Ferrand v. Van Benthuysen

2 La. App. 8, 1925 La. App. LEXIS 334
CourtLouisiana Court of Appeal
DecidedMarch 30, 1925
DocketNo. 8861
StatusPublished
Cited by1 cases

This text of 2 La. App. 8 (Ferrand v. Van Benthuysen) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferrand v. Van Benthuysen, 2 La. App. 8, 1925 La. App. LEXIS 334 (La. Ct. App. 1925).

Opinion

BELL, J.

Plaintiff, a contractor, sues for $584.71, a balance alleged to be due for certain work involving the demolition and reconstruction of a building belonging to defendant. The petition sets up a written contract, with specifications, signed by plaintiff as contractor and defendant as owner. It is alleged that the entire work was to be done for $4,473.00; that after the building had been entirely demolished from one site and its foundations had been reconstructed on another site, and after the first certificate for partial payment of the contract had been issued and approved by the architect and had been partially paid by defendant, that defendant stopped all work under the contract, leaving as a balance due for brick, labor and services rendered the amount now claimed, to-wit: $584.71. It is further alleged in the petition that differences had arisen between plaintiff and defendant, the latter having made demands upon plaintiff which were unjust, unreasonable and contrary to the terms of the building contract, particularly in that defendant had demanded that plaintiff should demolish the work already completed, although same had been approved by the architect in charge; that plaintiff offered, within the provisions of the contract, to submit these differences to arbitration, but that defendant, without reason, refused so to do.

Defendant answered, admitting the contract alleged by plaintiff, except that the price should have been $4,673.00 instead of $4,773.00. He also admitted that the work was to be done under the direction of R. Spencer Soule, architect, whose powers were fixed in the contract and specifications. He also admitted that the specifications provided that any dispute arising as to quality or fitness of material or workmanship should be decided strictly by the architect, and that payments under the contract as it progressed were to be made as alleged in the petition. Defendant denied that plaintiff performed the work and furnished the material in accordance with the contract and specifications -and denied that the necessary certificate from the architect had been obtained; but he admitted that a certificate for $600.00 was obtained from the architect and paid by him. Defendant further denied that any itemized statement verified by the architect, was furnished, but admitted that he received an unverified statement showing a balance as now claimed by plaintiff, and at the same time he received an itemized statement from his architect showing the amount of work done by the contractor and upon this latter statement or certificate he paid the sum of $600.00. He denied owing the balance now claimed, but admitted that differences had arisen between him and plaintiff and that he had demanded that plaintiff should demolish the work already reconstructed at the new site because the foundations there had been constructed out of line and out of level, and that the bricks were laid without any cement in the mortar. Admitting that he refused to arbitrate, defendant averred that the contract did not provide for arbitration of such matters, but he admitted that amicable demand had been made upon him and that the architect did approve of the work done by the plaintiff and did issue the Certificate No. One which covered the work on the foundations and which he had paid before he saw the work. He then alleged he visited the work six days later and found that the foundations were out of line and out of level and the mortar useless and not up to specifications, and he [10]*10averred further that the approval of the work by the architect was in violation of ■ the contract, not binding upon him, and that he had paid the $600.00 on the first certificate issued in ignorance of the character of the work. Assuming the position .of plaintiff in reconvention, defendant alleged that the work done by plaintiff was of a value not exceeding $300.00 and that defendant had, therefore, been overpaid, and further that he called on plaintiff to demolish the work and reconstruct the foundations, and that plaintiff having failed to do so, he had the work done by another contractor at an additional cost of $100.00, and that this latter amount, together with the overpaid amount of $300.00, he was entitled to recover against plaintiff, and so prayed in reconvention.

Pending this suit, the plaintiff became a bankrupt, and his trustee was interpleaded, and after trial had on the issues here involved, there was judgment in favor of plaintiff’s trustee and against defendant for the amount sued upon and defendant’s re-conventional demand was dismissed. Prom this judgment defendant has appealed.

The important question in this case is one founded wholly upon issues of fact and is to be determined upon the evidence of six witnesses, three for plaintiff and three for the defendant. The trial judge, under these conditions, has rendered judgment in favor of the plaintiff. We are disposed to believe that our learned brother of the District Court, after hearing the evidence of witnesses divided in number, as just noted, was influenced in his final determination by the building contract and stipulations made part of that contract. Defendant admits that he signed the contract and the specifications, and that the .latter specifically provided that should any dispute arise as to the quality and fitness .of the material or workmanship, the decision should rest strictly with the architect. We find such a stipulation in the specifications and conclude, therefore, that unless the decision of the architect as rendered in.this case under the dispute which has arisen between the litigants is shown to be arbitrary and plainly contrary to the evidence, that such decision should be maintained.

We find from the evidence that the defendant paid the first certificate issued by the architect approving the work done up to the time that said certificate was issued. Defendant admits that he paid this certificate without examining the work and relied upon the certification made by his architect, who was of his own choosing. Defendant testifies that six days after making this payment, he went to the site at which the building was to be reconstructed, and found the foundations badly constructed, as set forth in his answer to this suit. It appears that in the early part of August, almost two months- after payment of this first certificate, and' after he had found the work unsatisfactory, he called upon Dr. Metz, a chemist, and Mr. Devereaux O’Reilly, an engineer and contractor, to examine the work as then constructed and to report their findings to him.- It appears that prior to calling upon these experts for their opinion, defendant instructed the architect and he in turn directed the plaintiff to cease all further work under the contract. We find from the report of the chemist and of the engineer employed by the defendant, that these gentlemen did find some defects in the work. Dr. Metz, however, who made the chemical examination as to the proportions of lime, sand and cement which should have been in compliance with the specifications in respect to the mortar to be furnished, declares that he found the mortar itself apparently without any adhesive qualities and that he could flake a good deal of it with a penknife as when lifting the top of a [11]*11cardboard box. This witness, however, failed to testify that there was no cement in the mortar, which seems to have been the main complaint made by defendant as to the mortar. On the contrary, this witness swears that neither he nor anyone else could say exactly what the proportion of cement was to lime and sand in the mortar as used in this work. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JH Jenkins Contractor, Inc. v. City of Denham Springs
216 So. 2d 549 (Louisiana Court of Appeal, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
2 La. App. 8, 1925 La. App. LEXIS 334, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferrand-v-van-benthuysen-lactapp-1925.