Fibre Optic Plus, Inc. v. XL Specialty Insurance

8 A.3d 539, 125 Conn. App. 399, 2010 Conn. App. LEXIS 546
Connecticut Appellate Court·Decided December 7, 2010·No. AC 30366·Published·Cited by 2 cases

Opinion

Opinion

GRUENDEL, J.

The defendants, XL Specialty Insurance Company (XL), American Networks International, LLC (American), and Semac Electric Company, Inc. (Semac), appeal from the judgment of the trial court, rendered after a trial to the court, in favor of the plaintiff, Fibre Optic Plus, Inc. On appeal, the defendants *401 claim that the court improperly (1) rendered judgment more than 120 days after the completion date of trial in violation of General Statutes § 51-183b and (2) concluded that they waived application of the 120 day requirement set forth therein. Although we disagree with the trial court’s conclusion that the defendants waived application of § 51-183b, we nonetheless affirm the judgment of the trial court.

The following facts, as found by the court, and procedural history are relevant to the resolution of the defendants’ appeal. In the spring and summer of 2005, Darien High School was undergoing a large scale renovation project (project). Semac was the general contractor retained by the town of Darien to oversee the project, and American was a subcontractor employed on the project by Semac. Additionally, in accordance with General Statutes § 49-41 (a), 1 XL, a bonding company, served as the surety for a payment bond underwriting the work performed on the project. Shortly after construction commenced, American approached the plaintiff, seeking assistance in completing wiring connection services for new computers being installed in the high school as part of the project. Pursuant to an oral agreement with American, the plaintiff subsequently provided substantial services for the project, yet was never fully reimbursed by American for its work. As such, in March, 2006, the plaintiff filed a five count complaint against American, Semac and XL, 2 seeking *402 payment of the outstanding balance owed for services it rendered on the project.

In October, 2007, a four day trial to the court was held, with the close of evidence occurring on October 25, 2007. Following the close of evidence, extensive posttrial briefing ensued, and the final briefs were submitted on January 22,2008. On May 14,2008, in a memorandum of decision, the court ruled in favor of the plaintiff on counts two, three, four and five with respect to the liability of the defendants; however, the court did not award any damages to the plaintiff on those counts. With respect to count one, the court stated that it had “not felt sufficiently persuaded, in the absence of oral argument, as to which side must prevail, or, if the plaintiff prevails, which [theory] . . . would form the appropriate [basis for] recovery . . . .” The court further explained that it would “schedule a hearing in late May or early June, 2008, to consider argument of the parties” as to the appropriate basis for relief under count one and, at that time, would also “weigh and determine the costs, interest and attorney’s fees with [regard] to all counts.” 3

Despite the court’s scheduling proposal, by June, 2008, no hearing had taken place to resolve the lingering liability and damages issues. Then, on June 4, 2008, the *403 defendants filed an “objection to the court’s continued personal jurisdiction,” claiming that the court had failed to render judgment within 120 days of the completion date of the trial in violation of § 51-183b. As argued by the defendants, because the court had failed to render a timely judgment in accordance with § 51-183b, the court could not “retain continuing personal jurisdiction over the parties,” and any subsequent judgment against them would be voidable. On September 3, 2008, the hearing originally scheduled for May or June, 2008, was held. At the September 3, 2008 hearing, the court overruled the defendants’ objection to its “continuing personal jurisdiction,” rendered judgment in favor of the plaintiff on all counts, and awarded damages, including interest, attorney’s fees and punitive damages, in accordance with its ruling. This appeal followed.

Subsequently, this court granted the defendants’ motion for review of the trial court’s denial of their motion for articulation, directing the court to “articulate whether it [had] found a waiver [by the defendants] of the 120 day rule, and, if so, the factual basis underlying [this] conclusion.” In response, the court stated that the “defendants did impliedly, at least, waive the 120 day requirement,” and alternatively, “waiver was not necessary [under § 51-183b], because [completion of] the [trial] . . . did not occur until the court made its last determination” on September 3, 2008, with judgment being rendered that same day.

The defendants now claim that the court improperly rendered its September 3,2008 judgment more than 120 days after the completion date of trial in contravention of § 51-183b. Specifically, the defendants maintain that the 120 day time requirement began to run on the last day that posttrial briefs were submitted, or January 22, 2008. Therefore, the defendants argue, the court was required to render judgment on or before May 21, 2008, which it failed to do. Additionally, the defendants argue *404 that the court’s conclusion that they had waived the application of the 120 day time requirement was clearly erroneous. We address each of the claims in turn.

I

The defendants first claim that the court improperly rendered judgment more than 120 days after the completion of trial in violation of § 51-183b. In support of this claim, the defendants assert that the appropriate date for assessing when the 120 day period began to run was the date that the final posttrial brief was filed, or January 22, 2008, rather than the date of the final hearing and argument on September 3, 2008. Our case law is clearly to the contrary.

Section 51-183b provides in relevant part: “Any judge of the Superior Court . . . who has commenced the trial of any civil cause, shall have power to continue such trial and shall render judgment not later than one hundred and twenty days from the completion date of the trial of such civil cause. The parties may waive the provisions of this section.” (Emphasis added.) In construing the meaning of the phrase “ ‘completion date of the trial’,” our Supreme Court, in Frank v. Streeter, 192 Conn. 601, 604, 472 A.2d 1281 (1984), endorsed the principle that “ ‘completion’ has been held to encompass the availability of all the elements directly or indirectly to be considered [by the trial court] in the rendering of a decision.” More recently, this court has had the opportunity to elaborate on this principle in a case with a procedural posture similar to that in the present case.

Free access — add to your briefcase to read the full text and ask questions with AI

Fibre Optic Plus, Inc. v. XL Specialty Insurance, 8 A.3d 539, 125 Conn. App. 399, 2010 Conn. App. LEXIS 546 (Colo. Ct. App. 2010).

8 A.3d 539 (Fibre Optic Plus, Inc. v. XL Specialty Insurance) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Independent Party of CT-State Central v. Merrill
200 A.3d 1118 (Supreme Court of Connecticut, 2019)
Firbe Optic Plus, Inc. v. Xl Specialty Insurance Company
12 A.3d 1003 (Supreme Court of Connecticut, 2011)