Fischer v. Borsher

63 Pa. D. & C.2d 167, 1972 Pa. Dist. & Cnty. Dec. LEXIS 47
CourtPennsylvania Court of Common Pleas, Monroe County
DecidedDecember 8, 1972
Docketno. 410
StatusPublished

This text of 63 Pa. D. & C.2d 167 (Fischer v. Borsher) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Monroe County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fischer v. Borsher, 63 Pa. D. & C.2d 167, 1972 Pa. Dist. & Cnty. Dec. LEXIS 47 (Pa. Super. Ct. 1972).

Opinion

WILLIAMS, P. J.,

Plaintiff filed a complaint in assumpsit against defendants on May 21, 1968, to February term, 1968, no. 497, in which he sought to recover $10,590.59, with interest from May 10, 1968, which he claimed was due him for work performed and materials furnished in constructing a home for defendants. This suit was not pursued to a conclusion and the claim was submitted to arbitration as required by section 15 of a written contract entered into by the parties.

Defendants filed a document with the arbitrators which treated the complaint in assumpsit as constituting the claim of plaintiff in the arbitration proceeding. This document set up a counterclaim which alleged that defendants claimed from plaintiff $9,400 for delay in completion of the work and an aggregate of $4,100 for defective work in respect to a well, pump and flooring.

The arbitrators filed the following report and award:

“AND NOW, the 20th day of May, 1969, we the undersigned arbitrators chosen in the above case, after having been duly sworn, and having heard the evidence and allegations of the parties, do award and [169]*169find for the Plaintiff, John E. Fischer in the sum of $9,140.59.

“Hearing held May 19, 1969

“Substitution of Arbitrators as follows: None

ISI John H. Kerrick, Arbitrator

ISI Paul L. Edinger, Arbitrator and Umpire”

Paragraph 3 of the construction contract provides that no alterations or deviations shall be made in the performance of the work except upon written order of the owners. The contract requires that if any alterations or deviations do occur the parties shall agree on the amount which would either be added to or subtracted from the contract price. The contract then provides:

“In the event of a disagreement between the Owner and the Contractor as to either of the said two amounts last mentioned, the Contractor shall proceed to perform the work pursuant to said order, and the determination of the amount either to be added to or subtracted from the contract price hereinafter mentioned, shall be submitted to arbitration as provided for in this contract, and the parties hereto agree to abide by the result of such arbitration.” (Italics supplied.)

Paragraph 4 of the contract provides for extra work or materials. These items are to be furnished or performed on written order of the owners. The contract states further:

“In the event that the Owner and Contractor fail to agree upon said amounts, the Contractor shall proceed and perform the said extra work and furnish such other materials last mentioned; and the amount to be paid thereon to the Contractor shall be determined [170]*170by arbitration, as provided in this agreement.” (Italics supplied.)

Paragraph 3 further provides that when any material is furnished or work done not shown on the drawings and specifications but upon written order of the owners, the furnishing of such materials and the performance of said work “shall be deemed to be done under and in performance of the terms of this contract,” and the provisions of the agreement requiring certificates and final payment therefor shall apply.

Section 15 of the contract provides that:

“All questions that may arise under this Contract and in the performance of the work thereunder, shall be submitted to arbitration at the choice of either of the parties hereto.”

This section of the contract also provides:

“The decision of any' two shall be binding on all the parties to the dispute. . . . The award of the Arbitrators must be in writing, and if in writing, shall not be subject to objection, on account of the procedure or form of the award.”

Defendants did not pay the amount of the award to plaintiff, who filed a complaint in assumpsit on the award to which defendants have filed an answer.

We have before us for determination a petition of defendants to vacate the arbitrators’ award and a petition of the plaintiff for judgment on the pleadings. Rules to show cause issued on both petitions.

The parties stipulated that in disposing of the petitions that the court treat as true the factual averments alleged in defendants’ petition to vacate the arbitrators’ award. These averments are that plaintiff failed to produce proof of the cost of the kitchen cabinetry in excess of the specifications; that the arbitrators failed to dispose of defendants’ counterclaim; that there was no proof that the extras claimed [171]*171by plaintiff were requested in writing; that there was no proof of the reasonableness of plaintiff’s charges except an itemization of work and labor in the form of plaintiff’s exhibit to his complaint; that the arbitrators exceeded their authority in considering extras for which there was no written order; that any oral requests were independent of the contract and would require a separate action.

We must first determine the scope of judicial review as to the issues raised by the pleadings. If the arbitration is under the Act of April 25, 1927, P. L. 381, 5 PS §173, the scope of judicial review of the arbitration proceedings is broad. If the arbitration is under the rules of common-law arbitration, the scope of judicial review is limited to whether there is an allegation and proof that the award was the result of fraud or corruption or such irregularity which caused the arbitrators to render an unjust, unequitable and unconscionable award or that a hearing had been denied: Keller v. Local 249 of International Brotherhood of Teamsters, Chauffeurs, Warehousemen and Helpers of America, 423 Pa. 353 (1966).

The construction contract makes no reference to the Act of April 25, 1927. It further provides that the decision of any two arbitrators is binding on the parties. It further provides that the award must be in writing and shall not be subject to objection on account of the procedure or the form of the award. It does not provide for an appeal from the award. Under such circumstances, the arbitration proceeding was common-law arbitration and not under the Act of 1927. Our power to review is, therefore, limited. See Nationwide Mutual Insurance Company v. Barbera, 443 Pa. 93 (1971), where Mr. Justice Eagen said:

“Moreover, since admittedly the arbitration proceedings involved were at common law, the Arbitrator was [172]*172the final judge of both law and fact, and his award will not be set aside, unless it is alleged and proven by clear, precise and convincing evidence that the parties were denied a hearing or that there was fraud, misconduct, corruption or some other irregularity of this nature on the part of the Arbitrator which caused him to render an unjust, inequitable or unconscionable finding.”

There are no allegations of fraud, corruption or any irregularity of that nature. Rather the objections relate to: (a) the rulings made by the arbitrators at the hearing on evidentiary questions; (b) the assumption of jurisdiction over certain extras claimed by plaintiff;

(c) the failure to dispose of defendants’ counterclaim;

(d) the refusal of the arbitrators to grant defendants a continuance to permit them to obtain costs on the kitchen cabinetry in excess of the amount stated in the specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

P G Metals Co. v. Hofkin
218 A.2d 238 (Supreme Court of Pennsylvania, 1966)
Wingate Construction Co. v. Schweizer Dipple, Inc.
213 A.2d 275 (Supreme Court of Pennsylvania, 1965)
Freeman v. Ajax Foundry Products, Inc.
159 A.2d 708 (Supreme Court of Pennsylvania, 1960)
Harwitz v. Selas Corp. of America
178 A.2d 617 (Supreme Court of Pennsylvania, 1962)
Nationwide Mutual Insurance v. Barbera
277 A.2d 821 (Supreme Court of Pennsylvania, 1971)
Kersey Manufacturing Co. v. Rozic
222 A.2d 713 (Supreme Court of Pennsylvania, 1966)
Westinghouse Air Brake Co. Appeal
70 A.2d 681 (Superior Court of Pennsylvania, 1949)
Keller v. Local 249 of International Brotherhood of Teamsters
223 A.2d 724 (Supreme Court of Pennsylvania, 1966)
Great American Insurance v. American Arbitration Ass'n
260 A.2d 769 (Supreme Court of Pennsylvania, 1970)
Reading Tube Corp. v. Steel Workers Federation & Reading Tube Local
98 A.2d 472 (Superior Court of Pennsylvania, 1953)
Kersey Manufacturing Co. v. Rozic
215 A.2d 323 (Superior Court of Pennsylvania, 1965)
Lighting Unlimited, Inc. v. Unger Construction Co.
269 A.2d 368 (Superior Court of Pennsylvania, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
63 Pa. D. & C.2d 167, 1972 Pa. Dist. & Cnty. Dec. LEXIS 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fischer-v-borsher-pactcomplmonroe-1972.