Fleming v. Wilmington & Weldon Railroad

20 S.E. 714, 115 N.C. 676
CourtSupreme Court of North Carolina
DecidedSeptember 5, 1894
StatusPublished
Cited by16 cases

This text of 20 S.E. 714 (Fleming v. Wilmington & Weldon Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fleming v. Wilmington & Weldon Railroad, 20 S.E. 714, 115 N.C. 676 (N.C. 1894).

Opinion

Avery, J.:

The rule adopted by this Court restricts the trial Judge in settling the issues to those raised by the pleadings, but does not require him to frame an issue involving the truth of every fact alleged on the one side and denied on the other. When those submitted are raised by the pleadings, and with the findings upon them form a sufficient basis for the Court to proceed to judgment, no exception to them is available to either of the parties, unless it can be made to appear that there was some view of the law arising out of the testimony which the party appealing was precluded from presenting for the consideration of the jury for want of a pertinent issue.

The question whether the culverts constructed were suf-ficent to carry off the water was involved in the broader and more general inquiry suggested by the third issue submitted. If the defendant negligently constructed the culvert so as to cause the water to be ponded on plaintiffs’ land, then it was *691 insufficient for the purpose and the defendant was liable. It would seem impossible to conceive of any legal proposition growing out of the testimony, in reference to the culvert, that could not have been considered in passing upon the third issue, if it had been presented by the defendant in the shape of a prayer for instruction.

To build a culvert that is insufficient to carry off the water, whereby water is ponded on a complainant’s land, is a wrongful and negligent construction. The gist of the controversy, or that part of it, was involved in the inquiry whether .the plaintiff had been damaged by the negligent ponding of water by the defendant in constructing its road. The building of an insufficient culvert is one ' species of carelessness that might have been the immediate cause of such an injury. Indeed, all three of the specific allegations contained in the three separate causes of action, and constituting the grounds of complaint, to wit, first, the insufficiency of the culvert; second, the filling up of the ditches; and third, the diversion of water from its natural course so as to cause plaintiffs’ land to be overflowed, might have been comprehended under one general issue as to negligent construction, and the Judge might, in his discretion, have dispensed with the fourth and fifth issues, which involved the specific allegations of negligence in the other cause of action, to wit, the filling of the ditches and the diversion of the creek.

The finding upon one general issue, involving every species of carelessness mentioned in all of the three causes of action, and the judgment thereon, would of necessity have been conclusive upon the parties as to all matters in controversy, and as to the right to recovér upon any of the causes of action. Whatever might have been offered in evidence and passed upon, the law will generally presume was presented to the jury.

It being incumbent on the defendant to show that it was deprived of the opportunity to present some material view *692 of the law arising out of the evidence, and its counsel having failed to point out any pertinent principle of law that could not have been applied, through the medium of instruction, to the issues submitted, there is no abuse of the discretionary power of the Judge shown in framing them as he did.

The conclusion that the fifth issue is not raised by the pleadings is not tenable. The allegation in the third cause of action was that, “ in the construction of said road the defendant dug on each side of the bed of the road a ditch, whereby a large and unusual volume of water is diverted from its natural course and turned upon the land and into the ditches of plaintiffs,” etc. There was evidence that the natural course of the water alleged to have been diverted was through Barnfield branch. It would be sticking in the bark to say the issue was not raised because, on hearing the proof that water was diverted from its course, the natural course was shown to be a certain branch, and the Court specified such alleged natural outlet by name in the issue, in order more clearly to direct attention to the real subject of inquiry raised by the pleadings. The question passed upon was not whether the water of Barnfield branch was wrongfully and negligently diverted from its natural course, but simply whether it was diverted. There being “ evidence tending to show that the branch was a natural waterway, and evidence to the contrary,” as defendant’s counsel states in his brief, he had the opportunity to request the Court to tell the jury that, if they found that the branch was not a natural channel, it was not negligent or wrongful, on the part of the company, to divert it from the ravine down which it previously ran. The question might have been raised by such-a prayer for instruction, but not by objecting to the issue before or after failing to do so.

We shall have occasion, upon the consideration of another branch of this controversy, to discuss the bearing of this question-whether that branch was a natural outlet.

Such damage as is due to the erection of a waterway over *693 a running stream, at the point of its intersection with the line of a railway, is considered, when the work is skilfully done, as included in the cost and valuation of the easement, or to have passed as incident to a grant of it, and the fact that it was so constructed as to pass the water, even in time of ordinary freshet, being admitted, neither the owner of the servient tenement, nor the proprietor of a tract above can maintain an action for damages caused by placing the structure across the stream.” Adams v. Railroad, 110 N. C., 725.

It was not competent, then, to prove upon what principle the commissioners estimated damages in the condemnation proceedings. The law determines what rights and privileges pass to the dominant owner, upon proof that the right-of-way was lawfully condemned for public use. One uniform rule applies in ascertaining what has passed as incidental to the acquisition of the right-of-way. The dominion and privileges of a corporation have the same limit, and are subject to the same restrictions on every part of its line, except when the right-of-way is granted by the owner with reservations, presumably allowed by reason of the exaction of a smaller consideration than would otherwise have been charged, as where the width of the way granted is to be narrower, or the company agrees to construct crossings or cattle-guards at a designated point, or in a particular manner, not otherwise required. The testimony was not competent in any point of view, but, if the undisputed evidence showed that the trestle over the Great Swamp was a sufficient waterway to discharge the water that flowed through it, except when there was an extraordinary rainfall, then it was immaterial, even if competent. Emry v. Railroad, 102 N. C., 20.9

When two of the counsel for the defendant admitted in the progress of the trial, on behalf of their client, that the plaintiffs owned and were possessed of the land, it was error in the Court to instruct the jury to respond in the affirmative to the first issue, involving the question of title and *694 possession.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner v. Southeastern Grain & Livestock Co.
102 S.E. 849 (Supreme Court of North Carolina, 1920)
Carr v. . Alexander
86 S.E. 613 (Supreme Court of North Carolina, 1915)
Edwards v. City of Cheyenne
114 P. 677 (Wyoming Supreme Court, 1911)
Roberts v. . Baldwin
66 S.E. 346 (Supreme Court of North Carolina, 1909)
Rich v. . Morisey
62 S.E. 762 (Supreme Court of North Carolina, 1908)
Davenport v. . R. R.
62 S.E. 431 (Supreme Court of North Carolina, 1908)
Davenport v. Norfolk & Southern & Suffolk & Carolina Railroad Companies
148 N.C. 287 (Supreme Court of North Carolina, 1908)
State Ex Rel. Moseley v. Johnson
56 S.E. 922 (Supreme Court of North Carolina, 1907)
Craft v. . Timber Co.
43 S.E. 597 (Supreme Court of North Carolina, 1903)
Craft v. Albemarle Timber Co.
132 N.C. 151 (Supreme Court of North Carolina, 1903)
Tucker v. . Satterthwaite
27 S.E. 45 (Supreme Court of North Carolina, 1897)
Parker v. Norfolk & Carolina Railroad
25 S.E. 722 (Supreme Court of North Carolina, 1896)
Wool v. . Bond
23 S.E. 923 (Supreme Court of North Carolina, 1896)
Simmons v. . Allison
24 S.E. 716 (Supreme Court of North Carolina, 1896)
Porter v. . Durham
74 N.C. 767 (Supreme Court of North Carolina, 1876)

Cite This Page — Counsel Stack

Bluebook (online)
20 S.E. 714, 115 N.C. 676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fleming-v-wilmington-weldon-railroad-nc-1894.