First National Bank v. United States Fidelity & Guaranty Co.

373 F. Supp. 235, 1974 U.S. Dist. LEXIS 9539
CourtDistrict Court, D. South Carolina
DecidedMarch 14, 1974
DocketCiv. A. 73-205
StatusPublished
Cited by3 cases

This text of 373 F. Supp. 235 (First National Bank v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First National Bank v. United States Fidelity & Guaranty Co., 373 F. Supp. 235, 1974 U.S. Dist. LEXIS 9539 (D.S.C. 1974).

Opinion

ORDER

ON PLAINTIFF’S MOTION FOR PARTIAL SUMMARY JUDGMENT

HEMPHILL, District Judge.

At the pretrial hearing of this matter it was agreed between the parties hereto that, in order to conserve time, the court would consider cross motions for partial *236 summary judgment on plaintiff’s first cause of action. Partial summary judgment is sought as to the coverage of a performance and payment bond executed by defendant and the court is called upon, at this point, to interpret the provisions of the bond.

STATEMENT OF FACTS

On October 7, 1968, O. C. Vaughn Construction Co., Inc. (hereinafter referred to as Vaughn) entered into a contract with the Housing Authority of Union, South Carolina (hereinafter referred to as the Housing Authority) for the construction of a “Housing for Senior Citizens and Low Rent Housing Project”. The contract required Vaughn to furnish a performance and payment bond. Vaughn obtained the bond from defendant. 1

In October, 1969, Vaughn borrowed a total of $75,000.00 from plaintiff, secured by an assignment of Vaughn’s “retainages” 2 due from the Housing Authority. Subsequently, in January, 1970, Vaughn defaulted on the contract with the Housing Authority, and the Housing Authority had to complete the project. Plaintiff has been able to partially satisfy the notes executed by Vaughn but there remains due and unpaid thereon the principal sum of $54,959.39 and accrued interest. Plaintiff has alleged, and declares it is prepared to prove, that all or part of the funds borrowed by Vaughn for use in or about the construction of the Housing Authority project were used by Vaughn in or about the project. Defendant has denied this assertion, and it has been agreed that this factual question will be reserved.

ISSUE

The issue presented is whether the performance and payment bond covers loans made to the contractor for use on the bonded project. More narrowly stated, the issue is whether the bond executed by defendant covers the loans made by plaintiff to Vaughn, assuming that some or all of the borrowed funds were used on the Housing Authority project. Because the jurisdiction of the court is based on diversity of citizenship, resolution of this issue is governed by the law of South Carolina. Erie R. R. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938).

ANALYSIS

Plaintiff contends that the bond executed by defendant covers loans made to the contractor for use on or in connection with the bonded project. The; conditions of the bond are not only that the contractor shall promptly pay “for all work done, or skill tools, or machinery, supplies, labor, and materials furnished” but also that the contractor shall “promptly pay all . . . debts incurred by the contractor in or about the performance of the work contracted for”. On two previous occasions the courts of South Carolina have been called upon to resolve the question of whether similar language extended the coverage of payment bonds to include bank loans to the contractor. In both cases South Carolina held that the bank was entitled to recover against the bond. Because these cases are similar to the case at bar they will be fully examined herein.

The first of these cases is National Loan & Exch. Bank v. Gustafson, 157 S. C. 221, 154 S.E. 167 (1930). There *237 plaintiff bank had made loans to the contractor on a school construction project in Greenwood, South Carolina. The loans were secured by an assignment to the bank of the contractor’s estimates and retainages and the money borrowed was used to pay for materials and payrolls. The contractor failed to complete the project, and completion was taken over by the bonding company. The bonding company also failed to complete the project, and the school trustees finally took charge and completed the job. During the period when the bonding company was in control of the job, certain estimates which had secured the bank’s loan of $12,000.00 to the contractor (which was then past due) were paid to the bonding company. The bank thereafter commenced an action against the contractor and bonding company for the $12,000.00 and also asked that the trustees be enjoined from making further payments of estimates. The trustees were permitted to complete the project and after its completion the trial court took up the claims of the bank against the bonding company. The bank’s claim rested upon the grounds that the bonding company had received estimates assigned to the bank, that the bonding company had assumed the obligations of the contractor and that the bank’s loan was covered by the bond. The court held that the bonding company was liable to the bank under each of the theories and that any one of the theories alone would support a recovery by the bank.

To determine that the bank could recover under the terms of the bond, the trial court looked to the language of the bond which provided:

The condition of this Obligation is such that if the Principal shall faithfully perform the Contract on his part, and satisfy all claims and demands incurred for the same, . . . and shall pay all persons who have contracts directly with the Principal for labor or materials, then this obligation shall be null and void . . . (Emphasis added.) 157 S.C., at 245, 154 S.E., at 176.

The trial court noted that the liability of the bonding company rested upon the terms of the bond and the intention of the parties and that the words used should be given their ordinary popular meanings. The decision states, in part:

If these words in the bond [the words emphasized above] are given their ordinary meaning, in accordance with the terms set forth in the plans and specifications, and as generally understood, then the bond in specific terms secures the payment of this claim. These words ‘satisfy all claims and demands’ if given any meaning at all, must mean something other than the things specifically set out in bond thereafter. The bond in specific terms provided for the payment of labor and materials, and these words must have been intended to be broader than those specific terms. This was a public building; public funds were used in its construction and the Board of Trustees were naturally interested in seeing that all claims incurred by the contractor in connection therewith were paid, and for that purpose the clause in the bond was inserted. . .

157 S.C., at 247, 154 S.E., at 177. On appeal to the South Carolina Supreme Court the trial court’s decision was affirmed for the reasons assigned by the trial judge.

Defendant’s attorney is apparently in error in stating that the court in Gustafson did not allow recovery under the language of the bond. After discussing the bank’s priority over the bonding company in the contractor’s assignment of the estimates, the court said, “There is still another compelling reason why the Surety Company is liable to the Bank.” 154 S.E., at 176. The court then held the surety liable under the language of the bond, portions of which holding this court has quoted above. 154 S.E., at 176-177. Similarly, the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hard Hat Workforce Solutions, LLC v. Mechanical HVAC Services, Inc.
750 S.E.2d 921 (Supreme Court of South Carolina, 2013)
Sloan Construction Co. v. Central National Insurance
236 S.E.2d 818 (Supreme Court of South Carolina, 1977)
Smith v. Mandel
66 F.R.D. 405 (D. South Carolina, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
373 F. Supp. 235, 1974 U.S. Dist. LEXIS 9539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-national-bank-v-united-states-fidelity-guaranty-co-scd-1974.