012); Daniels-Hall v. Nat'l Educ. Ass'n, 629 F.3d 992, 998 (9th Cir. 2010). To be entitled to a presumption of truth, allegations in a complaint "may not simply recite the elements of a cause of action, but must contain sufficient allegations of underlying facts to give fair notice and to enable the opposing party to defend itself effectively." Starr v. Baca, 652 F.3d 1202, 1216 (9th Cir. 2011). The court must draw all reasonable inference from the factual allegations in favor of the plaintiff. Newcal Indus. v. Ikon Office Sol., 513 F.3d 1038, 1043 n.2 (9th Cir. 2008). The court need not, however, credit a plaintiff's legal conclusions that are couched as factual allegations. Ashcroft v. Iqbal, 556 U.S. 662, 678-79 (2009). A complaint must contain sufficient factual allegations to "plausibly suggest an entitlement to relief, such that it is not unfair to require the opposing party to be subjected to the expense of discovery and continued litigation." Starr, 652 F.3d at 1216. "A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged." Iqbal, 556 U.S. at 678 (citing Bell Atl. Corp. v. Twombly, 550 U.S. 544, 556 (2007)). "The plausibility standard is not akin to a probability requirement, but it asks for more than a sheer possibility that a defendant has acted unlawfully." Id. (quotation marks omitted). BACKGROUND A. Defendant's Admissions and Allegations1 Effective July 15, 2022, the parties entered into a Ground Lease Agreement (the "Lease") for land located at Highway 217 and Allen Boulevard in Beaverton, Washington County, Oregon (the "Premises"). Compl., ECF [1], ¶ 6 & Ex. A, at 1 (referring to pagination of exhibit); Answer, Aff. Defenses, & Counterclaims (the "Answer"), ECF [60], at 2 ¶ 6, 4 ¶ 22. Plaintiff leased the Premises for the purpose of constructing and operating a new retail and distribution store. Compl. ¶ 11; Answer 2 ¶ 11. A true and

1 Unless stated otherwise, defendant admits to or affirmatively alleges the facts within this section. correct copy of the Lease is attached to plaintiff's complaint as Exhibit A. Compl. ¶ 6 & Ex. A; Answer 2 ¶ 6, 20 ¶ 5. The parties amended the Lease in October 2022 (the "Lease Amendment"). Compl. ¶ 7 & Ex. B; Answer 2 ¶ 7. A true and correct copy of the Lease Amendment is attached to plaintiff's complaint as Exhibit B. Compl. ¶ 7 & Ex. B; Answer 2 ¶ 7. Defendant also owns the land surrounding the Premises, including an adjacent parcel upon which a hotel is being developed. Compl. ¶ 12; Answer 2 ¶ 12, 20 ¶ 6. The Lease sets forth certain construction work to be performed by or at the direction of defendant, including, in relevant part, certain utility work (the "Utility Work") and off-Premises work ("Offsite Work") (together, the "Landlord Work"2) required for plaintiff to obtain the necessary permits (the "Permits") to open and operate its retail store. Answer 2-3 ¶¶ 14, 16; see Compl. ¶¶ 14, 16 & Exs. A & B-1. The Utility Work and Offsite Work was scheduled to be due August 9, 2023, and December 27, 2023, respectively. Compl ¶¶ 24, 32; Answer 5 ¶ 24, 6 ¶ 32. Defendant concedes that delays occurred related to the Utility Work and Offsite Work but alleges that the delays were beyond defendant's control and subject to the force majeure clause found in Section 35(k) of the Lease. See Answer 3 ¶ 18, 6-7 ¶¶ 33-34. Defendant further alleges that under the Lease, plaintiff "only had the right to take possession of and construct a retail store on the Premises on or after the Commencement Date." Answer 20 ¶ 7. The Lease defines the Commencement Date as follows: "The later of (i) the date on which [defendant] has delivered possession of the Premises to [plaintiff] with the Landlord Work completed and all personal property and equipment of [defendant] and any other party removed and (ii) the earlier of (A) the Permitting Expiration Date or (B) the date that [plaintiff] has waived its right to terminate this Lease under Section 2(i) of this Lease in writing."

Compl. Ex. A, at 1 (emphasis in original); Answer 20 ¶ 7. Regarding option (i), the parties agree that defendant has not delivered possession of the Premises to plaintiff with the Landlord Work completed. See Compl. ¶ 30; Answer 22 ¶ 18; Pl. Mot. 4. As to option (ii)(A), the parties agree that this option is governed by the Permitting Expiration Date, which the parties further agree is June 10, 2023. See Compl. ¶ 23;

2 For clarity, the Court acknowledges that the Landlord Work, as that term is defined in the Lease, encompasses more than just the Utility Work and Offsite Work. See Compl. Ex. A, at 42-44. Answer 20 ¶ 8; Pl. Mot. 4; Def. Resp. Opp'n Pl. Mot. ("Def. Resp."), ECF [11], at 9 & n.4. Thus, the parties agree that the Commencement Date is determined by the date of completion of the Landlord Work. Answer 20 ¶ 9; Pl. Mot. 4; see Compl. ¶ 32.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Shroyer v. New Cingular Wireless Services, Inc.
622 F.3d 1035 (Ninth Circuit, 2010)
Daniels-Hall v. National Education Ass'n
629 F.3d 992 (Ninth Circuit, 2010)
Groves v. Prickett
420 F.2d 1119 (Ninth Circuit, 1970)
Wilson v. Hewlett-Packard Co.
668 F.3d 1136 (Ninth Circuit, 2012)
Bennett v. Farmers Insurance Co.
26 P.3d 785 (Oregon Supreme Court, 2001)
D & D CO. v. Kaufman
912 P.2d 411 (Court of Appeals of Oregon, 1996)
Waterway Terminals Co. v. P. S. Lord Mechanical Contractors
406 P.2d 556 (Oregon Supreme Court, 1965)
Yogman v. Parrott
937 P.2d 1019 (Oregon Supreme Court, 1997)
Eagle Industries, Inc. v. Thompson
900 P.2d 475 (Oregon Supreme Court, 1995)
Stark Street Properties, Inc. v. Teufel
562 P.2d 531 (Oregon Supreme Court, 1977)
Newcal Industries, Inc. v. IKON Office Solution
513 F.3d 1038 (Ninth Circuit, 2008)
Schray v. Fireman's Fund Insurance
402 F. Supp. 2d 1212 (D. Oregon, 2005)
Koch v. Spann
92 P.3d 146 (Court of Appeals of Oregon, 2004)
Alpine Mountain Homes, Inc. v. Bear Creek Homes, Inc.
122 P.3d 111 (Court of Appeals of Oregon, 2005)
Harold Schnitzer Properties v. Tradewell Group, Inc.
799 P.2d 180 (Court of Appeals of Oregon, 1990)
McKAY'S MARKET OF COOS BAY, INC. v. Pickett
157 P.3d 291 (Court of Appeals of Oregon, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Floor and Decor Outlets of America, Inc. v. Oregon Worsted Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/floor-and-decor-outlets-of-america-inc-v-oregon-worsted-company-ord-2025.