LARAMORE, Judge.

This suit was brought by plaintiff Far-well Company, Inc., to recover from defendant the sum of $35,184.96, which *948 amount was withheld from the amount payable under a contract as the result of a change order which modified the contract so as to permit plaintiff to install copper tubing in lieu of “copper or brass pipe” specified in the contract. The tubing was admittedly not as expensive as the pipe.

The facts necessary to this decision are briefly these: On February 7, 1948, plaintiff entered into a contract with defendant’s Corps of Engineers under which plaintiff was to furnish the materials and perform the work for installation of all mechanical work in the main hospital and the boiler house of the Veterans’ Administration Hospital, Shreveport, Louisiana, in accordance with the contract documents, plans, and specifications. The specifications were drawn up by a firm of architeets-engineers under a separate contract between it and the defendant. The firm’s consulting engineer, in preparing the plumbing specifications, used without change, the Corps of Engineers’ Standard Guide Specifications, C. E. — 300.02, dated April 7, 1947, which forms paragraph 45-15b of the contract specifications and is as follows:

“b. Brass or Copper: Pipe used for domestic hot and cold water, return circulating hot water, and chilled water, except underground pipe 3 inches in diameter and larger, shall be brass or copper. Threaded fittings shall be brass. Threadless fittings for brazing with silver solder will be acceptable, except for swing joints. The material and dimensions of threadless fittings shall conform to the requirements of Federal Specifications WW-p-460.”

Although the Corps of Engineers-’ Standard Guide Specifications 300.02 were amended by the addition of the words “copper tubing will not be acceptable” prior to the issuance of the invitation for bids on the job here in question, neither the firm’s consulting engineer nor the plaintiff were informed of this modification and the later addition does not appear in paragraph 45-15b of the contract specifications.-

Plaintiff entered on the construction work using type B copper tubing instead of “brass or copper pipe” as called for in the specifications. On or about December 3, 1948, the architeets-engineers directed plaintiff to suspend further installation of type B copper tubing pending an interpretation of the specifications. It was thereafter determined that the type B copper tubing did not comply with the specifications, but to avoid delay, plaintiff was permitted to continue with the installation of said copper tubing. At that time a change order was issued, together with findings of fact, modifying paragraph 45-15b to permit the use of copper tubing and making an equitable adjustment in the contract price of $35,184.96, the difference in the market price of copper pipe and type B copper tubing.

Plaintiff contends that paragraph 45-15b of the contract specifications is ambiguous where it specifies brass or copper “pipe” and threaded fittings and also permits the use of threadless fittings; that the term “pipe” in specifications and in trade usage includes “tubing” and that the two terms do not have technically exclusive meanings; that it bid on type B copper tubing; that such tubing was satisfactory for the job; and that the Government was not justified in reducing the contract price when plaintiff was permitted to continue installing tubing.

Defendant in its brief recites that the defendant is not contending in this case that type B copper tubing would not give satisfactory results. The Government concedes that it permitted the use of the tubing and that it is adequate for the job but it contends it permitted its use only to expedite the job and feels that an adjustment downward in the contract price should be made because of the lesser expense entailed by the contractor in obtaining copper tubing. The Government, contrary to plaintiff’s contention, argues that the use of the term “pipe” in the specifications does not within the ordinary trade usage also mean “tubing”.

*949 The question of whether or not “pipe” also means “tubing” was decided by this court when the case was previously before it on cross-motions for summary judgment, Farwell Co., Inc., v. United States, 115 F.Supp. 477, 126 Ct.Cl. 317, wherein we held that plaintiff was not justified in interpreting paragraph 45-15b as written to permit the use of copper tubing. However, the court at that time found that there were genuine issues of material fact as to (1) whether the defendant has previously accepted copper tubing under the same specification provision as paragraph 45-15b, and (2) whether copper tubing was suitable or conformed with the technical requirements of the contract specifications. Thus, the case was remanded to the Commissioner for further proceedings.

Trial on the above issues was had and in support of the first issue above plaintiff claims that shortly prior to bidding on the contract here in suit it performed the mechanical work on the Veterans’ Administration Hospital, Big Springs, Texas, as a subcontractor, and that type B copper tubing was installed, approved, accepted, and paid for under the same specification provision as paragraph 45-15b here in question.

This contention of plaintiff is in error since the bid on the Big Springs, Texas, job was qualified with a statement that it was based on tubing and the bid Was accepted on that basis. Plaintiff, in arguing against defendant’s contention that the bid was qualified to the extent hereinbefore noted, states in its reply brief that “ * * * there is not one scrap of evidence in the record concerning the Big Springs Hospital or any ‘qualification’ of the bid on that job.” In response to this statement, we simply point to finding 12, which is taken from an exhibit introduced by plaintiff, and to finding 13. The statements contained in the contracting officer’s memorandum, and the decision of the Claims and Appeals Board therein quoted, indicate without question that the bid on the Big Springs project was qualified, to the extent that it permitted the use of copper tubing under a specification' similar to 45-15b of the contract in question in the suit now before us. Moreover, this issue was completely abandoned by plaintiff on trial of the case; therefore, any further discussion is unnecessary.

As to the second issue, plaintiff claims that the copper tubing was suitable and conformed with the technical requirements of the contract specifications, and its use should, therefore, be permitted without any reduction in the contract price.

The Government has stated in its brief that it does not contend that the copper tubing was not suitable. It does say that it did not conform with the requirements of the contract specifications, and quite obviously it did not. It is of no concern to plaintiff why the Government specified brass or copper “pipe” instead of “tubing,” and it was not within plaintiff’s province to substitute its judgment for that of the Government by deciding that tubing was satisfactory when pipe was specified. The Government may have had many reasons for requiring pipe instead of tubing, but in any event the specifications called for pipe and the Government had a right to expect that pipe Would be used.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elastomeric Roofing Associates, Inc. v. United States
26 Cl. Ct. 1106 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
148 F. Supp. 947, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farwell-company-v-united-states-cc-1957.