Fehler v. Gosnell

35 S.W. 1125, 99 Ky. 380, 1896 Ky. LEXIS 96
CourtCourt of Appeals of Kentucky
DecidedMay 26, 1896
StatusPublished
Cited by31 cases

This text of 35 S.W. 1125 (Fehler v. Gosnell) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fehler v. Gosnell, 35 S.W. 1125, 99 Ky. 380, 1896 Ky. LEXIS 96 (Ky. Ct. App. 1896).

Opinion

JUDG3 Du RELLE

delivered the opinion oe tiie court.

These cases have been heard together, and are appeals from judgments enforcing liens for the improvement of a part of Oak street, in Louisville, by original construction of the carriage-way.

The case of Dickson v. Gleason presents a question of jurisdiction not presented in the other case, which may be first disposed of. It was a suit upon apportionment warrants for street improvements, and the amount adjudged in the court below, as a lien upon the property of any one of the defendants, was less than $100, though the aggregate amount of the judgments is more than that sum.

It has been settled in this State that separate judgments [384]*384can not be added together, in order, to give jurisdiction by the amount involved. “The legal questions involved may be identical, but the judgments are entirely distinct.” (Zabel v. Harris, 82 Ky., 475; Oswald v. Morris, 92 Ky., 52). But the question remains whether this court has jurisdiction of the appeal in this case, irrespective of the amount of the-judgment.

Section 950, Kentucky Statutes, provides: “No appeal shall be taken to the Court of Appeals from a judgment for the recovery of money or personal property, if the value in controversy be less than one hundred dollars, exclusive of interest and costs, nor to reverse a judgment granting a divorce. ... In all other civil cases the Court of Appeals shall have appellate jurisdiction over the final orders and judgments of all courts.”

In common acceptation the words “judgment for the recovery of money or personal property” imply a personal judgment. In this procedure no personal judgment was sought or obtained. The proceeding was in rem against the property, and provides for a sale of the land. There seems little difference beween the judgment in this case for the sale of land under a proceeding in rem to satisfy the lien upon it, and a judgment for the recovery of land, which it is conceded may be brought to this court by appeal, irrespective of the value of the land. (Smith v. Moberly, 15 B. M., 72.)

In our opinion a judgment in rem to enforce a street assessment lien may be appealed without regard to the amount of money for which the lien is adjudged. The next question for decision is whether the ordinances providing for the improvements were so passed as to be valid.

By section 2834, Kentucky Statutes (a section of the act [385]*385for the government of cities of the first class), it is provided that . . . “no ordinance for any original improvement mentioned in this act shall pass both boards of the general council at the same meeting, and at least two weeks shall elapse between the passage of any such ordinance from, one-board to the other.”

In the case of Fehler v. Gosnell, the ordinance providing for the improvement passed the lower board on April 5th, and the upper board on April 19, 1894; and the appellants contend that two weeks did not “elapse” between the votes of the two boards, within the meaning of the statute. It is earnestly contended by counsel for appellants — and much authority from other States is cited in support of their position — that the intent of the statute was to provide for fourteen full days between the days of the passage of the-ordinance by the respective boards; but this contention does not seem to us to be supported either by the ordinarily accepted use of the language or by the statutory rule of construction of this State. In ordinary language a provision that two weeks must elapse between two acts would be considered as fulfilled by the first act occurring Thursday, and the second act occurring Thursday two weeks thereafter.

Moreover, section 453, Kentucky Statutes, provides that “'if a statute requires a notice to be given, or any other-act to be -done a certain time before any motion or proceeding, there must be that time, exclusive of the day for such motion or proceeding; but the day on which such notice is given or such act is done may be counted as one day and part of the time.”

It is to be observed that the time required by section 2834-of the statutes is between the passage by one board and the passage by the other, and is not between the day on which [386]*386it is passed by one board and the (Lay on which it is passed by the other.

Without undertaking to answer in detail the ingenious argument of counsel for appellant, it is sufficient to say that, in our opinion, the statute requires only that the passage by the first board shall be fourteen days before the passage by the other board; and that, in this case, that provision has been complied with. (Woods v. Patrick, Hardin, 457; Pollard v. Yoder, 2 A. K. Marshall, 264; Ogden v. Redman, 3 A. K. Marshall, 234; Sanders v. Norton, 4 Monroe, 464; Wood v. Commonwealth, 11 Bush, 220; and Mooar v. Bank of Covington, 80 Ky., 305.) Nor can we concede much force to the contention that section 453 of the statutes, being a general law of construction, must yield to the peculiar language employed in the act for the government of cities of the first class. The latter act is also a general law, and must be so under the Constitution.

The next objection to the judgments in these cases is based upon section 67 of the act for the government of cities of the first class (Kentucky Statutes, section 2829), which provides that whenever the board of public works shall order any work to be done, to be performed by independent contract, there shall be prepared and placed on file in said office complete drawings and specifications of said work. “Thereupon said board shall cause a notice to be published in one daily or weekly newspaper, of general circulation, published in said city, once in each week for two weeks, informing the public of the general nature of the work,- of the fact that the drawings and specifications are on file in said office and of the nature and extent of the bond or security required, and calling for sealed proposals for said work by a day not earlier than ten. days after the first of said publications.”

[387]*387Appellants claim that the demurrer to the petition should have been sustained, because it did not allege that the notice informed the public of the general nature of the work or of the fact that the drawings, etc., were on file in the office of the board or gave information of the nature or extent of the bond or security required.

The averment of the petition is as follows:

“And the plaintiffs say that the said board of public works caused to be printed and published, on the 5th and 18th days of April, 1894, in and by the said Evening Post and Louisville Anzeiger, advertisements; that, up to 12 m. on the 18th day of April, 1894, bids, offers and proposals would be received by said board of public works from persons offering, proposing and bidding to furnish all necessary labor and material therefor and to construct and complete the improvement of the carriage-way of Oak street, 30 feet in width, from the west line of 15th street to the center line of 16th street with the material and in the manner as prescribed by it and as provided for in the ordinance hereinbefore referred to as approved March 1, 1894.”

After the demurrer was overruled, the defendants in each case pleaded over and filed with their answers copies of the notice which was actually given, and averred failure in said notices to comply with the provisions of the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Corbin Ex Rel. Moore v. Rains
140 S.W.2d 1057 (Court of Appeals of Kentucky (pre-1976), 1940)
Southern Mining Co. v. Childers
142 S.W.2d 995 (Court of Appeals of Kentucky (pre-1976), 1940)
Hunt-Forbes Construction Co. v. City of Ashland
96 S.W.2d 854 (Court of Appeals of Kentucky (pre-1976), 1936)
Clingingsmith v. Jackson Dairy Co.
211 N.W. 413 (Supreme Court of Iowa, 1926)
Realty Savings Co. v. Southern Asphaltoilene Road Co.
202 S.W. 679 (Court of Appeals of Kentucky, 1918)
American Car & Foundry Co. v. Sellards
154 S.W. 897 (Court of Appeals of Kentucky, 1913)
Barber Asphalt Paving Co. v. City of Indianapolis
101 N.E. 31 (Indiana Court of Appeals, 1913)
Napier v. Bowling
139 S.W. 942 (Court of Appeals of Kentucky, 1911)
Johnson v. Wilson
134 S.W. 1141 (Court of Appeals of Kentucky, 1911)
Barber Asphalt Paving Co. v. City of Louisville
97 S.W. 31 (Court of Appeals of Kentucky, 1906)
Mudge v. Walker
122 Ky. 29 (Court of Appeals of Kentucky, 1906)
Orth v. R. B. Park & Co.
79 S.W. 206 (Court of Appeals of Kentucky, 1904)
Pfaffinger v. Kremer
74 S.W. 238 (Court of Appeals of Kentucky, 1903)
Barber Asphalt Paving Co. v. Garr
73 S.W. 1106 (Court of Appeals of Kentucky, 1903)
Young v. City of Tacoma
71 P. 742 (Washington Supreme Court, 1903)
Shake v. Smith
157 Ind. 401 (Indiana Supreme Court, 1901)
Barfield v. Gleason
63 S.W. 964 (Court of Appeals of Kentucky, 1901)
Richardson v. Mehler
63 S.W. 957 (Court of Appeals of Kentucky, 1901)
State ex rel. Wheeler v. District Court
83 N.W. 183 (Supreme Court of Minnesota, 1900)
City of Louisville v. Mehler
56 S.W. 712 (Court of Appeals of Kentucky, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
35 S.W. 1125, 99 Ky. 380, 1896 Ky. LEXIS 96, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fehler-v-gosnell-kyctapp-1896.