Flintlock Construction Services, LLC v. Arch Specialty Insurance Company

CourtDistrict Court, S.D. New York
DecidedFebruary 29, 2024
Docket1:23-cv-01701
StatusUnknown

This text of Flintlock Construction Services, LLC v. Arch Specialty Insurance Company (Flintlock Construction Services, LLC v. Arch Specialty Insurance Company) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flintlock Construction Services, LLC v. Arch Specialty Insurance Company, (S.D.N.Y. 2024).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK --- ----------------------------------------------------------- X : FLINTLOCK CONSTRUCTION SERVICES, : LLC, : Petitioner, : 23 Civ. 1701 (LGS) : -against- : OPINION AND ORDER : ARCH SPECIALTY INSURANCE COMPANY, : et al., : Respondents. : -------------------------------------------------------------- X

LORNA G. SCHOFIELD, District Judge:

On November 16, 2022, the American Arbitration Association (the “AAA”) issued an award (the “Award”) against Petitioner, Flintlock Construction Services LLC, in favor of Respondents, Arch Specialty Insurance Company and Catlin Special Insurance Company. At issue are Flintlock’s Amended Petition to vacate the Award and Respondents’ cross-motion to confirm the Award. For the following reasons, Petitioner’s motion to vacate is denied, and Respondents’ motion to confirm is granted. Respondents’ related request for attorney’s fees is denied. I. BACKGROUND The following facts are taken from the sworn declarations of the parties’ counsel and attached exhibits, including the Award. Petitioner, a general contractor, was insured under a Subcontractor Default Insurance Policy (the “Policy”) purchased from Respondents. In 2018, Petitioner filed a claim under the Policy in connection with the default of its subcontractor, BMNY Contracting Corp. (“BMNY”), for defective supply and/or installation of concrete on a construction project in Manhattan. The parties disagreed over coverage and payment under the Policy. Petitioner initiated an arbitration proceeding against Respondents, and the parties later reached a settlement in the amount of $9.2 million (the “Settlement Agreement”). One term of the Settlement Agreement required Petitioner, at its own expense, to continue pursuing its state court action against certain parties who allegedly were responsible for

the loss resulting from the BMNY default (the “Recovery Action”). Under a “waterfall provision,” Petitioner and Respondents agreed that “[a]ny recoveries or damages obtained by [Petitioner] in connection with the Recovery action shall be shared among [Petitioner] and [Respondents]” according to the following formula: the first $2 million shall be split evenly between Petitioner (50%) and Respondents (25% and 25%); the next $500,000 shall go entirely to Petitioner and any remainder shall be split with half to Petitioner and half to Respondents (25% and 25%). Interpretation of this waterfall provision -- specifically the “any recoveries or damages” language -- is the subject of the Award at issue on this motion. The Settlement Agreement contains an arbitration provision which states, “Any dispute relating in any manner to this Settlement Agreement shall be heard in arbitration following the arbitration provision of the

SDI Policy.” A number of proceedings followed the Settlement Agreement, initiated by various entities. Relevant to the present action, two concrete suppliers initiated an arbitration proceeding against Petitioner and BMNY, alleging breach of contract and wrongful termination, among other claims. The Recovery Action parties agreed to withdraw that action pending a determination in the arbitration. Petitioner and Respondents also agreed that the Recovery Action was effectively subsumed by this arbitration, which would determine the issue of defective concrete, and that the arbitration constituted the Recovery Action for purposes of the Settlement Agreement. The arbitration was bifurcated so that liability and damages would be

2 determined at different stages. After fifteen days of hearings, the arbitrator issued a liability award in favor of Petitioner and BMNY against the concrete suppliers (the “Interim Award”). The arbitrator decided against Petitioner on its claim against BMNY, holding that BMNY did not default under its subcontract with Petitioner. The arbitrator awarded BMNY damages against

Petitioner for BMNY’s contract retainage. After liability was determined but before the arbitrator reached the damages phase, Petitioner, BMNY and the concrete suppliers entered a global settlement (the “Global Settlement”) whereby the parties agreed that the concrete suppliers would pay Petitioner and BMNY $8,700,000 in “full and final settlement” of any claims related to concrete supplied to the construction project. A portion, $349,500, was allocated to Petitioner to settle a dispute unrelated to the construction project. The balance of $8,350,500 was allocated $7,100,000 to Petitioner and $1,250,000 to BMNY.1 Petitioner and BMNY also agreed that BMNY’s retainage claim against Petitioner would be settled for $3,434,845.20. Accordingly, the final allocation of the $8.7 million Global Settlement was $4,014,654.80 to Petitioner and $4,684,845.20 to

BMNY. In a separate agreement between Petitioner and BMNY, executed simultaneously with the Global Settlement, the two agreed to settle any remaining claims against each other related to the construction project. Petitioner paid BMNY $225,000 and BMNY agreed to forfeit to Petitioner the $4,684,845.20 it had been allocated under the Global Settlement. Considering the Global

1 The Global Settlement appears to contain a calculation error, as it allocates $500 less than the $8,350,500 to be shared by Petitioner and BMNY. $7,100,000 + $1,250,000 = $8,350,000. This Opinion defers to the parties’ characterizations of the figures. The $500 discrepancy has no bearing on the Opinion’s legal analysis or conclusion.

3 Settlement and the Petitioner/BMNY settlement together, Petitioner recovered $8,125,500 related to the construction project.2 The present dispute arose from this figure. An escrow attorney for Petitioner then made a distribution of $1,582,827.40 to Respondents pursuant to the waterfall provision in the Settlement Agreement. In calculating the

amount due to Respondents, the attorney excluded from the “recoveries or damages obtained by [Petitioner]” the $4,684,845.20 that had been allocated to BMNY under the Global Settlement. Respondents disputed this interpretation of the waterfall provision, arguing that their share should have been based on the $8,125,500 that Petitioner ultimately netted. Using that figure, Respondents were entitled to an additional $2,342,423. This amount was placed in escrow pending resolution of the dispute. In accordance with the Settlement Agreement, Petitioner commenced a AAA arbitration against Respondents. AAA appointed a panel of three arbitrators mutually selected by the parties (the “Panel”). The parties submitted cross-motions for summary judgment, and oral argument was held on October 10, 2022. On November 16, 2022, the Panel issued the Award in

Respondents’ favor, finding that the “plain and unambiguous meaning” of the Settlement Agreement subjects the entire amount credited to Petitioner to the waterfall provision. The award directed Petitioner to pay Respondents the $2,229,923.60 they sought.3

2 This represents the $8.7 million total from the Global Settlement, less the $349,500 that was paid to Petitioner to settle an unrelated matter and the $225,000 Petitioner paid to BMNY in their private agreement. $8,700,000 – $349,500 – $225,000 = $8,125,500.

3 This figure differs slightly from the $2.34 million Respondents initially sought due to a stipulation of the parties made during arbitration. 4 II. STANDARD The parties disagree about whether Article 75 of the New York Civil Practice Law and Rules (“CPLR”) or the Federal Arbitration Act (“FAA”) provides the relevant legal standard. Both parties contend that either body of law yields their preferred outcome, but Petitioner argues

for the application of CPLR while Respondents press federal law. Ultimately, it is unnecessary to decide which law applies. For the reasons discussed below, the petition to vacate fails under either standard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rich v. Spartis
516 F.3d 75 (Second Circuit, 2008)
Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
Langrock Sperry v. Citigroup
702 F.3d 720 (Second Circuit, 2012)
Wien & Malkin LLP v. Helmsley-Spear, Inc.
846 N.E.2d 1201 (New York Court of Appeals, 2006)
City School District of the City of New York v. McGraham
958 N.E.2d 897 (New York Court of Appeals, 2011)
Seneca Nation of Indians v. State of New York
988 F.3d 618 (Second Circuit, 2021)
In re the Arbitration between Falzone & New York Mutual Fire Insurance
939 N.E.2d 1197 (New York Court of Appeals, 2010)
Goldfinger v. Lisker
500 N.E.2d 857 (New York Court of Appeals, 1986)
Pike v. Freeman
266 F.3d 78 (Second Circuit, 2001)
D.H. Blair & Co. v. Gottdiener
462 F.3d 95 (Second Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Flintlock Construction Services, LLC v. Arch Specialty Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flintlock-construction-services-llc-v-arch-specialty-insurance-company-nysd-2024.