Fieseler Masonry, Inc. v. City of Mabel, Exact Construction Company, LLC

Court of Appeals of Minnesota·Decided September 8, 2014·No. A14-246·Unpublished

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2012).

STATE OF MINNESOTA

IN COURT OF APPEALS

A14-0246

Fieseler Masonry, Inc.,

Appellant,

vs.

City of Mabel, et al.,

Respondents,

Exact Construction Company, LLC, Defendant.

Filed September 8, 2014

Affirmed

Schellhas, Judge

Fillmore County District Court File No. 23-CV-12-667

William L. French, Rochester, Minnesota (for appellant)

Christopher W. Harmoning, Gray, Plant, Mooty, Mooty & Bennett, P.A., St. Cloud, Minnesota (for respondents)

Considered and decided by Worke, Presiding Judge; Schellhas, Judge; and Rodenberg, Judge.

UNPUBLISHED OPINION

SCHELLHAS, Judge In this dispute over nonpayment for construction work, appellant challenges the district court’s grant of summary judgment to respondents on its statutory, breach-of- contract, and equitable claims. We affirm.

FACTS

Respondents City of Mabel and Alliance Building Construction Corp. entered into a contract for the construction of the Mabel Community Center, and Alliance posted performance and payment bonds. Alliance and defendant Exact Construction LLC1 entered into a $112,612 subcontract for the Mabel construction work. Alliance and Exact later executed a change order regarding masonry and burnished block that increased the payment due to Exact under the subcontract to $150,812. Appellant Fieseler Masonry Inc., without seeing the job site, reached an agreement with Exact to build a straight block wall requiring 2800 block for $14,200. At the direction of Tony Braun of Alliance, Mark Fieseler of Fieseler Masonry met with Braun at the job site on July 28, 2011. Braun said that he wanted Fieseler Masonry to start work right away. Fieseler returned the next day to set up the job. On August 1, 2011, Fieseler went to the job site to start work and realized that “the job was going to be much more time consuming than Exact had led [Fieseler Masonry] to believe.” On August 10, 2011, Exact sent Fieseler Masonry an e- mail, “confirm[ing] . . . the agreement between Exact Construction and Fieseler Masonry for work to be performed on the Mabel City Hall project” for payment of “the sum of

1 Exact has not participated in this appeal.

$14,200 for labor only in the installation of all interior burnished block and any associated labor involved in insulation, clean up, and repairs of unsatisfactory work with relation to the burnished block only.” Fieseler Masonry did not respond to this e-mail.

After Fieseler Masonry began work on the job, Fieseler spoke with Darin Jensen of Exact and asked him to come to the job site to “straighten things out,” but no one from Exact ever appeared on the job site during Fieseler Masonry’s work, and Exact did not return Fieseler’s many calls. Ultimately, Fieseler Masonry contacted Alliance and demanded more money, threatening to abandon the job unless it received payment. Fieseler Masonry claims that Alliance responded that, if forced to hire a replacement, it “would come after” Fieseler Masonry. Fieseler Masonry therefore remained on the job and completed it on September 25. “Instead of taking one week and 120 man hours,” the job took seven weeks and 887.5 man hours. Fieseler Masonry sent Exact one invoice for $13,444.81 on September 1. On September 13, Exact informed Alliance that it could not complete the remainder of its subcontract work. Due to Exact’s default, Alliance terminated the subcontract on October 10.

In December 2011, Fieseler Masonry submitted an invoice to Alliance for $82,983.92 and filed a mechanic’s lien against the Mabel property. Fieseler Masonry did not file a claim under Alliance’s payment bond. In September 2012, Fieseler Masonry commenced this lawsuit to obtain payment, seeking in part to enforce its mechanic’s lien. On summary-judgment motions, the district court first dismissed Fieseler Masonry’s mechanic’s lien claim and later dismissed all remaining claims.

This appeal follows.

DECISION

On appeal from summary judgment, appellate courts “view the evidence in the light most favorable to the party against whom summary judgment was granted to determine whether there are any genuine issues of material fact and whether the district court correctly applied the law.” Dukowitz v. Hannon Sec. Servs., 841 N.W.2d 147, 150 (Minn. 2014). A district court properly grants summary judgment “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, . . . show that there is no genuine issue as to any material fact and that either party is entitled to a judgment as a matter of law.” Minn. R. Civ. P. 56.03. “No genuine issue for trial exists when the record taken as a whole could not lead a rational trier of fact to find for the nonmoving party.” McKee v. Laurion, 825 N.W.2d 725, 729 (Minn. 2013) (quotations omitted). Appellate courts “review de novo a district court’s grant of summary judgment.” Dukowitz, 841 N.W.2d at 150.

In its complaint, Fieseler Masonry asserted alternate theories of recovery. Fieseler Masonry sought to enforce a mechanic’s lien against the City of Mabel and alleged promissory estoppel against Alliance; entitlement to payment under Minn. Stat. § 514.02, subd. 1a (2012), against Alliance and Exact; unjust enrichment against the City of Mabel, Alliance, and Exact; and breach of contract against Alliance.2 On appeal, Fieseler Masonry does not challenge the district court’s dismissal of its mechanic’s-lien claim.

2 We cite the most recent version of the statutes in this opinion because they have not been amended in relevant part. See Interstate Power Co. v. Nobles Cnty. Bd. of Comm’rs, 617 N.W.2d 566, 575 (Minn. 2000) (stating that, generally, “appellate courts apply the law as it exists at the time they rule on a case”).

Fieseler Masonry challenges the court’s summary-judgment dismissal of its remaining claims. We address each claim in turn. Claim under Minn. Stat. § 514.02, subd. 1a In dismissing this claim, the district court noted that respondents made no mention of Minnesota Statutes section 514.02, subdivision 1a, in their motion, but the court nevertheless concluded, in light of Minnesota Statutes section 469.155, subdivision 16 (2012), that the provisions of chapter 514, as they relate to labor and materials, are not applicable to Fieseler Masonry’s claim because, under the City of Mabel’s requirement, Alliance secured a performance bond.3 Minnesota Statutes section 469.155, subdivision 16, provides that if “a contractor’s payment and performance bond of the kind described in section 574.26” is required, then “the provisions of chapter 514 relating to liens for labor and materials are not applicable with respect to work done or labor or materials supplied for the project.”4 See also Judd Supply Co., Inc. v. Merchs. & Mfrs. Ins. Co., 448 N.W.2d 895, 898 (Minn. App. 1989) (noting that “if a [contractor’s] bond is required [under Minn. Stat. § 469.55, subd. 16], then the provisions of Minn. Stat. ch. 514 (relating to mechanics’ liens) are not applicable”), review denied (Minn. Feb. 21, 1990).

3 In their reply memorandum to the district court, respondents argued for summary judgment on Fieseler Masonry’s statutory claim. 4 Minnesota Statutes section 574.26, subdivision 1(a)-(b) (2012), provides that sections 574.26 to 574.32 are the “Public Contractors’ Performance and Payment Bond Act,” and that “[f]or the purposes of the act[,] . . . ‘labor and materials’ means work, skill, tools, machinery, materials, . . . and . . . ‘contract’ means a contract with a public body for the doing of public work.”

Free access — add to your briefcase to read the full text and ask questions with AI

Fieseler Masonry, Inc. v. City of Mabel, Exact Construction Company, LLC, (Mich. Ct. App. 2014).

Fieseler Masonry, Inc. v. City of Mabel, Exact Construction Company, LLC (Fieseler Masonry, Inc. v. City of Mabel, Exact Construction Company, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Judd Supply Co. v. Merchants & Manufacturers Insurance Co.
448 N.W.2d 895 (Court of Appeals of Minnesota, 1989)
Del Hayes & Sons, Inc. v. Mitchell
230 N.W.2d 588 (Supreme Court of Minnesota, 1975)
United States Fire Insurance Co. v. Minnesota State Zoological Board
307 N.W.2d 490 (Supreme Court of Minnesota, 1981)
Commercial Associates, Inc. v. Work Connection, Inc.
712 N.W.2d 772 (Court of Appeals of Minnesota, 2006)
Hebrink v. Farm Bureau Life Insurance Co.
664 N.W.2d 414 (Court of Appeals of Minnesota, 2003)
Pine River State Bank v. Mettille
333 N.W.2d 622 (Supreme Court of Minnesota, 1983)
ServiceMaster of St. Cloud v. GAB Business Services, Inc.
544 N.W.2d 302 (Supreme Court of Minnesota, 1996)
Interstate Power Co. v. Nobles County Board of Commissioners
617 N.W.2d 566 (Supreme Court of Minnesota, 2000)
Ostrander v. Ostrander
252 N.W. 449 (Supreme Court of Minnesota, 1934)
Amcon Block & Precast, Inc. v. Suess
794 N.W.2d 386 (Court of Appeals of Minnesota, 2011)
SCI Minnesota Funeral Services, Inc. v. Washburn-McReavy Funeral Corp.
795 N.W.2d 855 (Supreme Court of Minnesota, 2011)
Park Nicollet Clinic v. Hamann
808 N.W.2d 828 (Supreme Court of Minnesota, 2011)
Anderson v. Christopherson
816 N.W.2d 626 (Supreme Court of Minnesota, 2012)
Caldas v. Affordable Granite & Stone, Inc.
820 N.W.2d 826 (Supreme Court of Minnesota, 2012)
McKee v. Laurion
825 N.W.2d 725 (Supreme Court of Minnesota, 2013)
Dukowitz v. Hannon Security Services
841 N.W.2d 147 (Supreme Court of Minnesota, 2014)