Fidelity & Deposit Co. v. Pittman

183 S.E. 572, 52 Ga. App. 394, 1936 Ga. App. LEXIS 647
CourtCourt of Appeals of Georgia
DecidedJanuary 14, 1936
Docket24922
StatusPublished
Cited by11 cases

This text of 183 S.E. 572 (Fidelity & Deposit Co. v. Pittman) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. Pittman, 183 S.E. 572, 52 Ga. App. 394, 1936 Ga. App. LEXIS 647 (Ga. Ct. App. 1936).

Opinion

Sutton, J.

Suit for the use of a materialman who furnished marble to a subcontractor for a United States Government hospital, against the surety on the bond of the subcontractor, was brought in the name of the trustee in bankruptcy of the main contractor, who was the obligee in the bond. The material facts are substantially as follows: The Jewell Riddle Company, the main contractor, had a contract with the Government for the construction of a hospital. The Georgia Marble Company furnished marble to the Blue Ridge Tile Company, the subcontractor, which material was accepted by both the subcontractor and the main contractor and used in the construction of the hospital, in accordance with the contract bétween the main contractor and the Government. The Fidelity and Deposit Company of Maryland executed a bond to the main contractor as owner or obligee, agreeing to pay the main contractor the sum named therein, and providing further: “Whereas the principal [the subcontractor] has, by means of a written agreement dated June 23, 1931, entered into a contract with the owner [the main contractor] for furnishing and installing all labor and material necessary for a complete job of all slate, marble, tile, soapstone work, and accessories, including all setting material for the hospital at Fort Humphrys, Virginia, a copy of which agreement is by reference made a part hereof: Now, therefore, the condition of this obligation is such that if the principal [the subcontractor] shall faithfully perform the contract on his part, and satisfy all claims and demands incurred for the same, and shall indemnify and save harmless the owner from all cost and damage which he may suffer by reason of failure so to do, and shall fully reimburse and repay the owner [the main contractor] all outlay and expense which the owner may incur in making good any such default, and shall pay all persons who have contracts directly with the principal [the subcontractor] for labor or materials, then this obligation shall be null and void; otherwise it shall remain in full force and effect.” On March 28, 1932, an involuntary petition in bankruptcy was filed against the Jewell Riddle Company, the main [396]*396contractor, under which that company was adjudicated a bankrupt on June 27, 1932, at which time said company was due and owing the subcontractor, under a contract between the main contractor and subcontractor, $1884.46 for work done and materials furnished by the subcontractor in the construction of the hospital, which sum was still due and owing. The petition alleged the failure of the subcontractor to pay the materialman for the material furnished to the subcontractor by the materialman.

The original petition was in the name of the Georgia Marble Company, the materialman, the real plaintiff in interest. By amendment it substituted as the nominal plaintiff, J. C. Pittman, trustee in bankruptcy of the Jewell Biddle Company, the main contractor, suing for the use of the Georgia Marble Company. The defendant surety made a motion to disallow and to strike the amendment, on the grounds that no cause of action was set out in the original petition, and therefore that there was nothing by 'which to amend; that it did not appear that the main contractor had any right to bring the action for the use and benefit of another; and that there was no allegation in the petition, nor would there be on the allowance of the amendment, to show any liability on the surety. The defendant excepted pendente lite to the order overruling this motion. It demurred to the petition, before and after the amendment, on the grounds that no cause of action was stated; that the bond sued on contained no promise or other contractual obligation running from the surety to the materialman; that it did not appear from the petition and its exhibits that the owner had sustained any loss or damage by reason of any default of the principal, the subcontractor, and that the Georgia Marble Company, as materialman, was not a beneficiary under the terms of the bond. The defendant excepted pendente lite to the order overruling its demurrer. Its answer set up that the Blue Bidge Tile Company was a subcontractor under the Jewell Biddle Company, which company had a contract with the United States Government for the erection of the public work referred to in the bond; that this public work was to be performed under statutes of the United States; that the main contractor, Jewell Biddle Company, in pursuance of such statutes, gave bond with.security, conditioned for the payment of all labor and material used in the prosecution of the work, and in order to protect itself against liability for labor [397]*397and materials furnished by the subcontractor in the work done under the subcontractor, but for which the subcontractor might not pay, so that liability therefor could be established against it and its surety, took from said subcontractor the bond sued on, for its sole benefit and protection; that the plaintiff’s right of action, if any existed, was on the bond given by the main contractor, Jewell Eiddle Company, to the Government, and not on the subcontractor’s bond to the main contractor. However, there was no direct proof that the Jewell Eiddle Company had ever given a contractor’s bond to the Government; this allegation of the defendant being based on the alleged presumption that the main contractor had complied with the United States statutes providing for such bond.

The defendant pleaded further that at the time the main contractor became bankrupt it was due and owing the subcontractor, under the terms of the contract between the main contractor and the subcontractor, $1884.46 for work and materials furnished by the subcontractor in the construction of the hospital, which was not paid to the subcontractor, and which the defendant averred was still owing; that the Jewell Eiddle Company, as the main contractor and as obligee in the bond sued on, had released the subcontractor (the principal in the bond) and the defendant surety, by increasing the risk of the surety by rendering the subcontractor less able to discharge its obligation to the materialman, by the failure of the main contractor to pay the subcontractor the sums due it, thereby making it impossible for the subcontractor to comply with the terms of the subcontractor’s bond to the main contractor, the bond sued on. By way of set-off and counter-claim the defendant alleged that the nominal plaintiff, the trustee in bankruptcy was indebted to the subcontractor $1884.46 for work done and materials furnished by the subcontractor in the construction of the hospital; and prayed that it be allowed to set off against the plaintiff’s claim the claim of the subcontractor as principal and/or the defendant as surety, up to the sum sued for.

By agreement the case was tried by the judge without a jury. He rendered judgment in favor of the plaintiff in the amount sued for, with interest. To this judgment the defendant excepted, and assigned error also on its exceptions pendente lite.

[398]*3981. The materialman had such a beneficial interest in the subcontractor’s bond as to authorize a suit thereon for the use of the materialman. American Surety Co. v. DeWald, 30 Ga. App. 606 (118 S. E. 703); Union Indemnity Co. v. Riley, 169 Ga. 229 (150 S. E. 216), and cit. The petition in the DeWald ease showed that a suit was brought against the American Surety Company in ithe name of Mrs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kitaeff v. Vappi & Co. (In Re Bay State York Co.)
140 B.R. 608 (D. Massachusetts, 1992)
Sims' Crane Service, Inc. v. Reliance Insurance
514 F. Supp. 1033 (S.D. Georgia, 1981)
Powers Regulator Co. v. United States Fidelity & Guaranty Co.
388 N.E.2d 1205 (Massachusetts Appeals Court, 1979)
McLendon Electric Co. v. McDonough Construction Co.
243 S.E.2d 537 (Court of Appeals of Georgia, 1978)
Sentry Indemnity Company v. Central Electric Company, Inc.
222 S.E.2d 40 (Court of Appeals of Georgia, 1975)
Robinson Explosives, Inc. v. Dalon Contracting Co.
209 S.E.2d 264 (Court of Appeals of Georgia, 1974)
Climatrol Industries, Inc. v. Home Indemnity Co.
316 F. Supp. 314 (N.D. Georgia, 1970)
Pacific National Fire Insurance v. Cummins Diesel of Georgia, Inc.
96 S.E.2d 881 (Supreme Court of Georgia, 1957)
Glens Falls Indemnity Co. v. Southeastern Construction Co.
62 S.E.2d 149 (Supreme Court of Georgia, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
183 S.E. 572, 52 Ga. App. 394, 1936 Ga. App. LEXIS 647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-pittman-gactapp-1936.