Fidelity & Deposit Co. v. City of Stafford

144 P. 852, 93 Kan. 539, 1914 Kan. LEXIS 468
CourtSupreme Court of Kansas
DecidedDecember 12, 1914
DocketNo. 19,078
StatusPublished
Cited by17 cases

This text of 144 P. 852 (Fidelity & Deposit Co. v. City of Stafford) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. City of Stafford, 144 P. 852, 93 Kan. 539, 1914 Kan. LEXIS 468 (kan 1914).

Opinion

The opinion of the court was delivered by

West, J.:

Joseph Bortenlanger contracted with the city of Stafford for the construction of a waterworks system and an electric light plant. Pursuant to the provision requiring him to give bond he furnished one executed by the plaintiff, which bond provided that if the principal should voluntarily abandon the contract the surety should have the right to assume the same and sublet or complete it, “and if said contract shall be assumed by the Surety, then as such contract is duly performed, any reserve, deferred payments and all other monies provided by said contract to be paid to the Principals, shall'be paid to the Surety, at the same times and under the same conditions as by the terms thereof, such monies would have been paid to the Principals had the contract, been duly performed by them.” This was executed January 30, 1911. The same principal and surety on the same date executed a bond to the state conditioned for the payment of all [541]*541indebtedness incurred for the material furnished for making the improvement. Before the execution of these bonds Bortenlanger executed and delivered to the plaintiff an agreement in writing to pay all loss and damage on account of any default or neglect on his part, and providing that in case of any breach or default on his part the company should be subrogated to all his rights in the contract, “and that deferred payments and any and all monies and properties that may be due and payable to me, at the time of such breach or default, or that may thereafter become due and payable to me, on account of said contract, shall be credited upon any claim that may be made upon the Fidelity and Deposit Company of Maryland under the bond above mentioned.” The trial court found that Bortenlanger failed to complete his contract by the first day of July, 1911, and an extension having been granted until September 15, he continued the work, but about that time abandoned the same, and upon the request of the city the defendant assumed the contract and completed the work in accordance therewith; that the work was accepted by the city October, 1911, when it was mutually agreed that the amount due from the city on the contract was $5534.02; that the plaintiff thereupon offered to pay all labor and material bills remaining unpaid, amounting to $5888.62, and demanded that the city pay the $5534.02, which the city refused to do; that in completing the contract the plaintiff paid labor and material bills amounting to $1000, and had also paid the $5888.62, amounting to $6888.62 in all; that about April 15, 1911, the contractor borrowed of the defendant bank $2000, and without knowledge and consent of the plaintiff executed and delivered to the bank an order or assignment in the sum of $2000 drawn against the city and directed it to pay the bank such sum out of any funds due or becoming due to him from the city on his contract; that about November 4, 1911, over the protest and objection of the plaintiff, the city paid the bank $2000 out of the [542]*542$5534.02 remaining unpaid on the contract. It was stipulated that the money was borrowed as follows:

“The bank was to give Bortenlanger credit for said $2000.00, and it was to be drawn out on the checks of said Bortenlanger for material and labor in the fulfillment of his contract with the city, to which check was to be attached the bill of such labor and material for which said check was issued, properly signed by the materialman or laborer so paid; that no part of said $2000.00 was to be drawn in any other manner, and none of it was in fact drawn or used by said Bortenlanger in any other manner than as agreed; that said agreement and said credit was given on the above terms and conditions prior to any of such money being drawn out of said bank; that the said money was loaned by the bank to Bortenlanger for the payment of labor and .material thereafter to go into the work.”

The company recovered and the city and the bank appeal, the sole point presented being the effect of the arrangement made with the bank.

It is manifest that under the contract already referred to the surety company, on completing the work after the contractor’s default, was entitled to step into his shoes and receive such payments from the city as otherwise he could have been entitled to. Also, that the bank was not the contractor’s creditor by virtue of an ordinary loan of money to him to use as he pleased, but because of having furnished $2000 to pay that amount of the" labor and material claims as they accrued in the progress of the work; and of course by paying them they were taken out of the category of possible demands, lienable or otherwise, to be considered in the final settlement. It is also clear that while this transaction was had by consent of the contractor, the bank and the city, the plaintiff surety company was not assenting thereto and does not appear to have had notice thereof, and yet under one of the contracts said by the trial court to have been on file with the city clerk the plaintiff, upon completing the work, was entitled to look to the city for all sums due or to become due on the contract. The plaintiff’s position is that [543]*543upon the contractor’s default all sums due or to become due for the work became a trust fund in the hands of the city upon which the plaintiff acquired a lien when it paid the remainder of such sums, and that this lien related back to the date of the original contract, January 31, 1911; that the bank was a mere volunteer and did not acquire the right of subrogation or an equitable lien, but only the right to whatever funds might be left after the surety company should be paid its losses sustained by Bortenlanger’s default. The defendant bank’s position is that it in reality paid certain labor and material claims, receiving receipted bills therefor, and thereby became the equitable assignee of such claims; that it not only took an order on the city, but it paid nothing to the contractor, simply taking up certain claims for labor and material which went into the building; that had not such labor and materialmen assigned such claims to the bank they could have participated in the fund provided for the erection of the plant, and that by this arrangement the city was protected from liens which otherwise might have been filed for these claims. The exact situation is this: The surety company had a contract on file with the city clerk entitling it upon completion of the contract to all the moneys due or to become due Bortenlanger. This sum was $5534.02, but of this $2000 worth of claims had been paid with the money borrowed of the bank, hence he would have been entitled to the balance only, or $3534.02, had he completed the contract himself, and had the $2000 order on the city in favor of the bank been honored. On this basis, the surety company, having paid out $6888.62 in order to complete the contract, would, by the recovery of the $3534.02, lose $3354.60, and if paid the entire sum of $5534.02 it would still be loser in the sum of $1354.60. Bortenlanger is out of the deal now. The city has lost nothing, and it remains to determine whether the bank or the bonding company must suffer.

A brief review of the cases relied on by the plaintiff [544]*544seems proper. In Ætna Life Ins. Co. v. Middleport, 124 U. S. 534, 8 Sup. Ct. Rep. 625, 31 L. Ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Fidelity & Guaranty Co. v. First State Bank
494 P.2d 1149 (Supreme Court of Kansas, 1972)
Katschor v. Ley
113 P.2d 127 (Supreme Court of Kansas, 1941)
Federal Intermediate Credit Bank v. Howard
284 P. 380 (Supreme Court of Kansas, 1930)
Waddle v. Bird
267 P. 974 (Supreme Court of Kansas, 1928)
Morris v. Nelson
257 P. 729 (Supreme Court of Kansas, 1927)
Federal Land Bank v. Hanks
254 P. 1040 (Supreme Court of Kansas, 1927)
Crane v. Daniel
245 P. 1017 (Supreme Court of Kansas, 1926)
State Ex Rel. Southern Surety Co. v. Schlesinger
151 N.E. 177 (Ohio Supreme Court, 1926)
Elggren v. Woolley
228 P. 906 (Utah Supreme Court, 1924)
United States Fidelity & Guaranty Co. v. City of Pittsburg
225 P. 83 (Supreme Court of Kansas, 1924)
Breyfogle v. Jackson
214 P. 779 (Supreme Court of Kansas, 1923)
Neodesha National Bank v. Russell
200 P. 281 (Supreme Court of Kansas, 1921)
New Amsterdam Casualty Co. v. Wurtz
177 N.W. 664 (Supreme Court of Minnesota, 1920)
Illinois Surety Co. v. Mitchell
1918A L.R.A. 931 (Court of Appeals of Kentucky, 1917)
Fidelity & Deposit Co. v. City of Stafford
165 P. 837 (Supreme Court of Kansas, 1917)
New v. Smith
145 P. 880 (Supreme Court of Kansas, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
144 P. 852, 93 Kan. 539, 1914 Kan. LEXIS 468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-city-of-stafford-kan-1914.