Fed. Energy Regulatory Comm'n v. Powhatan Energy Fund, LLC

345 F. Supp. 3d 682
CourtDistrict Court, E.D. Virginia
DecidedSeptember 24, 2018
DocketCivil Action No. 3:15cv452
StatusPublished
Cited by2 cases

This text of 345 F. Supp. 3d 682 (Fed. Energy Regulatory Comm'n v. Powhatan Energy Fund, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fed. Energy Regulatory Comm'n v. Powhatan Energy Fund, LLC, 345 F. Supp. 3d 682 (E.D. Va. 2018).

Opinion

M. Hannah Lauck, United States District Judge

This matter comes before the Court on the Joint Motion to Dismiss (the "Motion to Dismiss") filed by Respondents Powhatan Energy Fund, LLC ("Powhatan"), Houlian "Alan" Chen ("Chen"), HEEP Fund, Inc. ("HEEP Fund"), and CU Fund, Inc. ("CU Fund") (collectively, "Respondents"). (ECF No. 95.) Respondents contend that the Federal Energy Regulatory Commission ("FERC" or the "Commission") brought this action beyond the applicable statute of limitations, that FERC does not have the authority to seek disgorgement as a civil penalty, and, assuming disgorgement is available, that it is also barred by the statute of limitations. (Mem. Supp. Mot. Dismiss 1, ECF No. 96.) FERC opposed the Motion to Dismiss, and Respondents replied. (ECF Nos. 99, 106.) Accordingly, the matter is ripe for disposition.

The Court dispenses with oral argument because the materials before it adequately present the facts and legal contentions, and argument would not aid the decisional process. The Court exercises jurisdiction pursuant to 16 U.S.C. § 823b(d)(3)(B)1

*686and 28 U.S.C. § 1331.2 For the reasons that follow, the Court will deny the Motion to Dismiss.

I. Factual and Procedural Background

An earlier decision by this Court concluded that its de novo review of FERC's imposition of penalties required application of the Federal Rules of Civil Procedure and the Federal Rules of Evidence. Fed. Energy Regulatory Comm'n v. Powhatan Energy Fund, LLC ("FERC I "), 286 F.Supp.3d 751 (E.D. Va. 2017). FERC I contains a detailed explanation of the two administrative procedures available in 16 U.S.C. § 823b : the typical administrative process, which this Court has dubbed the "Default Option," and the uncommon administrative scheme, which this Court has called the "Alternate Option," at issue here. The determination below presumes familiarity with FERC I .

A. Factual Background 3

Respondents consist of Chen and various financial entities on whose behalf Chen traded energy for the approximately two months at issue in this case, between June 1, 2010, and August 3, 2010 (the "Two-Month Alleged Manipulation Period"). Chen owns the entirety of Respondents HEEP Fund and CU Fund. Respondents conducted financial trades through the wholesale electricity market administered by PJM Interconnection, LLC ("PJM"), an organization that operates various electricity markets throughout the Mid-Atlantic. Certain energy trades qualified market participants to receive a payment, known as a "Marginal Loss Surplus Allocation," or MLSA, which PJM distributed to customers making certain trades. (Am. Compl. Ex. 1 ("Penalty Order") ¶ 2, ECF No. 93-1.) FERC alleges here that, during the Two-Month Alleged Manipulation Period, Respondents "designed and implemented a fraudulent ... trading scheme to receive excessive amounts of MLSA payments," by manipulating "day-ahead" and "real-time" energy trades to engage in wash trades: "trades that are pre-arranged to cancel each other out and involve no economic risk." (Id. ¶¶ 3, 6.)

FERC became aware of Respondents' purportedly manipulative activities after PJM received two complaints from a market participant about someone "trying to game the system." (Id. ¶ 26.) In August 2010, in response to these complaints, PJM submitted a "referral" to the Commission's Office of Enforcement ("Enforcement"), alerting the Commission to Respondents' allegedly fraudulent behavior and setting off the investigations that ultimately resulted in this action.4 (Id. ) That same month, Enforcement began investigating Respondents. On August 25, 2010, the Commission issued an order formalizing the investigation. The investigation, while formal, was not adversarial. See *68718 C.F.R. § 1b.13. Under applicable regulations, the investigation became formal because FERC issued an Order of Investigation.5 On August 9, 2013, after nearly three years of formal investigation, Enforcement staff issued letters of preliminary findings to Respondents "explaining the factual and legal bases for its preliminary findings of violations." (Id. ¶ 30.) Respondents replied to the letters on October 9, 2013.

On August 5, 2014, almost one year later, four years after the Commission began investigating Respondents, and more than four years after the Two-Month Alleged Manipulation Period, the Office of the Secretary issued a Notice of Alleged Violations. Settlement discussions failed, and Enforcement issued Respondents a notice of its "intent to recommend the initiation of a public proceeding against Respondents" (the "Notice"). Respondents replied to the Notice on September 24, 2014. The Notice and Respondents' opportunity to reply constituted the first procedural requirement with which the Commission had to comply in the investigation and penalty assessment process.6 Respondents submitted their response, and almost two months later, on December 17, 2014-four years and four months after the end of the Two-Month Alleged Manipulation Period-the Commission issued an Order to Show Cause.7 The OSC constituted the second procedural requirement-and the first process compelled by statute-with which the Commission had to comply.8 See *68816 U.S.C. § 823b(a) ("After notice and an opportunity for public hearing, the Commission may issue such orders as necessary to require compliance ...." (emphasis added) ).

The OSC alleged Respondents violated the statute and regulation forbidding the use of manipulative behaviors in connection with the purchase or sale of electric energy:9 16 U.S.C. § 824v(a)10 and 18 C.F.R. § 1c.2,11 respectively. The OSC recommended that the Commission assess penalties and profit disgorgement against each of the Respondents in the following amounts:

CU Fund: $10,080,000 civil penalty; $1,080,576 disgorgement;
HEEP Fund: $1,920,000 civil penalty; $173,100 disgorgement;
Powhatan: $16,800,000 civil penalty; $3,465,108 disgorgement; and,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FERC v. Powhatan Energy Fund, LLC
949 F.3d 891 (Fourth Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
345 F. Supp. 3d 682, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fed-energy-regulatory-commn-v-powhatan-energy-fund-llc-vaed-2018.