Flint Ridge Development Co. v. Benham-Blair & Affiliates, Inc.

1989 OK 48, 775 P.2d 797, 1989 Okla. LEXIS 61, 1989 WL 27672
CourtSupreme Court of Oklahoma
DecidedMarch 28, 1989
Docket60204
StatusPublished
Cited by12 cases

This text of 1989 OK 48 (Flint Ridge Development Co. v. Benham-Blair & Affiliates, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flint Ridge Development Co. v. Benham-Blair & Affiliates, Inc., 1989 OK 48, 775 P.2d 797, 1989 Okla. LEXIS 61, 1989 WL 27672 (Okla. 1989).

Opinion

LAVENDER, Justice:

Appellant, Flint Ridge Development Company, filed its petition initiating this action on January 20, 1982. The petition alleged that in April 1973 appellant entered into a contract with appellees. Under the contract’s provisions appellees were to furnish architectural, engineering and construction supervision services'in the development of a 7,000 acre residential subdivision being developed by appellant. Appellant’s petition alleged that appellees had breached the contract in the following particulars:

A. Insufficient care and expertise were given to the design of Deer Lake Dam.
B. Improper attention and expertise were given to the design of Deer Lake Dam in order to avoid water seepage through, under, and around the dam.
C. Failure to properly design, plan, supervise, and observe construction of the facility and improvements including, but not limited to, Deer Lake Dam.
D. Improper design, supervision, and construction of the water drain system at Clear Creek Lake.
E. Improper water line installation.
F. Defective and erroneous survey and platting of lots and streets.
G. Generally unprofessional inattention to the duties and responsibilities of defendants under the contract.

And, as to the damages said to have been suffered:

As a direct result of the breach of contract by the defendants, plaintiff has suffered damages for cost of repair and attempted repairs of the Deer Lake Dam; cost of resurvey of lots; cost of resurvey and platting of streets; loss of sale of lots which were improperly surveyed; redesign and installation of water facilities from Clear Creek Lake; decrease in value of lots surrounding Deer Lake; inability to sell lakefront lots around Deer Lake; cost of either total and complete repair or total and complete reconstruction of Deer Lake Dam._

A limitations defense was initially raised in the answer filed by appellees to appellant’s petition and first amended petition. Appellees subsequently presented a motion for summary judgment following discovery in the case. In support of their motion for summary judgment appellees argued that the two year statute of limitations govern *799 ing actions in tort 1 governed in this ease. Appellees argued that appellant’s claims were tort-based as allegedly resulting from appellees’ negligent performance of duties arising out of the contractual relationship. Appellees presented a list of facts supported by affidavit to establish the various dates upon which the activities mentioned in appellant’s petition occurred and on which the various projects covered by the contract were completed. Appellees cited Oklahoma law establishing that an action for faulty design and supervision begins to run on the completion of the construction. 2

In response to appellees’ motion for summary judgment appellant argued that it had the choice of bringing an action arising out of the failure to perform the obligations imposed by the contract with reasonable care and skill in either tort or contract, 3 and that it had chosen contract. Appellant also argued that the duties alleged to have been breached by appellees arose from a written contract and were therefore governed by the five year limitations period provided by 12 O.S.1981 § 95 (First). Appellant did not contest the factual contentions made in the motion for summary judgment.

The trial court entered judgment for ap-pellees, finding appellant’s action to be brought in tort and governed by the two year statute of limitations. The trial court ruled that each of the actionable events alleged by appellant had occurred more than two years prior to the bringing of the action and therefore recovery of damages on these claims was time-barred.

On appeal the basic arguments presented by the parties below are reurged. Appellant again argues that under Oklahoma law the breach of contractual obligations may give rise to an action both in tort and in contract and that a party is not required to elect between the two in its pleadings. Ap-pellees argue that here appellant has alleged only a breach of duties implied as a result of the contractual relationship and has sought damages recoverable only in a tort action and that therefore the trial court properly held the action to have been brought exclusively in tort.

While both arguments have merit, on review of the present case we find that the grant of summary judgment in the matter was not proper.

Oklahoma law has long recognized that an action for breach of contract and an action in tort may arise from the same set of facts. 4 The argument presented by ap-pellees is that where the action alleged arises solely from a breach of an obligation imposed by law as a result of the contractual relationship, and the damages sought are those associated with an action in tort rather than an action on the contract, this Court has held the gravamen of the action to be in tort and thus governed by principles, including limitations, which control actions in tort. 5

Our review of case law on this point reveals an evolution of a view which we have found to be clearly put forth by the Supreme Court of Oregon in a discussion of the same question in a factually similar case; 6

Thus the statutes and the precedents leave us with several variations when an action for damages against one engaged to provide professional or other independent services is commenced after two *800 years and is pleaded as a breach of contract. If the alleged contract merely incorporates by reference or by implication a general standard of skill and care to which the defendant would be bound independent of the contract, and the alleged breach would also be a breach of this noncontractual duty, then ORS 12.-110 [the two year general statute of limitation covering most tort claims] applies. Dowell v. Mossberg, supra [226 Or. 173, 355 P.2d 624, 359 P.2d 541 (1961) ]. Conversely, the parties may have spelled out the performance expected by the plaintiff and promised by the defendant in terms that commit the defendant to this performance without reference to and irrespective of any general standard. Such a defendant would be liable on the contract whether he was negligent or not, and regardless of facts that might excuse him from tort liability. Or the nature either of the defendant’s default or of the plaintiffs loss may be of a kind that would not give rise to liability apart from the terms of their agreement. In such cases, there is no reason why an action upon the contract may not be commenced for the six years allowed by ORS

Related

Proe v. Diamond Homes
2025 OK CIV APP 18 (Court of Civil Appeals of Oklahoma, 2025)
Ward v. Fisher
N.D. Oklahoma, 2024
Finnell v. Seismic
2003 OK 35 (Supreme Court of Oklahoma, 2003)
Leak-Gilbert v. Fahle
2002 OK 66 (Supreme Court of Oklahoma, 2002)
Federal Deposit Ins. Corp. v. Grant
8 F. Supp. 2d 1275 (N.D. Oklahoma, 1998)
Great Plains Federal Savings & Loan Ass'n v. Dabney
1993 OK 4 (Supreme Court of Oklahoma, 1993)
MBA Commercial Construction, Inc. v. Roy J. Hannaford Co.
1991 OK 87 (Supreme Court of Oklahoma, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1989 OK 48, 775 P.2d 797, 1989 Okla. LEXIS 61, 1989 WL 27672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flint-ridge-development-co-v-benham-blair-affiliates-inc-okla-1989.