Fieseler Masonry, Inc. v. City of Mabel, Exact Construction Company, LLC

CourtCourt of Appeals of Minnesota
DecidedSeptember 8, 2014
DocketA14-246
StatusUnpublished

This text of Fieseler Masonry, Inc. v. City of Mabel, Exact Construction Company, LLC (Fieseler Masonry, Inc. v. City of Mabel, Exact Construction Company, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fieseler Masonry, Inc. v. City of Mabel, Exact Construction Company, LLC, (Mich. Ct. App. 2014).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2012).

STATE OF MINNESOTA IN COURT OF APPEALS A14-0246

Fieseler Masonry, Inc., Appellant,

vs.

City of Mabel, et al., Respondents,

Exact Construction Company, LLC, Defendant.

Filed September 8, 2014 Affirmed Schellhas, Judge

Fillmore County District Court File No. 23-CV-12-667

William L. French, Rochester, Minnesota (for appellant)

Christopher W. Harmoning, Gray, Plant, Mooty, Mooty & Bennett, P.A., St. Cloud, Minnesota (for respondents)

Considered and decided by Worke, Presiding Judge; Schellhas, Judge; and

Rodenberg, Judge. UNPUBLISHED OPINION

SCHELLHAS, Judge

In this dispute over nonpayment for construction work, appellant challenges the

district court’s grant of summary judgment to respondents on its statutory, breach-of-

contract, and equitable claims. We affirm.

FACTS

Respondents City of Mabel and Alliance Building Construction Corp. entered into

a contract for the construction of the Mabel Community Center, and Alliance posted

performance and payment bonds. Alliance and defendant Exact Construction LLC1

entered into a $112,612 subcontract for the Mabel construction work. Alliance and Exact

later executed a change order regarding masonry and burnished block that increased the

payment due to Exact under the subcontract to $150,812. Appellant Fieseler Masonry

Inc., without seeing the job site, reached an agreement with Exact to build a straight

block wall requiring 2800 block for $14,200. At the direction of Tony Braun of Alliance,

Mark Fieseler of Fieseler Masonry met with Braun at the job site on July 28, 2011. Braun

said that he wanted Fieseler Masonry to start work right away. Fieseler returned the next

day to set up the job. On August 1, 2011, Fieseler went to the job site to start work and

realized that “the job was going to be much more time consuming than Exact had led

[Fieseler Masonry] to believe.” On August 10, 2011, Exact sent Fieseler Masonry an e-

mail, “confirm[ing] . . . the agreement between Exact Construction and Fieseler Masonry

for work to be performed on the Mabel City Hall project” for payment of “the sum of

1 Exact has not participated in this appeal.

2 $14,200 for labor only in the installation of all interior burnished block and any

associated labor involved in insulation, clean up, and repairs of unsatisfactory work with

relation to the burnished block only.” Fieseler Masonry did not respond to this e-mail.

After Fieseler Masonry began work on the job, Fieseler spoke with Darin Jensen

of Exact and asked him to come to the job site to “straighten things out,” but no one from

Exact ever appeared on the job site during Fieseler Masonry’s work, and Exact did not

return Fieseler’s many calls. Ultimately, Fieseler Masonry contacted Alliance and

demanded more money, threatening to abandon the job unless it received payment.

Fieseler Masonry claims that Alliance responded that, if forced to hire a replacement, it

“would come after” Fieseler Masonry. Fieseler Masonry therefore remained on the job

and completed it on September 25. “Instead of taking one week and 120 man hours,” the

job took seven weeks and 887.5 man hours. Fieseler Masonry sent Exact one invoice for

$13,444.81 on September 1. On September 13, Exact informed Alliance that it could not

complete the remainder of its subcontract work. Due to Exact’s default, Alliance

terminated the subcontract on October 10.

In December 2011, Fieseler Masonry submitted an invoice to Alliance for

$82,983.92 and filed a mechanic’s lien against the Mabel property. Fieseler Masonry did

not file a claim under Alliance’s payment bond. In September 2012, Fieseler Masonry

commenced this lawsuit to obtain payment, seeking in part to enforce its mechanic’s lien.

On summary-judgment motions, the district court first dismissed Fieseler Masonry’s

mechanic’s lien claim and later dismissed all remaining claims.

This appeal follows.

3 DECISION

On appeal from summary judgment, appellate courts “view the evidence in the

light most favorable to the party against whom summary judgment was granted to

determine whether there are any genuine issues of material fact and whether the district

court correctly applied the law.” Dukowitz v. Hannon Sec. Servs., 841 N.W.2d 147, 150

(Minn. 2014). A district court properly grants summary judgment “if the pleadings,

depositions, answers to interrogatories, and admissions on file, together with the

affidavits, . . . show that there is no genuine issue as to any material fact and that either

party is entitled to a judgment as a matter of law.” Minn. R. Civ. P. 56.03. “No genuine

issue for trial exists when the record taken as a whole could not lead a rational trier of

fact to find for the nonmoving party.” McKee v. Laurion, 825 N.W.2d 725, 729 (Minn.

2013) (quotations omitted). Appellate courts “review de novo a district court’s grant of

summary judgment.” Dukowitz, 841 N.W.2d at 150.

In its complaint, Fieseler Masonry asserted alternate theories of recovery. Fieseler

Masonry sought to enforce a mechanic’s lien against the City of Mabel and alleged

promissory estoppel against Alliance; entitlement to payment under Minn. Stat. § 514.02,

subd. 1a (2012), against Alliance and Exact; unjust enrichment against the City of Mabel,

Alliance, and Exact; and breach of contract against Alliance.2 On appeal, Fieseler

Masonry does not challenge the district court’s dismissal of its mechanic’s-lien claim.

2 We cite the most recent version of the statutes in this opinion because they have not been amended in relevant part. See Interstate Power Co. v. Nobles Cnty. Bd. of Comm’rs, 617 N.W.2d 566, 575 (Minn. 2000) (stating that, generally, “appellate courts apply the law as it exists at the time they rule on a case”).

4 Fieseler Masonry challenges the court’s summary-judgment dismissal of its remaining

claims. We address each claim in turn.

Claim under Minn. Stat. § 514.02, subd. 1a

In dismissing this claim, the district court noted that respondents made no mention

of Minnesota Statutes section 514.02, subdivision 1a, in their motion, but the court

nevertheless concluded, in light of Minnesota Statutes section 469.155, subdivision 16

(2012), that the provisions of chapter 514, as they relate to labor and materials, are not

applicable to Fieseler Masonry’s claim because, under the City of Mabel’s requirement,

Alliance secured a performance bond.3 Minnesota Statutes section 469.155, subdivision

16, provides that if “a contractor’s payment and performance bond of the kind described

in section 574.26” is required, then “the provisions of chapter 514 relating to liens for

labor and materials are not applicable with respect to work done or labor or materials

supplied for the project.”4 See also Judd Supply Co., Inc. v. Merchs. & Mfrs. Ins. Co., 448

N.W.2d 895, 898 (Minn. App. 1989) (noting that “if a [contractor’s] bond is required

[under Minn. Stat. § 469.55, subd. 16], then the provisions of Minn. Stat. ch. 514

(relating to mechanics’ liens) are not applicable”), review denied (Minn. Feb.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Judd Supply Co. v. Merchants & Manufacturers Insurance Co.
448 N.W.2d 895 (Court of Appeals of Minnesota, 1989)
Del Hayes & Sons, Inc. v. Mitchell
230 N.W.2d 588 (Supreme Court of Minnesota, 1975)
United States Fire Insurance Co. v. Minnesota State Zoological Board
307 N.W.2d 490 (Supreme Court of Minnesota, 1981)
Commercial Associates, Inc. v. Work Connection, Inc.
712 N.W.2d 772 (Court of Appeals of Minnesota, 2006)
Hebrink v. Farm Bureau Life Insurance Co.
664 N.W.2d 414 (Court of Appeals of Minnesota, 2003)
Pine River State Bank v. Mettille
333 N.W.2d 622 (Supreme Court of Minnesota, 1983)
ServiceMaster of St. Cloud v. GAB Business Services, Inc.
544 N.W.2d 302 (Supreme Court of Minnesota, 1996)
Interstate Power Co. v. Nobles County Board of Commissioners
617 N.W.2d 566 (Supreme Court of Minnesota, 2000)
Ostrander v. Ostrander
252 N.W. 449 (Supreme Court of Minnesota, 1934)
Amcon Block & Precast, Inc. v. Suess
794 N.W.2d 386 (Court of Appeals of Minnesota, 2011)
SCI Minnesota Funeral Services, Inc. v. Washburn-McReavy Funeral Corp.
795 N.W.2d 855 (Supreme Court of Minnesota, 2011)
Park Nicollet Clinic v. Hamann
808 N.W.2d 828 (Supreme Court of Minnesota, 2011)
Anderson v. Christopherson
816 N.W.2d 626 (Supreme Court of Minnesota, 2012)
Caldas v. Affordable Granite & Stone, Inc.
820 N.W.2d 826 (Supreme Court of Minnesota, 2012)
McKee v. Laurion
825 N.W.2d 725 (Supreme Court of Minnesota, 2013)
Dukowitz v. Hannon Security Services
841 N.W.2d 147 (Supreme Court of Minnesota, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Fieseler Masonry, Inc. v. City of Mabel, Exact Construction Company, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fieseler-masonry-inc-v-city-of-mabel-exact-construction-company-llc-minnctapp-2014.