Finn v. Krumroy Construction Co.

589 N.E.2d 58, 68 Ohio App. 3d 480, 1990 Ohio App. LEXIS 2814
CourtOhio Court of Appeals
DecidedJuly 5, 1990
DocketNo. 14288.
StatusPublished
Cited by11 cases

This text of 589 N.E.2d 58 (Finn v. Krumroy Construction Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Finn v. Krumroy Construction Co., 589 N.E.2d 58, 68 Ohio App. 3d 480, 1990 Ohio App. LEXIS 2814 (Ohio Ct. App. 1990).

Opinion

Cirigliano, Judge.

This cause is before this court upon the appeal of Bruce and Deborah Finn from the judgment of the Common Pleas Court of Summit County finding in favor of the appellee, Krumroy Construction Company (“Krumroy”) for a breach of a construction contract to remodel appellants’ home. The court found that the appellee perfected its mechanic’s lien on appellant’s property and permitted enforcement of a $67,224.34 award. However, the trial court denied appellee’s motion for prejudgment interest. Both parties appeal.

Bruce S. Finn and Deborah Finn are the owners and residents of 2635 Yellow Creek Road, Akron, Ohio 44313. The Finns purchased the home in 1976 for $73,000. Krumroy is an Ohio corporation engaged in the general constructing business since the 1950’s.

These two parties have entered into contractual relationships for extensive remodeling of the Finn residence on three separate occasions, commencing in 1981, again in 1984 and 1985. These three remodeling projects are identified as Phase I, Phase II, and Phase III, respectively. The subject of the present dispute concerns only work involved in Phase III of the remodeling.

On May 10, 1985, the parties entered into a written contract for an addition and other modifications to the Finns’ house. The contract, in the form of a letter, was prepared by Krumroy and referred to itself as an estimate. During the planning of Phase III, Bruce Finn expressed concern for the project’s cost and sought to have the work completed for no greater than *483 $200,000. In the May 10 letter, Krumroy’s president, James Cozad, itemized the work to be done and estimated costs for certain allowances involving some additional work discussed by the parties but not yet finalized. The contract price as stated by the letter was $153,580. This total price reflected an estimated cost for labor and materials, and a percentage for Krumroy’s overhead (five percent) and commission (five percent). These figures are based on the plans prepared by Krumroy and inspected by Finn.

Krumroy billed the Finns on a monthly basis for work performed the previous month. The Finns paid in full each month without any objections until October 1985. At that point in time, Mr. Finn was not pleased with the quantity or quality of the work performed and withheld payments for work completed during the two previous months. Cozad informed the Finns that unless prompt payment was made, Krumroy would cease work on the project and execute a lien on the house. In December 1985, Mrs. Finn paid the unpaid balance and Krumroy continued the remodeling.

The relationship erupted once again at the end of December when the Finns received that month’s invoice. On January 7, 1986, Mr. Finn informed Krumroy that he did not intend to pay for work completed unsatisfactorily and ordered the construction workers off the job site. At the time of this work stoppage, the Finns had already paid more than $78,000 above the $153,580 estimated cost. Krumroy claimed that the Finns owed another $77,224.39 for work completed but remaining unpaid. Including the unpaid balance, Krumroy’s total charge for the project was $355,644.89.

On March 20, 1986, the Finns filed a complaint in the within matter against Krumroy alleging breach of contract, breach of warranties, negligence, misrepresentation and fraud arising from the written contract. The Finns contended in the trial court that the May 10 letter had established a “fixed cost” contract between the parties and that there is no obligation for excess charges above the fixed contract price. The complaint sought $675,000 in compensatory damages and $250,000 in punitive damages.

Krumroy’s answer denied the majority of Finns’ allegations and asserted the affirmative defenses of waiver, estoppel and laches. On May 6, 1986, Krumroy filed a counterclaim for breach of contract and requested foreclosure upon a mechanic’s lien encumbering the Finns’ home for the unpaid balance of the contract in the amount of $77,224.39. Krumroy’s response to Finns’ contention was that the contract between the parties was a “cost-plus fee” contract.

A cost-plus contract would estimate the construction costs, and the homeowner’s obligation would be for all actual costs plus overhead and commission charged by the builder. Such a contract arrangement was estab *484 lished for the first two phases of the remodeling. Krumroy claimed that this was the only type of arrangement that would lend itself to the control and flexibility that the Finns required to permit modifications and amendments during the course of the project.

In response to Krumroy’s counterclaim, the Finns argued that even if the written agreement is construed as a cost-plus contract, a review of the contract negotiations reveals an intent to impose a maximum cost of $200,000 for Phase III and that the builder bears the burden of proving that any cost in excess of the limitation must be reasonable in order to create an obligation on the homeowner to pay.

A trial to the court was held during which fourteen witnesses testified and over one hundred exhibits were introduced. On October 21, 1988, the trial court issued its findings of facts and conclusions of law holding, inter alia, that evidence supports Krumroy’s view of a cost-plus contractual relationship. The court also found that some of Krumroy’s work was improperly completed and in need of correction. The court determined the correction cost to be $10,000. This amount was set off against Krumroy’s counterclaim award of $77,224.34 and the court entered judgment in Krumroy’s favor in the amount of $67,224.34.

The trial court also concluded that Cozad, who was responsible for preparing the building plans for the job, did not violate the requirements of R.C. 4703.18(B) and (C), which prohibits unauthorized persons from practicing architecture. Finally, having found that Krumroy perfected its mechanic’s lien and permitting enforcement of same, the trial court denied Krumroy’s motion for prejudgment interest.

On December 30, 1988, the Finns filed a motion for new trial pursuant to Civ.R. 59. A $75,000 bond was set and an order staying execution of judgment was entered during the pendency of the new trial motion. By order dated September 26, 1989, the trial court denied the Finns’ new trial motion.

On appeal, the Finns assign four assignments of error. Krumroy filed a cross-appeal, presenting one assignment of error.

Assignment of Error I

“The predecessor trial court prejudicially erred by misapplying and misinterpreting the opinions in Charles A. Burton, Inc. v. Durkee (1952), 158 Ohio St. 313 and Charles A. Burton, Inc. v. Durkee (1954), 162 Ohio St. 433 and hence, by finding that a ‘cost-plus’ contract existed between the parties.”

The Finns charge that the evidence does not support the existence of a cost-plus contract and that the trial court misrelied on the authority of Charles A. Burton, Inc. v. Durkee (1952), 158 Ohio St. 313, 49 O.O. 174, 109 *485 N.E.2d 265 (“Burton I ”), and Charles A. Burton, Inc. v. Durkee (1954), 162 Ohio St. 433, 55 O.O. 247, 123 N.E.2d 432 (“Burton II”),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doss v. Doss
2022 Ohio 1339 (Ohio Court of Appeals, 2022)
Dilallo v. Dilallo, L-06-1329 (7-20-2007)
2007 Ohio 3684 (Ohio Court of Appeals, 2007)
Valentine v. Valentine, Unpublished Decision (5-16-2005)
2005 Ohio 2366 (Ohio Court of Appeals, 2005)
Witt v. Akron Express, Inc.
823 N.E.2d 473 (Ohio Court of Appeals, 2004)
Nationwide Mutual Fire Insurance v. Pendrey
703 N.E.2d 334 (Ohio Court of Appeals, 1997)
Winter v. Winter
658 N.E.2d 38 (Ohio Court of Appeals, 1995)
Ford v. Tandy Transportation, Inc.
620 N.E.2d 996 (Ohio Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
589 N.E.2d 58, 68 Ohio App. 3d 480, 1990 Ohio App. LEXIS 2814, Counsel Stack Legal Research, https://law.counselstack.com/opinion/finn-v-krumroy-construction-co-ohioctapp-1990.