First Millennium Construction, LLC v. Parish of Jefferson

70 So. 3d 942, 10 La.App. 5 Cir. 1029, 2011 La. App. LEXIS 751, 2011 WL 2328268
CourtLouisiana Court of Appeal
DecidedJune 14, 2011
Docket10-CA-1029
StatusPublished

This text of 70 So. 3d 942 (First Millennium Construction, LLC v. Parish of Jefferson) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Millennium Construction, LLC v. Parish of Jefferson, 70 So. 3d 942, 10 La.App. 5 Cir. 1029, 2011 La. App. LEXIS 751, 2011 WL 2328268 (La. Ct. App. 2011).

Opinion

JUDE G. GRAVOIS, Judge.

l2Pefendants, Sizeler Thompson Brown Architects, A Professional Corporation, and Sizeler Thompson Brown Architects Regional Design Group, LLC (both Sizeler defendants are sometimes referred to herein collectively as “Sizeler” or “the Siz-eler defendants”), have appealed a default judgment in the amount of $423,850.70, plus court costs, that was rendered jointly against them in favor of plaintiff, First Millennium Construction, LLC (“First Millennium”). For the reasons that follow, we vacate the judgment and remand this matter for further proceedings.

FACTS AND PROCEDURAL HISTORY

On February 10, 2010, First Millennium filed a Petition for Breach of Contract, Unfair Trade Practices, Damages, and Attorney’s Fees naming as defendants the Sizeler defendants, the Parish of Jefferson, the Jefferson Parish Council (the Parish of Jefferson and the Jefferson Parish Council are sometimes referred to herein collectively as “the Parish”), and Eddie Castelin (“Castelin”), ^allegedly an employee of Siz-eler. The petition states that First Millennium was the general contractor of a building to be built for the Parish in Marrero to be used as a “Head Start” school (“the project”). The petition alleges that either one or both of the Sizeler defendants served as the architect on the project and as the Parish’s authorized representative on the project. Eddie Castelin was the site representative of Sizeler on the project. First Millennium’s contract with the Parish provides for the project to be “substantially complete” within 365 days after the day indicated in the “Notice to Proceed” issued in connection with the project (i.e., within 365 days after March 5, 2008, *944 or by March 6, 2009), and that failure to complete the project on time would result in liquidated damages in the amount of $600.00 per day having to be paid by First Millennium to the Parish. The petition alleged that the conduct of Sizeler and Castelin resulted in delays in the construction of the project which caused First Millennium to incur damages. 1 Specifically, First Millennium alleged that Sizeler’s plans and specifications for the project contained several “errors, discrepancies, and/or ‘holes’ ” which prompted First Millennium to send a number of Requests for Information (“RFIs”) to Sizeler seeking additional information. The petition alleged that Sizeler ignored and/or refused to adequately respond to most of these requests.

The petition further made the following allegations of fault against the Sizeler defendants, to-wit:

■ The site elevations called for in Siz-eler’s plans and specifications were inaccurate which caused problems with ingress and egress to the rear patios and resulted in drainage catch basins being placed in a hole over two feet deep, resulting in First Millennium having to perform extra work.
■ The “Tryke path” dimensions and layout and playground dimensions were omitted from the plans and specifications causing numerous delays in the construction.
\4U The steel beams called for in the plans and specifications interfered with some of the roof trusses.
■ The steel tubing canopy called for in the plans and specifications “ran into the front porch roof’ and Sizeler’s proposed solution did not solve the problem.
■ Sizeler unnecessarily required that First Millennium “wrap the exterior sheathing of the entire building with plastic to ‘protect’ the sheathing from the elements,” increasing the cost of construction.
■ The plans and specifications contained an incorrect water meter size and it took Sizeler “close to thirteen (13) months to get a Change Order signed for [First Millennium] to move forward, which caused many delays.”
■ Sizeler unnecessarily forced First Millennium to get an engineer to inspect the concrete to report that it was cured in accordance with the plans and specifications.
■ The plans and specifications did not provide for a sufficient amount of support for the air-conditioning units that were placed on the roof of the building.
■ Sizeler designed the electrical room too small for the equipment called for in the plans and specifications resulting in a lengthy delay in the project.

In its petition, First Millennium requested a declaratory judgment “that the delays experienced by the Project were not caused by [First Millennium],” and an award for damages it suffered as a result of Sizeler’s and Castelin’s actions, as well as attorney’s fees and any other “legal and/or equitable” relief.

Castelin was served with the petition at his residence. The Sheriffs Office was unable to serve the Sizeler defendants through their respective registered agents *945 for service of process. However, on March 29, 2010, the Sizeler defendants were purportedly served with the petition pursuant to LSA-C.C.P. arts. 1266(B) and 1261, respectively, through an alleged employee of suitable age and discretion at the place where the business of the Sizeler defendants was regularly conducted.

On April 14, 2010, First Millennium obtained a preliminary default against Sizeler. On April 22, 2010, following a confirmation hearing, judgment was rendered in favor of First Millennium and against Siz-eler confirming the | ¡{preliminary default, ordering Sizeler to “immediately reimburse, indemnify, and hold [First Millennium] and its surety harmless for any ‘liquidated damages’ that [First Millennium] and/or its surety pays to [the Parish] in connection with [the project],” and awarding “actual” damages to First Millennium in the amount of $423,850.37, plus court costs. This appeal followed the denial of Sizeler’s Motion for New Trial.

On appeal, Sizeler contends that the trial court erred in confirming the default judgment because the Sizeler defendants were not properly served with the petition, and because the evidence submitted at the default confirmation hearing was insufficient to establish a prima facie case as to fault and damages.

ANALYSIS

Louisiana Code of Civil Procedure article 1701 provides for the entry of a judgment by default when the defendant in the demand fails to answer within the time prescribed by law. Article 1702 sets forth the procedure for confirmation of a default judgment, stating that a “judgment of default must be confirmed by proof of the demand sufficient to establish a prima facie case.” A prima facie case is established, as required for confirmation of a default judgment, when the plaintiff proves the allegations made in the petition, with competent evidence, to the same degree as if the allegations had been specifically denied by the defendant. Power Marketing Direct, Inc. v. Foster, 05-2023 (La.9/6/06), 938 So.2d 662.

The determination of whether there is sufficient proof to support a default judgment is a question of fact and should not be disturbed on appeal unless it is manifestly erroneous. Ledet v. Moe, 03-745 (La.App. 5 Cir. 12/9/03), 864 So.2d 643, 644.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hickman v. Wm. Wrigley, Jr. Co., Inc.
768 So. 2d 812 (Louisiana Court of Appeal, 2000)
Power Marketing Direct, Inc. v. Foster
938 So. 2d 662 (Supreme Court of Louisiana, 2006)
Ledet v. Moe
864 So. 2d 643 (Louisiana Court of Appeal, 2003)
Rodney v. All Star Ford, Inc.
599 So. 2d 812 (Louisiana Court of Appeal, 1992)
Ross Milling Co. v. Giliberti
3 La. App. 5 (Louisiana Court of Appeal, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
70 So. 3d 942, 10 La.App. 5 Cir. 1029, 2011 La. App. LEXIS 751, 2011 WL 2328268, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-millennium-construction-llc-v-parish-of-jefferson-lactapp-2011.