This text of F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES, LLC v. B & B SITE DEVELOPMENT, INC. (F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES, LLC v. B & B SITE DEVELOPMENT, INC.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES, LLC v. B & B SITE DEVELOPMENT, INC., (Fla. Ct. App. 2021).

Opinion

DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT

F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES LLC, a foreign corporation, Appellant,

v.

B&B SITE DEVELOPMENT, INC., a Florida corporation, Appellee.

No. 4D19-3839

[February 3, 2021]

Appeal from the Circuit Court for the Nineteenth Judicial Circuit in and for Okeechobee, County; Laurie E. Buchanan, Judge; L.T. Case No. 472016CA000326.

Caryn L. Bellus and Barbara E. Fox of Kubicki Draper, P.A., Miami, for appellant.

Kevin S. Hennessy of Lewis, Longman & Walker, P.A., St. Petersburg, and Christopher D. Johns of Lewis, Longman & Walker, P.A., West Palm Beach, for appellee.

GROSS, J.

A general contractor and a subcontractor disagree over the scope of work required by a subcontract. Litigation ensued and both parties moved for summary judgment. The circuit court denied the contractor’s motion and granted summary judgment in favor of the subcontractor. We affirm the finding of liability on two counts of implied contract, but reverse and remand for a determination of damages.

Facts

F.H. Paschen, S.N. Nielson & Associates (the “GC”) was the general contractor on a project for the United States Postal Service to perform construction work at various locations, including the main post office in Okeechobee, Florida. The master contract with the Postal Service required the GC to “verify all dimensions shown of existing work . . . by actual measurement of the existing work,” and to report any discrepancies to the Postal Service’s contracting office prior to submitting a price proposal for a particular project.

The GC entered into a subcontract with B&B Site Development, Inc. (the “Sub”) that required the Sub to perform demolition and paving work for the parking lot of the Okeechobee post office.

Various documents used to solicit bids from potential subcontractors interchangeably used the terms “pavement,” “cement concrete pavement,” “existing Portland cement concrete pavement,” and “existing PCC pavement” to describe what was to be demolished and removed. The GC and the Sub exchanged information prior to the execution of the subcontract.

The eastern driveway was not laid with Portland cement but asphalt. The Sub’s principal examined the asphalt, which was only three years old, and found that it was in good condition and did not need replacing. The Sub’s measurements at the site showed 9,000 square yards of concrete, so the Sub submitted a lump-sum bid based on that measurement.

The GC failed to perform a pre-bid site walk to verify the area of concrete to be demolished. The GC incorrectly assumed that the entire parking lot was concrete and relied upon this mistaken assumption when it submitted a price proposal to the Postal Service. That proposal quoted a price for concrete removal that included the total area of all the pavement in the parking lot, including the asphalt eastern driveway.

The GC and the Sub entered into a subcontract in December 2014. The subcontract described the project as “USPS—Okeechobee FL MPO— Replace Pavement” and provided that the Sub would perform “the work described in Schedule A.” Schedule A described the scope of work as including demolition of “the existing concrete pavement.” The subcontract also stated that the terms of the subcontract constituted “the full and complete agreement between the parties,” with “[a]ll previous oral or written promises, negotiations, representations or agreements relating to the subject matter of [the subcontract being] hereby declared to be null and void.”

Shortly after the parties executed the subcontract, the Sub provided the GC with a “job sequencing narrative” that described a sequence of tasks that did not include demolishing or repaving the asphalt on the eastern driveway. The GC responded with an email that identified the asphalt eastern driveway as “Phase B5,” but which did not indicate that any work was to be performed there.

2 A problem arose when the project neared completion. The GC maintained that removal and replacement of the asphalt on the Phase B5 eastern driveway was within the scope of the subcontract, while the Sub disagreed, pointing to language in the subcontract that specified removal of concrete only.

Although the GC believed that replacement of the B5 asphalt fell withing the subcontract’s scope of work, it requested a price proposal from the Sub. The Sub provided a proposed work order to remove 561 square yards of asphalt pavement and to replace it “to match existing contracted work” at a price of $33,386.80.

The parties came to no agreement about this extra work, with the GC maintaining that it was included in the Sub’s original contract price and the Sub insisting that it was extra work outside of the subcontract. Nonetheless, the Sub proceeded with the asphalt work to avoid delaying the project, insisting that it still expected to be paid for it. The GC responded that the project architect would review the costs and proposals to “ensure that this area was not already included” in the subcontract.

The project architect reviewed the GC’s bidding documents and opined that the asphalt pavement area was included in the cost of the project.

The Sub replaced the existing asphalt in the B5 area under protest and sought $33,386.80 in compensation. The GC denied the Sub’s request for additional compensation, maintaining its previous position.

The Sub sued the GC in a three-count amended complaint for breach of contract, and two theories of implied contract—quantum meruit and unjust enrichment. The Sub sought damages of $33,386.80 or the reasonable value of the labor and materials it provided.

Both parties moved for summary judgment. The circuit court granted the Sub’s motion for summary judgment on all three counts, denied the GC’s motion, and entered judgment for $33,386.80 plus interest. This appeal ensued.

The Circuit Court Properly Determined that the Scope of the Subcontract was Limited to Concrete Removal

The central issue in this case is whether the removal and replacement of the asphalt pavement on the eastern driveway fell within the scope of

3 the contract. The circuit court correctly ruled that the work at issue was not covered by the subcontract.

“When the language of a contract is clear and unambiguous, courts must give effect to the contract as written and cannot engage in interpretation or construction as the plain language is the best evidence of the parties’ intent.” Talbott v. First Bank Fla., FSB, 59 So. 3d 243, 245 (Fla. 4th DCA 2011). A court must interpret a contract “in a manner that accords with reason and probability,” endeavoring to “avoid an absurd construction.” Katz v. Katz, 666 So. 2d 1025, 1028 (Fla. 4th DCA 1996).

A contract should be read as a whole. Discover Prop. & Cas. Ins. Co. v. Beach Cars of W. Palm, Inc., 929 So. 2d 729, 732 (Fla. 4th DCA 2006). Courts must give reasonable meaning to all provisions of a contract, rather than rendering part of the contract useless. Publix Super Mkts., Inc. v. Wilder Corp. of Del., 876 So. 2d 652, 654 (Fla. 2d DCA 2004). Specific provisions in a contract control over general provisions. Bridges v. City of Boynton Beach, 927 So. 2d 1061, 1063 (Fla. 4th DCA 2006). Furthermore, “the headings or subheadings of a document do not dictate the meaning of the entire agreement, especially where the literal language of the heading is contrary to the agreement’s overall scheme.” Hinely v. Fla. Motorcycle Training, Inc., 70 So. 3d 620, 624 (Fla. 1st DCA 2011).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Katz v. Katz
666 So. 2d 1025 (District Court of Appeal of Florida, 1996)
W&J CONST. v. Fanning/Howey Associates
741 So. 2d 582 (District Court of Appeal of Florida, 1999)
JH Jenkins Contractor, Inc. v. City of Denham Springs
216 So. 2d 549 (Louisiana Court of Appeal, 1968)
Commerce v. Equity
695 So. 2d 383 (District Court of Appeal of Florida, 1997)
Levine v. Fieni McFarlane, Inc.
690 So. 2d 712 (District Court of Appeal of Florida, 1997)
American Safety Insurance Service v. Griggs
959 So. 2d 322 (District Court of Appeal of Florida, 2007)
Solutec Corp. v. Young & Lawrence Associates, Inc.
243 So. 2d 605 (District Court of Appeal of Florida, 1971)
Diamond" S" Development Corporation v. Mercantile Bank
989 So. 2d 696 (District Court of Appeal of Florida, 2008)
Publix Super Markets v. Wilder Corp. of De
876 So. 2d 652 (District Court of Appeal of Florida, 2004)
Townsend Contracting v. JENSEN CIV. CONST.
728 So. 2d 297 (District Court of Appeal of Florida, 1999)
Southern Bell Tel. & Tel. Co. v. ACME, ETC.
418 So. 2d 1187 (District Court of Appeal of Florida, 1982)
City of Homestead v. Johnson
760 So. 2d 80 (Supreme Court of Florida, 2000)
Kovtan v. Frederiksen
449 So. 2d 1 (District Court of Appeal of Florida, 1984)
FOREST CONST. v. Farrell-Cheek Steel Co.
484 So. 2d 40 (District Court of Appeal of Florida, 1986)
De Lotto v. Fennell
56 So. 2d 518 (Supreme Court of Florida, 1952)
Broderick v. Overhead Door Co. of Fort Lauderdale, Inc.
117 So. 2d 240 (District Court of Appeal of Florida, 1959)
Discover Property & Cas. Ins. v. Beach Cars
929 So. 2d 729 (District Court of Appeal of Florida, 2006)
James A. Cummings, Inc. v. Young
589 So. 2d 950 (District Court of Appeal of Florida, 1991)
Corn v. Greco
694 So. 2d 833 (District Court of Appeal of Florida, 1997)
Dean v. Blank
267 So. 2d 670 (District Court of Appeal of Florida, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES, LLC v. B & B SITE DEVELOPMENT, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/fh-paschen-sn-nielsen-associates-llc-v-b-b-site-development-fladistctapp-2021.