Fireside Marshmallow Co. v. Frank Quinlan Const. Co.

199 F.2d 511, 1952 U.S. App. LEXIS 3386
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 28, 1952
Docket14641_1
StatusPublished
Cited by7 cases

This text of 199 F.2d 511 (Fireside Marshmallow Co. v. Frank Quinlan Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fireside Marshmallow Co. v. Frank Quinlan Const. Co., 199 F.2d 511, 1952 U.S. App. LEXIS 3386 (8th Cir. 1952).

Opinions

COLLET, Circuit Judge.

Plaintiff-appellant made a contract, in writing, with defendant on June 14, 1950, for the installation of a mastical heavy duty trucking floor in the building occupied by plaintiff in Kansas City, Kansas. Defendant engaged a subcontractor to install the floor. The subcontractor commenced laying the floor on June 30, 1950. This type of floor was supposed to dry quickly and it was anticipated that it could be used within 48 hours. It did not dry. as quickly as expected. The subcontractor claimed that was because plaintiff would not permit the building to be opened (it was air conditioned) to permit proper drying. But for reasons which will become obvious, the reason for it not drying is not an issue on this appeal. Plaintiff’s president, Mr. Shafton, inspected the floor on the morning of July 5, 1950, in company with the president of defendant, Mr. Quinlan, and the subcontractor. The possibility and probability of the floor setting up or drying was discussed. No conclusion was reached and the parties agreed to inspect it again the following morning. When that inspection was made it was still not dry. Mr. Shafton was anxious to get the floor in a usable condition as soon as possible, because the business conducted in the building was being interrupted on account of the floor. He and Mr. Quinlan again discussed the possibility of it drying, but reached no conclusion. They discussed whether or not it would be advisable to remove the mastical floor and put down a different kind. As a result of this discussion, Mr. Krogsdale, an experienced man in that kind of work, was called in by Mr. Quinlan, whether at Mr. Quinlan’s suggestion or Mr. Shafton’s is disputed. After some discussion with-Mr. Krogsdale it was decided that Krogsdale should remove the mastical floor and put down a quick-drying concrete floor (an entirely different type). This was done and the new floor, completed oh July 8, 1950, was accepted and used by plaintiff. Krogsdale [513]*513submitted his bill to plaintiff and it was referred to defendant. Later, on September 28, 1950, Krogsdále’s bill was paid by plaintiff and the following receipt signed by Quinlan:

“September 28, 1950
“Received of Fireside Marshmallow Company the sum. of $2,434.97 in full payment for labor and material for the concrete floor installed in the basement of the premises at 1809 North 7th Street, Kansas City, Kansas. This does not waive any claim that Fireside Marshmallow Company might have for losses sustained by reason of the defective floor previously installed in July of this year by the Stokes Company. Frank Quinlan Construction Company
By: (Signed) Frank Quinlan”

Thereafter this action was filed by plaintiff to' recover $5,000 damages on account of the loss of use of the building for the period after plaintiff says the mastical floor should have been ready for use and until the concrete floor was finished and usable. The basis upon which the complaint predicated liability was that defendant had “failed to properly perform its contract” for the laying of the mastical floor. The answer denied any failure to properly perform the original contract and further by counterclaim asserted that it installed the floor in accord with the contract and prayed for the recovery of the contract price.

A pre-trial conference was held, at which the court in a pre-trial order summarized the issues to be tried as follows:

“The Stokes Company [the subcontractor] commenced laying the floor in the premises occupied by plaintiff on June 30, 1950. Plaintiff claims that because said floor was improperly laid that it could not open for business on July 3rd and July 5th. On July 6th, defendant sublet to Krogsdale the job of laying a new and different kind of floor, and Krogsdale began laying such floor on said date. Plaintiff opened its plant for business on Monday, July 10, 1950.
“It is plaintiff’s contention that because the first floor laid by The Stokes Company did not dry or was improperly laid, it could not open for business on July 3rd and 5th. That it was essential to have a new and different kind of floor laid, and while the latter was being constructed it was closed for business on July 6th and 7th, and one-half day on July 8th. Plaintiff claims damages of defendant for breach of contract that necessitated its closing its factory as above stated. Plaintiff will compile the cost of operation immediately prior to and subsequent to the days it contends it was forced to close down, and submit same to defendant.
“After the second floor was laid, plaintiff, on September 28, 1950, paid to defendant the sum of $2,434.97, as shown by plaintiff’s Exhibit A, here marked, and now introduced in evidence.
* * * * * *
“The parties are to obtain from Gypsum Company specifications for the kind of floor referred to in the contract between the parties and as was undertaken to be laid by The Stokes Company. If the floor so laid by The Stokes Company is found to be in accordance with the specifications of Gypsum Company, and same was laid according to contract and in a workmanlike manner, defendant is entitled to recover the contract price therefor under its counterclaim.”

The trial was before the court without a jury. At its close the court, being convinced from the evidence that there had been a mutual rescission of the original contract by Shafton and Quinlan, treated the pleadings as amended to conform to the proof, made findings of fact and conclusions of law and entered judgment1 dis[514]*514missing plaintiff’s complaint and defendant’s counterclaim. This appeaTis by the plaintiff.

It is asserted that there is no- evidentiary basis for the trial court’s finding that there was a rescission of the contract, and that the finding of rescission was erroneous for the further reason that both parties went to trial upon the theory that the contract had not been rescinded.

There is no doubt that both parties formulated their pleadings and entered upon the trial upon the theory that the contract was still in effect. But that fact in itself would not necessarily preclude the court from treating the pleadings as amended to conform to the issues presented -by the evidence. Rules 15(b) and 54(c), Federal Rules of Civil Procedure, 28 U.S.C.A.; Gipps Brewing Corp. v. Central Mfrs’ Mutual Ins. Co., 7 Cir., 147 F.2d 6; Gins v. Mauser Plumbing Supply Co., 2 Cir., 148 F.2d 974.

Was there evidentiary basis for the finding of rescission ? The second sentence of the receipt:—

“This does not waive any claim that Fireside Marshmallow Company might have for losses sustained by reason of the defective floor previously installed in July o-f this year by the Stokes Company.”

is definitely to the contrary. But the trial court found that there was a rescission by mutual consent in July preceding the signing of the receipt in September, and as a legal result any rights or obligations that accrued under the original contract prior to the date of rescission were abandoned by the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BHP Petroleum Co., Inc. v. Okie
836 P.2d 873 (Wyoming Supreme Court, 1992)
Nab v. Hills
452 P.2d 981 (Idaho Supreme Court, 1969)
Fireside Marshmallow Co. v. Frank Quinlan Const. Co.
199 F.2d 511 (Eighth Circuit, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
199 F.2d 511, 1952 U.S. App. LEXIS 3386, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fireside-marshmallow-co-v-frank-quinlan-const-co-ca8-1952.