Fesperman v. Silver Dollar City, Inc.

796 S.W.2d 384, 1990 Mo. App. LEXIS 1252, 1990 WL 118935
CourtMissouri Court of Appeals
DecidedAugust 16, 1990
DocketNo. 16335
StatusPublished
Cited by6 cases

This text of 796 S.W.2d 384 (Fesperman v. Silver Dollar City, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fesperman v. Silver Dollar City, Inc., 796 S.W.2d 384, 1990 Mo. App. LEXIS 1252, 1990 WL 118935 (Mo. Ct. App. 1990).

Opinion

WASSERSTROM, Senior Judge.

Plaintiff sues to collect the unpaid amount on a contract to supply trees. Defendant counterclaims for deficient performance by plaintiff. After trial without a jury, the trial court awarded damages to plaintiff on his petition and to defendant on its counterclaim. Defendant appeals from that portion of the judgment adverse to it. There being no appeal from the judgment on the counterclaim, only those facts pertaining to plaintiffs claim will be stated.

On October 27,1978, defendant issued its purchase order to plaintiff for a large number of trees including fifty-one sycamores, to be supplied for a new development referred to in the evidence as the Whitewater project. The purchase price was $55,130, of which defendant made an advance payment of $13,750. The order called for delivery in March 1979. However, by March 1979, the Whitewater project was not ready and the parties mutually agreed that the trees should be delivered to defendant’s Silver Dollar City theme park.1

Due to wet weather in Iowa, where plaintiff was to obtain most of the trees, delivery to plaintiff was delayed and the first trees did not arrive in Springfield until the first week of April, with further deliveries continuing through mid-May. The best time for planting trees of this kind was between November and the end of March or, at the latest, by mid-May. Nevertheless, plaintiff continued to supply trees for planting and defendant accepted those trees into June 1979.

Special difficulties existed with respect to the delivery of these trees because the [386]*386Silver Dollar City theme park was open to the public five days a week from the latter part of April to the end of May, leaving only two days within which to plant trees. After Memorial Day, the theme park was open to the public seven days a week and the time available for planting was still further restricted. Additionally, the topography of Silver Dollar City was such as to require much truck maneuvering to get the trees to the planting area, rendering it impossible to deliver more than four to five trees a day. By contrast, if the trees had been delivered at Whitewater, according to the original understanding, all the trees could have been planted in one week.

By Summer 1979, plaintiff still had thirty-three sycamore trees on hand, and it had become too late for planting. Plaintiff testified that the parties agreed that plaintiff should store the thirty-three trees at his Maplewood Gardens in Springfield until the Pall season and that plaintiff would be compensated for the care and storage of the trees until that time. Testimony was offered by defendant to the effect that it knew that the trees were being stored at Maplewood Gardens but believed them to be trees which had been previously delivered by plaintiff to Silver Dollar City and rejected by defendant.

In August 1979, the parties held a meeting at Maplewood Gardens. Defendant’s witness Graves testified that defendant’s purpose for the meeting was to get plaintiff to replace six trees which had been planted but which had died, and also to obtain a refund by plaintiff of the portion of defendant's $13,750 advance payment which represented trees which plaintiff had not delivered. Plaintiff testified that the purpose of the meeting was a proposal by defendant to rescind the old contract and supplant it with a new arrangement under which plaintiff would supply trees under an enlarged $85,000 landscaping budget for the Whitewater project. This new project would have included a number of sycamore trees.

During the course of the meeting, plaintiff stated to defendant’s representative that he would agree to the proposition provided he was given the exclusive right to furnish all the landscaping and further provided that defendant would furnish him with a $10,000 advance payment. Graves, one of the conferees on behalf of defendant, responded that he would talk to his supervisor about those conditions and then communicate with plaintiff further.

Immediately after that meeting, plaintiff began making inquiries of his suppliers as to availability of trees for the contemplated new project. However, by October he had heard nothing more from defendant. He then began making phone calls, followed by letter to Graves on October 3, 1979, and then a telegram to Graves dated October 24, 1979. Then plaintiff learned that competitors of his were putting in landscaping at the Whitewater project.

Finally, plaintiff was able to reach defendant’s representative Kreps and asked what was going on. Kreps answered that defendant was too big to do business with only one supplier. Plaintiff then asked what he was supposed to do with the thirty-three sycamores which he held in storage, to which Kreps answered that he did not know.

With that, plaintiff concluded that his contract with defendant was at an end, and he tried to find buyers for the thirty-three sycamore trees. He was unable to do so, and the trees, while in storage, died during the 1980 drought. Ultimately, they were cut up and burned.

Defendant’s points on appeal, briefly summarized, are as follows: (1) that plaintiff is not entitled to recover because he did not tender delivery of the thirty-three trees; and (2) plaintiff’s failure to deliver the trees was the result of wet weather in Iowa, which was a risk assumed by him.

I

Tender of Performance by Plaintiff

Defendant relies on § 400.2-5072 and § 400.2-301, which makes a seller’s right to recover under a sales contract contingent [387]*387upon delivery or tender of delivery. Plaintiff, on the other hand, relies on § 400.2-610(c) which excuses tender by the seller when the buyer repudiates the contract, thereby committing an anticipatory breach.

Here, defendant did clearly repudiate the contract. Under its evidence, it called the August meeting for the purpose of obtaining replacement of six trees which had died and “to discuss some credit arrangement that was due Silver Dollar City on the initial payment by them.” This demand by defendant for a refund on its advance deposit necessarily meant that it considered the 1979 contract at an end.

Moreover, its actions following the August meeting confirmed its repudiation of the contract. Despite Graves’ promise to further communicate with plaintiff, plaintiff testified and the trial court found that there was no further communication from Graves. The plaintiff tried by phone calls, a letter and a telegram to re-establish contact, without success. Finally, plaintiff did succeed in talking to Kreps, and when plaintiff asked what he should do with the thirty-three trees in storage, Kreps answered that he didn’t know.

All of this made perfectly plain to plaintiff that defendant no longer intended to recognize the 1979 contract or otherwise deal with him with respect to the thirty-three trees. Under those circumstances, a tender was futile and unnecessary. Indeed, it would be preposterous to require plaintiff to haul out to Silver Dollar City these very large trees, twenty-eight to forty-two feet in height, when defendant had made it clear that those trees would not be accepted.

Still further, defendant did not defend in the trial court on any theory of lack of tender. Instead, it defended on the wholly different and inconsistent theory that it had repudiated the contract because of unacceptable performance by plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beyerbach v. Girardeau Contractors, Inc.
868 S.W.2d 163 (Missouri Court of Appeals, 1994)
Phillips v. Hoke Construction, Inc.
834 S.W.2d 785 (Missouri Court of Appeals, 1992)
Skyles v. Burge
830 S.W.2d 497 (Missouri Court of Appeals, 1992)
E.D. Mitchell Living Trust v. Murray
818 S.W.2d 326 (Missouri Court of Appeals, 1991)
Mistler v. Mistler
816 S.W.2d 241 (Missouri Court of Appeals, 1991)
Ullius v. Ullius
814 S.W.2d 321 (Missouri Court of Appeals, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
796 S.W.2d 384, 1990 Mo. App. LEXIS 1252, 1990 WL 118935, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fesperman-v-silver-dollar-city-inc-moctapp-1990.