Fiumara v. American Surety Co. of New York

31 A.2d 283, 346 Pa. 584, 149 A.L.R. 545, 1943 Pa. LEXIS 376
CourtSupreme Court of Pennsylvania
DecidedJanuary 5, 1943
DocketAppeal, 226
StatusPublished
Cited by15 cases

This text of 31 A.2d 283 (Fiumara v. American Surety Co. of New York) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fiumara v. American Surety Co. of New York, 31 A.2d 283, 346 Pa. 584, 149 A.L.R. 545, 1943 Pa. LEXIS 376 (Pa. 1943).

Opinion

Opinion by

Mr. Chief Justice Maxby,

This is an appeal from the judgment entered by the court below after a trial without a jury. Appellant alleges that a contractor paid for materials furnished a sub-contractor after the materialman had lost his right of action on the contractor’s bond by failing to institute suit thereon within the statutory year for such suit and that therefore such payment by the contractor was made too late to permit the contractor to recover the amount so paid from the surety or the sub-contractor’s bond of indemnity. The limitation here invoked arises by reason of the provisions of the Miller Act, Sec. 2(b), 40 U. S. C. A. Sec. 270(b) 1 relating to performance bonds accompanying contracts for the construction, alteration and repairs of any public building or public works of the United States. The Comptroller General’s certificate gives the date of the final settlement of the contract as July 29,1938. Under the provisions of Section 3 of this Act 2 this date is conclusive on the parties.

*587 The appellee takes the position that “in a prior suit in the Federal Court between the same parties on the same cause of action, the United States Circuit Court of Appeals (Second Circuit) adjudged the effect of such payment and the surety’s liability therefor”, and that its judgment is res ad judicata of the issue. The court below upheld this view.

Other issues arose in this protracted litigation, 3 all of which have been eliminated.

The facts are as follows: The United States entered into an agreement on September 23,1937, with Bernard Fiumara, trading as the Delmar Construction Co. (hereinafter referred to as Fiumara), for the construction of additions to the sewage disposal plant of the Veterans Administration Facility, Long Island, New York. Fiumara as principal, and the United States Fidelity and Guaranty Co. as surety, delivered to the United States their bond conditioned for the payment of claims of all persons furnishing labor and materials in the prosecution of the work pursuant to the Miller Act. Fiumara engaged W. E. Foley and Bro. Inc. (hereinafter referred to as Foley), on October 14, 1937, to furnish certain materials and to do certain plumbing and mechanical work in connection with the construction of the additions, for the agreed price of $36,000. On October 19, 1937, Foley as principal, and the appellant, American Surety Company as surety, delivered to Fiumara their bond in the sum of $36,000. conditioned that “the principal shall faithfully perform the contract on its part, free and clear of all liens arising out of claims *588 for labor and materials entering into the construction, and indemnify and save harmless the obligee from all loss, cost or damage which it may suffer by reason of the failure so to do.”

Foley performed certain work under his subcontract, but on April 18, 1939, it withdrew from the project. The Veterans Administration Bureau accepted and approved the work done to that time, and during that time Foley was paid $21,000.86,leaving a balance of $14,999.14 for the unfinished work under the contract price. Foley, when it refused to further complete its subcontract, maintained that under its interpretation of the contract it did all the work it was obligated to perform and demanded the balance. Fiumara then completed the work in certain specifications under the subcontract at a cost to him of $14,963.35. In addition to this, Fiumara, on November 11, 1937, gave Warren Foundry & Pipe Corporation, its guarantee in writing to pay it for materials furnished to Foley for the project. The material furnished under this letter of guarantee amounted to $9,924.75. Foley also failed to pay Andrew Carlson & Sons, Inc. $475.60 for materials furnished to the project. 4

The several contentions of the respective parties brought on a series of lawsuits in the Federal Court of New York and in our State Court, as follows: On October 21, 1938, Fiumara instituted this suit against the American Surety Company as surety on the subcontractor’s bond of indemnity. The bond in express terms provided “that no suit shall be brought on this bond after the 19th day of April 1939”, so that this suit was instituted within the period provided by the bond itself for the bringing of the action. However, up to and including the date of this action, no money had yet been paid out by Fiumara for the materials furnished to Foley.

*589 Foley, then, on November 19, 1938, brought suit under the Miller Act in the Federal Court of New York in the name of the United States of America for Foley’s use against Fiumara and the United States Fidelity & Guaranty Co., surety, 5 on the payment bond furnished by Fiumara in connection with the principal contract of September 23, 1937. Fiumara filed a counterclaim against the subcontractor Foley, and a third-party complaint against the American Surety Company, surety on the subcontractor’s performance bond, upon which this suit is based.

While these suits were pending the Warren Corporation, on April 14, 1939, brought suit in the Court of Common Pleas of Philadelphia against Fiumara on his guarantee.

This was the state of the record when the first of the cases was heard by Judge Galston, without a jury, in the United States District Court in New York on June 26, 1938.

The issues of the respective parties in that case appear from the opinions of Judge Galston ° and the appellate court 6 to be these. Foley claimed that it performed all of the work that it was obliged to under the contract, and that having completed its contract that there was owing to it $14,999.14. Fiumara charged Foley “with two types of breach of contract: (1) refusing to do certain items of the work required by the terms of the contract, and (2) failure to pay . . . (the) materialmen from whom Foley obtained supplies and materials used on the project. 7 His “demand upon the American Surety Company” was “to pay these damages and losses.” 8 The Surety Company denied “the material *590 allegations of breach and liability. 9 On the appeal “the argument” was “limited to the single issue of error in denying Fiumara affirmative recovery against Foley and his surety on account of a bill of some $9000 owed by Foley to Warren Foundry and Pipe Company which had supplied materials for work done by Foley.” 10

On July 25,1939, Judge Galston dismissed the complaint, 11 the counterclaim and the third party complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wise Investments, Inc. v. Bracy Contracting, Inc.
232 F. Supp. 2d 390 (E.D. Pennsylvania, 2002)
DeHaven v. Armstrong World Industries Inc.
42 Pa. D. & C.3d 516 (Lancaster County Court of Common Pleas, 1986)
Robinson v. Trenton Dressed Poultry Co.
496 A.2d 1240 (Supreme Court of Pennsylvania, 1985)
Chavez v. Chenoweth
553 P.2d 703 (New Mexico Court of Appeals, 1976)
Leist v. Schattie
179 A.2d 277 (Superior Court of Pennsylvania, 1962)
United States Ex Rel. Almeida v. Baldi
195 F.2d 815 (Third Circuit, 1952)
Eshleman v. Mumper
70 Pa. D. & C. 329 (Lancaster County Court of Common Pleas, 1950)
Rumsey Electric Co. v. Heat Seal-It Co.
61 Pa. D. & C. 562 (Philadelphia County Municipal Court, 1947)
Ostler Land & Livestock Co. v. Brough
178 P.2d 911 (Utah Supreme Court, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
31 A.2d 283, 346 Pa. 584, 149 A.L.R. 545, 1943 Pa. LEXIS 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fiumara-v-american-surety-co-of-new-york-pa-1943.