FLNG Liquefaction LLC v. CB&I Inc

CourtUnited States Bankruptcy Court, S.D. Texas
DecidedJanuary 7, 2025
Docket24-03195
StatusUnknown

This text of FLNG Liquefaction LLC v. CB&I Inc (FLNG Liquefaction LLC v. CB&I Inc) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FLNG Liquefaction LLC v. CB&I Inc, (Tex. 2025).

Opinion

January 07, 2025 Nathan Ochsner, Clerk IN THE UNITED STATES BANKRUPTCY COURT FOR THE SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION

IN RE: § § CASE NO: 24-90377 ZACHRY HOLDINGS, INC., et § al., § CHAPTER 11 § Debtors. § § FLNG LIQUEFACTION LLC, et § al., § § Plaintiffs, § § VS. § ADVERSARY NO. 24-3195 § CB&I INC, et al., §

Defendants.

MEMORANDUM OPINION FLNG Liquefaction, LLC, FLNG Liquefaction 2, LLC, and FLNG Liquefaction 3, LLC (collectively “FLNG”) commenced this adversary proceeding against CB&I Inc., Zachry Industrial, Inc, and Chiyoda International Corporation (collectively “Contractors”) seeking damages arising from the alleged breach of engineering, procurement, and construction contracts (“EPC contracts”). The contracts concerned the construction of a natural gas liquefaction and liquified natural gas export facility on Quintana Island near Freeport, Texas. FLNG discovered assembly defects in three 75 MW motors after one motor tripped and remained offline. The Contractors seek partial dismissal of the claim for consequential damages. FLNG was granted leave to amend its complaint to plead gross negligence. For the reasons stated below, FLNG’s claim for consequential damages is dismissed with prejudice. BACKGROUND I. FACTUAL BACKGROUND Freeport LNG’s natural gas liquefaction and LNG export facility is the first world-scale electric-powered LNG plant in North America. ECF No. 60 at 4. The facility has three liquefaction processing trains, where natural gas is converted to liquid. ECF No. 60 at 4. Each train uses General Electric 75 MW motors, which were selected to comply with local air emissions standards and to meet FLNG’s production targets. ECF No. 60 at 4. Between 2013 and 2015, the parties executed virtually identical EPC contracts for the construction of Trains 1–3. ECF No. 60 at 5. Section 2.3 of the EPC contracts imposes liability on the Contractors for the acts and omissions of any subcontractors. Section 2.3 provides: Owner acknowledges and agrees that Contractor intends to have portions of the Work accomplished by Subcontractors pursuant to written Subcontracts between Contractor and such Subcontractors. . . . The provisions of any Subcontract or Sub-subcontract shall not relieve Contractor of any obligations to perform the Work or of its responsibility for each Subcontractor or Sub-subcontractor. . . . Contractor shall be fully responsible to Owner for the acts and omissions of Subcontractors and Sub- subcontractors and of Persons directly or indirectly used by any of them, as Contractor is for the acts or omissions of Persons directly employed by Contractor in the performance of the Work.

ECF No. 60 at 6. Section 20.5 of the EPC contracts waives any claim for consequential damages arising out of the construction of the trains. ECF No. 39 at 4. Section 20.5 provides: Consequential Damages. NOTWITHSTANDING ANY OTHER PROVISIONS OF THIS AGREEMENT TO THE CONTRACT, NEITHER OWNER NOR CONTRACTOR SHALL BE LIABLE TO EACH OTHER UNDER THIS AGREEMENT OR UNDER ANY CAUSE OF ACTION RELATED TO THE SUBJECT MATTER OF THIS AGREEMENT, WHETHER IN CONTRACT, TORT (INCLUDING NEGLIGENCE), STRICT LIABILITY, PRODUCTS LIABILITY, INDEMNITY, CONTRIBUTION, OR ANY OTHER CAUSE OF ACTION FOR SPECIAL, INDIRECT, INCIDENTAL OR CONSEQUENTIAL LOSSES OR DAMAGES, INCLUDING LOSS OF PROFITS, USE, OPPORTUNITY, REVENUES, FINANCING, BONDING CAPACITY, OR BUSINESS INTERRUPTIONS . . . AND OWNER AND CONTRACTOR ON BEHALF OF THEMSELVES HEREBY WAIVE AND RELEASE EACH OTHER FROM ALL SUCH LOSSES AND DAMAGES. ECF No. 39 at 4. On January 17, 2024, a Train 3 motor tripped and remained offline. ECF No. 60 at 10. Investigations determined that the direct cause of the motor failure was an electrical short caused by loose hardware within the non-accessible portion of the motor. ECF No. 60 at 10. The loose hardware dislodged from a protective panel and fell into the motor windings. ECF No. 60 at 10. The root cause analysis also found “significant partial discharge”1 on the cable bundles due to “the excessive length of the cables and the increased bend radius of the cabling.” ECF No. 60 at 11. Because the same GE motor was used in Trains 1 and 2, FLNG implemented enhanced monitoring of Trains 1 and 2 and planned to perform inspections of Trains 1 and 2 after repairs to Train 3 were completed. ECF No. 60 at 11. The enhanced monitoring discovered “an increase of partial discharge and current abnormalities in one of the Train 2 motors.” ECF No. 60 at 11. Train 2 was taken offline. ECF No. 60 at 11. Inspections of the Train 2 motors found similar defects that plagued the Train 3 motors. Additionally, the micarta panel separated because a two-foot-long bolt assembly dislodged from the panel. ECF No. 60 at 12.

1 Partial discharge is a localized electrical discharge that occurs within the insulation of electrical equipment and that does not completely break the insulation. Partial discharge can precipitate a short circuit in an electrical system. See Sambeet Mishra et al., Diagnostics Analysis of Partial Discharge Events of the Power Cables at Various Voltage Levels Using Ramping Behavior Analysis Method, 227 ELEC. POWER SYS. RSCH. 1 (2024). Due to the extent of defects found in Train 2, FLNG decided to take Train 1 offline to mitigate further damage. ECF No. 60 at 12. II. PROCEDURAL BACKGROUND On April 23, 2024, FLNG filed a lawsuit against the Contractors in Texas District Court seeking damages arising out of the motor defects. ECF No. 1-2 at 12. On May 21, 2024, various Zachry affiliated entities filed for bankruptcy under chapter 11 in this Court. ECF No. 1-2 at 3. On July 31, 2024, Zachry removed the lawsuit to this Court. ECF No. 1-2 at 1. On October 18, 2024, Zachry filed a motion to dismiss FLNG’s claim for consequential damages and lost profits. ECF No. 39. On November 18, 2024, the Court held a hearing on the motion to dismiss. ECF No. 48. The Court took the matter under advisement and set a status conference for November 25, 2024. On that date, the Court dismissed FLNG’s claim for consequential damages and granted FLNG leave to re-plead on the narrow grounds of gross negligence. On December 3, 2024, FLNG filed its first amended complaint. ECF No. 60. On December 4, 2024, Zachry filed its supplemental brief in support of the motion to dismiss FLNG’s claim for consequential damages. ECF No. 61. On December 9, 2024, the Court held a hearing on the amended complaint. ECF No. 66. On December 13, 2024, the Court announced its oral ruling dismissing FLNG’s claim for consequential damages with prejudice for failing to state a claim for gross negligence. ECF No. 70. JURISDICTION The District Court has jurisdiction over this proceeding under 28 U.S.C. § 1334(a). Venue is proper in this District pursuant to 28 U.S.C. § 1409. This is a core proceeding under 28 U.S.C. § 157(b)(2). The dispute has been referred to the Bankruptcy Court under General Order 2012-6. LEGAL STANDARD The Court reviews motions under Federal Rule of Civil Procedure 12(b)(6) “accepting all well-pleaded facts as true and viewing those facts in the light most favorable to the plaintiffs.” Stokes v. Gann, 498 F.3d 483, 484 (5th Cir. 2007). However, the Court will not strain to find inferences favorable to the plaintiff. Southland Sec. Corp. v. INSpire Ins. Sols. Inc., 365 F.3d 353, 361 (5th Cir. 2004). Motions to dismiss for failure to state a claim upon which relief can be granted “are viewed with disfavor and are rarely granted.” Lormand v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stokes v. Gann
498 F.3d 483 (Fifth Circuit, 2007)
Cuvillier v. Taylor
503 F.3d 397 (Fifth Circuit, 2007)
Lormand v. US Unwired, Inc.
565 F.3d 228 (Fifth Circuit, 2009)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Jim Walter Homes, Inc. v. Reed
711 S.W.2d 617 (Texas Supreme Court, 1986)
Louisiana-Pacific Corp. v. Andrade
19 S.W.3d 245 (Texas Supreme Court, 1999)
Diamond Shamrock Refining Co., LP v. Hall
168 S.W.3d 164 (Texas Supreme Court, 2005)
Sharyland Water Supply Corp. v. City of Alton
354 S.W.3d 407 (Texas Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
FLNG Liquefaction LLC v. CB&I Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flng-liquefaction-llc-v-cbi-inc-txsb-2025.