Fernholtz MacHinery Co. v. Wilson

5 P.2d 679, 118 Cal. App. 573
CourtCalifornia Court of Appeal
DecidedNovember 25, 1931
DocketDocket No. 4307.
StatusPublished
Cited by2 cases

This text of 5 P.2d 679 (Fernholtz MacHinery Co. v. Wilson) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fernholtz MacHinery Co. v. Wilson, 5 P.2d 679, 118 Cal. App. 573 (Cal. Ct. App. 1931).

Opinion

BURROUGHS, J., pro tem.

This action grows out of a contract made and executed between the Fulton Engineering Company, assignor of the plaintiff herein, and Lee W. Wilson and J. Andrew McLaughlin, the defendants. By the terms of the contract, the said assignor agreed to construct for the defendants a certain placer machine in accordance with the terms of said contract, and the defendants agreed to purchase the same.

It is alleged in the complaint that the contract was fully completed on the part of the plaintiff and its assignor; that by the mutual agreement of the parties certain changes were made which had been fully executed; that in addition to the above-mentioned placer machine the plaintiff had constructed for the defendants certain “gold saving devices”; that the purchase price of said placer machine was the sum of $14,500, of which sum $5,000 had been paid by the defendants; that the principal changes made in the construction of the said placer machine consisted in making the superstructure thereof of steel instead of wood, making the trucks of caterpillar type instead of wheel type, making the excavator of rehaul type instead of gravity return type, changing the hoist track cables and lines to accommodate, making a change in the drive to permit all power for the entire machine to be taken from one motor instead of two as originally planned; that all of the said changes were of the reasonable value of $2,500; that the “gold saving devices” were constructed according to certain models and plans furnished by the defendants, and that the reasonable value thereof was the sum of $1200; that plaintiff’s assignor furnished certain lumber, bolts and various materials of the reasonable value of $310; that it furnished certain steel tracks for the placer machine of the reasonable value of $160.

It is further alleged that in the erection of the machinery at the mine said plaintiff’s assignor furnished extra labor of the total value of $1800. It is further alleged in the complaint that all of the foregoing were furnished at the special instance and request of the defendants, for which *576 the said defendants agreed to pay the reasonable value thereof. The defendants admitted the making of the contract, but denied that the placer machine had been completed ; denied that any extras had been furnished or was a proper charge against them; alleged that the “gold saving devices” were manufactured by the plaintiff’s assignor and that the placer machine and the devices were intended by all the parties to co-ordinate and work as one unit, whereas they did not work together, and that neither the placer machine nor the devices were properly constructed. Many other allegations of the failure of the said machine and devices to meet requirements were alleged in the answer. The court found that the allegations of the complaint were true and those of the answer were untrue and rendered judgment against the defendants for the full amount claimed by the plaintiff.

It is first contended by the appellants that the evidence is insufficient to support the findings of fact and also that certain rulings of the trial court in relation to the admission and rejection of evidence were erroneous and prejudicial to the appellants’ rights. Under appellants’ claim that the findings of fact are without support in the evidence, it is unnecessary to cite authority to support the well settled rule of law that if the findings are supported by any substantial evidence, this court cannot interfere. In the light of this ruling we will examine the evidence.

It is admitted that the contract sued upon was executed by the parties as set forth in the pleadings; that two payments of $2,500 each were made by the defendants.

F. A. McAllister, who was one of the partners in the Fulton Engineering Company, testified in substance, that after the contract had been signed, the Fulton Engineering Company prepared designs and shop working details for the construction of the placer machine. The drawings were made as the work proceeded. The defendants saw the drawings and plans as the work progressed. The parties to the contract had many discussions over them, and the defendants _ never made any objections. The conditions to be met in the use of the machine and the handling of the material were discussed. There were certain alterations suggested. Mr. McLaughlin suggested making the excavator rolling type instead of gravity return type. This *577 was one of the principal changes in the machine. The defendants saw the changes in the working plan. “My recollection is that they were both pleased with it; what they wanted.” That was the substance of what they said. Another suggested change was made at the instance of the defendant McLaughlin; that the trucks were to be made of the caterpillar type instead of the wheel type. There was a discussion at the time as to the cost of such a change, and the witness told McLaughlin then that the added cost of that would be about $1500. And there was some further talk about how that expense could be avoided at that particular time, and that that difficulty was avoided by omitting the true tractor type and building the truck in such a fashion that power could be applied later. At the same time, it became necessary, on account of the fact that power might be applied directly to the trucks to change the substructure from wood to steel. This was discussed with Mr. McLaughlin. There was not an exact discussion as to what that particular construction would cost. Mr. McLaughlin and Mr. Wilson saw the drawings. They were at the Fernholtz Machinery Company, where the work was being done. They both said they were well pleased with the work. The contract as originally written called for use of one gas-engine or motor on the hoist for excavation machinery, and called for Wilson and McLaughlin to furnish an auxiliary engine for driving of the screening and drilling apparatus. In discussing the matter with them, it was agreed to make a change that would enable them to cut out the auxiliary engine. McLaughlin brought the subject up; he told us to go ahead and do it. We suggested the use of a Holt tractor type model of a larger size than indicated in the contract. Mr. McLaughlin acquiesced in the use of that model. Drawings were made so that machine could be built with that model of engine. The contract provided that the defendants were to furnish certain parts which are referred to in the contract as the “gold saving devices”. The witness had his first conversation about manufacturing them about a month after the contract was signed. Work had already begun on the dredger machine itself. The witness also testified that the various items of machinery were completed according to the contract, except where modified by the agreement of *578 the parties, and that these modifications were executed according to the said agreements; that the “gold saving devices” were manufactured according to models which were furnished to them by the defendants. The witness also testified that when completed, the machinery was all loaded f. o. b. the cars Los Angeles. It was transported on the cars to Goldfield, Nevada, for shipment to Lida, Nevada, where it was unloaded and shipped by truck from thence to the point where the plant was to be erected neat Lida, Nevada. The witness further testified that an engineer was sent upon the ground, who erected the machinery as per the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maravilla v. Los Angeles Dodgers CA2/2
California Court of Appeal, 2016
Holmes Packaging MacH. Corp. v. Bingham
252 Cal. App. 2d 862 (California Court of Appeal, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
5 P.2d 679, 118 Cal. App. 573, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fernholtz-machinery-co-v-wilson-calctapp-1931.