Federal Contracting Co. v. Board of Supervisors

153 Iowa 362
CourtSupreme Court of Iowa
DecidedDecember 18, 1911
StatusPublished
Cited by4 cases

This text of 153 Iowa 362 (Federal Contracting Co. v. Board of Supervisors) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Contracting Co. v. Board of Supervisors, 153 Iowa 362 (iowa 1911).

Opinion

Weaver, J.

Drainage district No. 5, in Webster county, having been duly established, the contract for constructing the ditch was let to the plaintiff at a stated price per cubic yard of excavation. 'Eighty percent of the compensation thus agreed upon was to be paid as the work progressed upon monthly estimates made by the engineer in charge of the construction. Concerning the remaining twenty percent of the sum thus earned, the contract pro[364]*364vided that, “when said improvement is completed to the satisfaction of the engineer in charge of the work and accepted by the board of supervisors of Webster county, the engineer shall certify such facts to the county auditor and the county auditor shall draw a warrant for the balance due from Webster county.”

Plaintiff alleges that it excavated the ditch according to contract; that the same was done under the charge and direction of engineers appointed by the board of supervisors for that purpose; that said engineers made and reported monthly estimates of the work done during the period of its prosecution; and that upon said estimates plaintiff has been paid eighty percent of the contract price for its services; but, notwithstanding the entire work called for by said contract has been fairly and fully performed in the manner provided by said agreement, the defendants refuse to pay the remaining twenty percent of the stipulated compensation, or to issue warrants therefor, or to make assessment upon the drainage district to provide the means for such payment. It is further alleged that defendants, with some of the property owners within the district, have wrongfully conspired to cheat and defraud the plaintiff out of the unpaid remainder of the contract price for the work, and that in pursuance of such unlawful confederation the county engineer, who is made a party defendant, has corruptly and without cause refused the plaintiff’s demand that he certify to the county auditor the completion of the ditch according to contract. It is still further charged that as part of said alleged conspiracy the supervisors of said county wrongfully agreed that, notwithstanding any certification which might be made by the engineer of the entire performance of the contract, they would not perform the duty imposed upon them by law to order the issuance of warrants for the payment due to the plaintiff. It is also charged that the objections made before the board of supervisors to the payment of [365]*365plaintiff’s claim have not been made in good faith, but in pursuance of a conspiracy to cheat and defraud the plaintiff. It is also alleged that moneys raised and appropriated for the construction of the ditch are now in the treasury of the county, and subject to warrant thereon for the payment of the claim in suit. Mandamus is therefore prayed to compel the engineer to issue certificates to the auditor and board of supervisors of the completion of the ditch according to contract, and to compel the auditor to issue his warrant for the payment of the balance due to the plaintiff; and, in the event that funds liable to such payment are not found in the hands of the treasurer, then the board of supervisors be directed to make the proper levy, or to sell the necessary bonds to provide means with which such warrant may be paid.

The defendants concede the execution of the contract with the plaintiff, and the performance by the latter of a large amount of work in the construction of the ditch, and the payment thereof of at least eighty percent of the stipulated price. They deny that the work has been completed according to contract, or that plaintiff is entitled to demand or receive the remainder of the contract price, or any part thereof. They also deny all charges of conspiracy and wrongdoing. They further aver that the plaintiff’s work; so far as done, has been performed in a negligent and unskillful manner; that the width of the berm provided for in the contract has not been left as agreed upon, with the result that much of the dirt and sods thrown out of the ditch have fallen or been washed by the rains back into the excavation; that the slope of the banks of the ditch has been made much steeper than was agreed upon; that in many places ■ the ditch as made is less in cross section than is called for by the contract, and overhanging sods and dirt have not been removed; that the bottom of the ditch has been left in rough and irregular condition, and pot in accordance with the grades, plans, and specifications [366]*366provided for the guidance of the plaintiff. It is also alleged that by the terms of the contract the plaintiff undertook and agreed to keep each mile of the ditch in good condition and repair at its own expense until the same was finally accepted by the parties of the first part, each mile to be accepted by the first parties when completed according to the specifications and terms of the contract; but defendants charge that plaintiff has wholly failed in the performance of this duty, and aver that no mile of said ditch has even been accepted, and that no mile of its course has’ in fact ever been completed or kept in repair according to the contract. Other matters are pleaded, but sufficient has been stated for the purposes of this opinion.

The engineer, answering separately, takes issue upon the allegations of the petition as against himself, and denies the completion of the work, setting out numerous details with respect to which the plaintiff is alleged to have failed in the due performance of its contract. A very large amount of testimony was heard, and at the close of the trial the court found the plaintiff not entitled to the relief prayed for, and dismissed the petition.

In nearly all essential particulars, this case is quite parallel in fact and circumstance with that of Littell v. Webster County, reported in 152 Iowa, 206, and reference thereto will sufficiently disclose the view taken by this court of the law applicable to issues of this nature. There is no occasion, therefore, for us to repeat the discussion there found, or to review again the authorities cited by counsel.

I. Mandamus: nature of wnt. It was there held that, assuming mandamus to be under some circumstances an available remedy to control the action of a drainage engineer and board of supervisors, who refuse to approve the work of a contractor, it must be limited to cases where fraud is shown, and that it will not lie to review errors of judgment on part of such officers. It requires [367]*367but little reflection to see the justice and propriety of this rule. Generally speaking, the sole office of mandamus is to compel the officer to whom it is directed to act, and if the thing which he neglects to do involves the exercise of judgment or discretion it is not within the province of the court to prescribe or order the result or conclusion at which he must arrive. In other words, while it may compel him to act, it can not control his judgment. His judgment may be erroneous, and the conclusion at which he arrives may be radically wrong, but the remedy of the party suffering prejudice therefrom is not to be found in mandamus. If in fact he has acted, and fraud and collusion are not made to appear, then nothing is left to which such proceedings are applicable. In point upon this discussion, see Woodbury Co. v. Talley, 147 Iowa, 498.

2. Same: burden of proof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gordon Construction Co. v. Board of Supervisors
72 N.W.2d 551 (Supreme Court of Iowa, 1955)
Bernstein v. City of Marshalltown
248 N.W. 26 (Supreme Court of Iowa, 1933)
Farmers Loan & Trust Co. v. Wright County
191 Iowa 825 (Supreme Court of Iowa, 1921)
Monter v. Board of Supervisors
187 Iowa 625 (Supreme Court of Iowa, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
153 Iowa 362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-contracting-co-v-board-of-supervisors-iowa-1911.