Fitness International LLC v. National Retail Properties Lp

CourtMichigan Court of Appeals
DecidedOctober 13, 2022
Docket358680
StatusUnpublished

This text of Fitness International LLC v. National Retail Properties Lp (Fitness International LLC v. National Retail Properties Lp) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fitness International LLC v. National Retail Properties Lp, (Mich. Ct. App. 2022).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

FITNESS INTERNATIONAL, LLC, UNPUBLISHED October 13, 2022 Plaintiff-Appellant,

v Nos. 358680; 358983 Macomb Circuit Court NATIONAL RETAIL PROPERTIES LIMITED LC No. 2020-004109-CB PARTNERSHIP, also known as NATIONAL RETAIL PROPERTIES, LP,

Defendant-Appellee.

Before: SWARTZLE, P.J., and CAVANAGH and REDFORD, JJ.

PER CURIAM.

In these appeals1 involving the enforceability of a commercial lease during the government shutdown orders of the COVID-19 pandemic, plaintiff appeals by right the circuit court’s opinion and order granting summary disposition in favor of defendant in Docket No. 358680 and the circuit court’s order granting defendant’s motion for attorney fees in Docket No. 358983. We affirm in Docket No. 358680 and reverse in Docket No. 358983.

I. BACKGROUND

Plaintiff is a nationwide operator of health clubs and fitness centers, including in Michigan. In July 2008, plaintiff entered into a 15-year commercial lease with defendant for premises located in Warren, Michigan, where plaintiff intended to operate a health and fitness facility. The lease required plaintiff to pay a base monthly rent in equal installments. On March 10, 2020, Michigan Governor Gretchen Whitmer declared a state of emergency in Michigan because of the novel COVID-19 pandemic. Five days later, Governor Whitmer issued an executive order mandating the closure of all gyms in Michigan, effective March 16, 2020, to prevent the further spread of the virus. The order prohibited plaintiff from operating its gym between March 17, 2020 and

1 See Fitness Int’l LLC v Nat’l Retail Props LP, unpublished order entered by the Court of Appeals on February 1, 2022 (Docket Nos. 358680, 358983) (ordering consolidation of appeals to advance the efficient administration of the appellate process).

-1- September 9, 2020, when the shutdown was lifted. During the closure period, plaintiff did not pay rent from April 2020 through August 2020, for a total of $109,561.11. In August 2020, defendant sent plaintiff a notice of default and demanded payment under the lease. Plaintiff then paid all the outstanding rent due.

A. LITIGATION

Several months later, plaintiff filed a two-count complaint alleging breach of the lease and seeking a declaratory judgment. In support, plaintiff alleged that defendant breached the lease by failing to abate the rent during the government closure period and also by failing to deliver to plaintiff the use of the premises as a health club and fitness center. In particular, plaintiff alleged that the purpose of the lease—to use the premises as a full-service health club—became frustrated and rendered both impossible and impracticable because the shutdown order prohibited plaintiff from using the premises in that manner. Plaintiff added that defendant breached its warranty of quiet enjoyment of the premises, as provided in the lease, and that full use was a condition precedent to plaintiff’s obligation to pay rent. Plaintiff sought a judgment declaring, in part, that the shutdown excused its performance under the lease and required a return of all monies paid during the closure period.

B. MOTIONS FOR SUMMARY DISPOSITION

The parties eventually filed cross-motions for summary disposition under MCR 2.116(C)(10). Defendant argued that plaintiff was not entitled to abate its rental payments during the shutdown period under the doctrines of frustration of purpose and impossibility and impracticability, in part, because plaintiff had assumed the risk of the government order under § 9.2 of the lease, and payment of rent was not impossible. Regarding the warranty of quiet enjoyment claim, defendant posited that dismissal was appropriate because it had not interfered with plaintiff’s quiet enjoyment; rather, the government order had caused the interference.

Plaintiff countered that it had established the elements of frustration of purpose. Plaintiff added that it had not assumed the risk of the government order because § 9.2 of the lease only applied to orders relating to physical improvements and alterations of the premises. Regarding the doctrine of impossibility and impracticability, plaintiff asserted that, because it was impossible to operate its health and fitness club during the shutdown, this impossibility excused its obligation to pay rent. For this same reason, plaintiff argued, the lease’s express warranty of quiet enjoyment had also been breached.

Ultimately, after a hearing on the motion, the circuit court issued an opinion and order granting defendant summary disposition. Regarding frustration of purpose, the circuit court found that plaintiff had not shown that the government shutdown had rendered the lease “virtually worthless” and that plaintiff had assumed the risk of a government shutdown under § 9.2. of the lease. The court rejected plaintiff’s interpretation of § 9.2, noting that it broadly included “various potential sources of required compliance” and that “by its own terms, Section 9.2, does not limit the cost allocation to only structural aspects of compliance.” Next, given that plaintiff had paid the rent under protest, the circuit court rejected plaintiff’s contention that the doctrine of impossibility and impracticability excused its payment of rent under the lease. The court reasoned that “economic unprofitability is not the equivalent to impossibility of performance and will not

-2- operate to relieve a party of its contractual obligations.” Finally, regarding the warranty of quiet enjoyment, the circuit court found that, because defendant did not cause the interruption, plaintiff had not shown that the lease’s quiet enjoyment provision suspended plaintiff’s obligation to pay rent.

C. MOTION FOR ATTORNEY FEES

After plaintiff filed a claim of appeal from the summary disposition order, defendant moved for an award of attorney fees and costs of $20,321. Defendant argued that § 25 of the lease entitled it to reasonable attorney fees and costs as the prevailing party. Plaintiff opposed any award of attorney fees or costs, arguing, in part, that defendant’s claim for attorney fees was barred because defendant failed to file a counterclaim for contractual fees as damages. Plaintiff asserted that, because defendant sought attorney fees based on the lease, defendant had to plead a claim for contract damages.

The circuit court ruled that the language of the lease required awarding defendant attorney fees and it held an evidentiary hearing and adjusted downward the hourly rate requested by defendant to $300 an hour. Later, the circuit court entered a written order awarding defendant costs of $164.99 and attorney fees of $13,410 (44.7 hours at $300 an hour). Plaintiff separately appealed this order.

II. ANALYSIS

A. DOCKET NO. 358680

On appeal in Docket No. 358680, plaintiff argues that the circuit court erred by granting summary disposition under MCR 2.116(C)(10) on its claims that frustration of purpose, impossibility and impracticability, and breach of the warranty of quiet enjoyment excused its performance under the lease. We disagree.

This Court reviews de novo a circuit court’s decision on a motion for summary disposition. Blackhawk Dev Corp v Village of Dexter, 473 Mich 33, 40; 700 NW2d 364 (2005). Summary disposition under MCR 2.116(C)(10) is proper if there “is no genuine issue about any material fact and the moving party is entitled to judgment . . . as a matter of law.” Bergen v Baker, 264 Mich App 376, 381; 691 NW2d 770 (2004).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blackhawk Development Corp. v. Village of Dexter
700 N.W.2d 364 (Michigan Supreme Court, 2005)
Haliw v. City of Sterling Heights
691 N.W.2d 753 (Michigan Supreme Court, 2005)
Quality Products and Concepts Co. v. Nagel Precision, Inc.
666 N.W.2d 251 (Michigan Supreme Court, 2003)
West v. General Motors Corp.
665 N.W.2d 468 (Michigan Supreme Court, 2003)
Yee v. Shiawassee County Board of Commissioners
651 N.W.2d 756 (Michigan Court of Appeals, 2002)
Zurich Insurance v. CCR & Co.
576 N.W.2d 392 (Michigan Court of Appeals, 1998)
Slatterly v. Madiol
668 N.W.2d 154 (Michigan Court of Appeals, 2003)
Roberts v. Farmers Insurance Exchange
737 N.W.2d 332 (Michigan Court of Appeals, 2007)
Fleet Business Credit, LLC v. Krapohl Ford Lincoln Mercury Co.
735 N.W.2d 644 (Michigan Court of Appeals, 2007)
Quinto v. Cross and Peters Co.
547 N.W.2d 314 (Michigan Supreme Court, 1996)
Bergen v. Baker
691 N.W.2d 770 (Michigan Court of Appeals, 2005)
Wilson Leasing Co. v. Seaway Pharmacal Corp.
220 N.W.2d 83 (Michigan Court of Appeals, 1974)
Bissell v. L. W. Edison Co.
156 N.W.2d 623 (Michigan Court of Appeals, 1967)
In Re Estate of Moukalled
714 N.W.2d 400 (Michigan Court of Appeals, 2006)
Clark v Al-Amin
872 N.W.2d 730 (Michigan Court of Appeals, 2015)
Pransky v. Falcon Group, Inc
874 N.W.2d 367 (Michigan Court of Appeals, 2015)
Pirgu v. United Services Automobile Association
884 N.W.2d 257 (Michigan Supreme Court, 2016)
Chase v. Clinton County
217 N.W. 565 (Michigan Supreme Court, 1928)
Hubbell, Roth & Clark, Inc. v. Jay Dee Contractors, Inc.
642 N.W.2d 700 (Michigan Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Fitness International LLC v. National Retail Properties Lp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fitness-international-llc-v-national-retail-properties-lp-michctapp-2022.