Flathead Lakers v. DNRC

2020 MT 132
Montana Supreme Court·Decided May 26, 2020·No. DA 19-0312·Published·Cited by 2 cases

Opinion

05/26/2020

DA 19-0312

Case Number: DA 19-0312

IN THE SUPREME COURT OF THE STATE OF MONTANA 2020 MT 132

FLATHEAD LAKERS INC., a Montana non-profit public benefit corporation, AMY J. WALLER, STEVEN F. MOORE, CYNTHIA S. EDSTROM, ADELE ZIMMERMAN, MARTIN FULSAAS and GAIL A. WATSON-FULSAAS, LAUREL FULLERTON, ALAN and DEIRDRE COIT, and FRANK M. WOODS,

Petitioners and Appellees, v.

MONTANA DEPARTMENT OF NATURAL RESOURCES AND CONSERVATION, and MONTANA ARTESIAN WATER COMPANY,

Respondents and Appellants, WATER FOR FLATHEAD’S FUTURE, Intervenor and Appellee.

APPEAL FROM: District Court of the First Judicial District, In and For the County of Lewis and Clark, Cause No. CDV-2018-135 Honorable Kathy Seeley, Presiding Judge

COUNSEL OF RECORD:

For Appellant Montana Department of Natural Resources and Conservation:

Brian C. Bramblett, Barbara Chillcott, Special Assistant Attorneys General, Helena, Montana

For Appellant Montana Artesian Water Company:

John E. Bloomquist, Richard C. Tappan, Bloomquist Law Firm P.C., Helena, Montana

For Appellees and Intervenor:

John J. Ferguson, Graham J. Coppes, Emily F. Wilmott, Ferguson Law Office PPLC, Missoula, Montana

Elizabeth A. Brennan, Brennan Law & Mediation, PLLC, Missoula, Montana

For Amicus Montana Building Industry Association:

Abigail J. St. Lawrence, Abigail St. Lawrence, Attorney at Law, P.C., Helena, Montana

Submitted on Briefs: January 22, 2020 Decided: May 26, 2020

Filed:

c.,.--.6--4(

Clerk

Justice Beth Baker delivered the Opinion of the Court.

¶1 Montana Artesian Water Company (“MAWC”) applied for a permit to appropriate water with the Department of Natural Resources and Conservation (“DNRC”) but did not include aquifer testing information required by DNRC rules. DNRC failed to identify defects in the application before the statutory deadline, and the application became correct and complete as a matter of law. On judicial review, the District Court concluded that the agency failed to comply with its own rules to determine whether the application was correct and complete and voided the permit without addressing other issues raised. We reverse and remand for further proceedings.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 Applicant MAWC proposes to pump 710.53 acre-feet annually from an artesian well for use in a commercial water bottling plant. The well is located in a deep alluvial aquifer of the Flathead Valley. MAWC filed the Application for Beneficial Water Use Permit No. 76LJ-30102978 with DNRC on June 24, 2015. DNRC issued MAWC a deficiency letter requesting more information regarding the proposed diversion means and beneficial use but did not identify defects in MAWC’s aquifer testing information— namely, that it did not include complete information on the observation wells, and the groundwater levels were not monitored prior to the beginning of the pump/aquifer test.

¶3 On December 30, 2015, more than 180 days after the application was filed, DNRC notified MAWC that its application was determined to be correct and complete. DNRC issued a Preliminary Determination to grant the application on January 14, 2016. After a contested case hearing, an appointed Hearing Examiner upheld DNRC’s Preliminary

Determination to grant the permit. Ten objectors—all of the individual appellees named— and Intervenor Water for Flathead’s Future (collectively “Objectors”) petitioned the First Judicial District Court for judicial review of the Hearing Examiner’s Final Order. Flathead Lakers also petitioned for judicial review, and the District Court consolidated the two actions.

¶4 The Objectors argued at the hearing—as they do on appeal—that DNRC erred when it issued its Preliminary Determination granting MAWC the water use permit based on incomplete data. The Objectors specifically point to Form 633, the “Aquifer Test Data Form,” required by Admin. R. M. 36.12.121 (2012).1 MAWC’s Form 633 contained incomplete information regarding its aquifer testing. The Objectors assert that DNRC itself, through rule promulgation, deemed this information mandatory and necessary to its determination whether to grant a permit under § 85-2-311, MCA, the statute setting forth criteria for issuance of a permit. Because MAWC did not include all information required by Form 633 in its application or provide it during the proceedings, the Objectors assert that DNRC did not have enough information to find that MAWC met the required criteria. Section 85-2-311, MCA.

¶5 DNRC and MAWC assert that it is irrelevant that the application did not have all of the Form 633 fields completed because the agency’s administrative rules mandating this specific testing information applied only in determining whether an application was correct and complete. They note that the Montana Water Use Act mandates that the application

1 All citations to the Administrative Rules of Montana will be to the rules in effect as of June 25, 2015, the date the application was filed.

be deemed correct and complete if DNRC does not notify an applicant of any deficiencies within 180 days. Section 85-2-302(5), MCA. Because 180 days had elapsed, DNRC and MAWC contend that the application was deemed correct and complete as a matter of law, and DNRC could not require the missing information.

¶6 The District Court reversed the Hearing Examiner’s decision. It held that DNRC’s administrative rules required certain minimum aquifer testing in the permit application criteria; as such, it was erroneous to conclude that the omitted information was not required when analyzing the -311 criteria. The court thus found it unnecessary to consider the Objectors’ additional arguments and voided the permit.2 STANDARD OF REVIEW

¶7 The Montana Administrative Procedure Act (“MAPA”) governs judicial review of final agency decisions. A reviewing court may reverse or modify an agency decision if substantial rights of the appellant have been prejudiced because the administrative decision is, among other reasons: affected by an error of law; clearly erroneous in view of the whole record; or arbitrary or capricious. Section 2-4-704(2)(a)(iv)-(vi), MCA. A district court reviews an administrative agency’s conclusions of law for correctness. Mont. Fish, Wildlife & Parks v. Trap Free Mont. Pub. Lands, 2018 MT 120, ¶ 11, 391 Mont. 328, 417 P.3d 1100 (citing Molnar v. Fox, 2013 MT 132, ¶ 17, 370 Mont. 238, 301 P.3d 824).

2 The District Court identified six issues objectors raised alleging error by the Hearing Examiner: 1) failing to require the mandatory components of aquifer tests; 2) not including analysis of all water sources that must be reviewed for legal availability; 3) determining no adverse effect to senior irrigators; 4) unequally applying the relevant evidence regarding water quality; 5) determining that speculatively accumulating groundwater is a beneficial use; and 6) applying an incorrect standard of review. The District Court found the first issue dispositive.

The same standard of review applies to this Court’s review of the district court’s decision. Molnar, ¶ 17.

DISCUSSION

¶8 DNRC is charged with “coordinat[ing] the development and use of the water resources of the state so as to effect full utilization, conservation, and protection of its waters.” Section 85-1-101(3), MCA. The Montana Water Use Act requires any person who wishes to appropriate water after July 1, 1973, to apply for and receive a permit from DNRC. Title 85, chapter 2, MCA. Applicants for a permit to appropriate water must prove that the permit applicant meets the criteria listed in § 85-2-311, MCA, known as the “-311 criteria.”

Permit Process

Free access — add to your briefcase to read the full text and ask questions with AI

Flathead Lakers v. DNRC, 2020 MT 132 (Mo. 2020).

2020 MT 132 (Flathead Lakers v. DNRC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

All Star Painting v. D. Jones
2021 MT 131N (Montana Supreme Court, 2021)
Debuff v. DNRC
2021 MT 68 (Montana Supreme Court, 2021)