Farrow Group Inc v. Detroit Land Bank Authority

CourtMichigan Court of Appeals
DecidedJanuary 7, 2021
Docket351138
StatusUnpublished

This text of Farrow Group Inc v. Detroit Land Bank Authority (Farrow Group Inc v. Detroit Land Bank Authority) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farrow Group Inc v. Detroit Land Bank Authority, (Mich. Ct. App. 2021).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

FARROW GROUP, INC, UNPUBLISHED January 7, 2021 Plaintiff-Appellant,

v No. 351138 Wayne Circuit Court DETROIT LAND BANK AUTHORITY, LC No. 17-002792-CK

Defendant-Appellee.

Before: STEPHENS, P.J., and SERVITTO and LETICA, JJ.

PER CURIAM.

Plaintiff, Farrow Group, Inc., (hereinafter, “Farrow”) appeals as of right a supplemental opinion and order, issued after remand from this Court1, granting summary disposition to defendant, Detroit Land Bank Authority (hereinafter, “DLBA”) with respect to Farrow’s promissory estoppel claim. We affirm.

I. STATEMENT OF FACTS

This case arises out of a call for bids from contractors for demolition of various properties

in Detroit. This Court previously summarized the facts leading to the first appeal to this Court in its earlier opinion:

DLBA is an independent public authority that was statutorily created to deal with vacant and abandoned property in the City of Detroit. As such, it has demolished more than 10,000 structures since 2014. Farrow Group, Inc. (“Farrow”), is a demolition contractor who performed demolition work for DLBA in the past.

1 Farrow Group, Inc v Detroit Land Bank Authority, unpublished per curiam opinion of the Court of Appeals, issued May 21, 2019 (Docket No. 341822),

-1- In June 2016, Farrow submitted bids to the Detroit Building Authority (“DBA”) for demolition work on properties owned by the DLBA pursuant to DBA’s request for proposals (“RFP”). The DBA was acting as the DLBA’s procurement manager. The bids were for demolition work on approximately 155 properties located in the City of Detroit. Farrow claims it had contracts with the DLBA to perform the demolition work on these properties and that it purchased more than $700,000 worth of equipment in reliance on the contracts. Farrow maintains the DLBA breached the contracts when it informed Farrow in October 2016 that all June 2016 RFPs needed to be re-bid per direction of the Michigan State Housing Development Authority and the United States’ Department of Treasury.

Farrow filed a three count complaint against the DLBA claiming breach of contract, promissory estoppel and asking this Court for injunctive relief. The DLBA filed [a] motion pursuant to MCR 2.116(C)(8) claiming Farrow ha[d] failed to state a claim on which relief can be granted. [Farrow Group, Inc v Detroit Land Bank Authority, unpublished per curiam opinion of the Court of Appeals, issued May 21, 2019 (Docket No. 341822), pp 1-2.]

The trial court had granted DLBA’s motion for summary disposition in its entirety. While this Court agreed with the trial court’s determination that Farrow’s breach of contract claimed failed, we did not reach the same conclusion with respect to the trial court’s decision on Farrow’s promissory estoppel claim. With regard to the promissory estoppel claim, this Court stated:

But we are not persuaded that the trial court correctly granted summary disposition on [Farrow]’s promissory estoppel claim. Indeed, it is not at all clear to us why the trial court granted summary disposition on this count inasmuch as there is no analysis or discussion of this claim. In any event, [Farrow]’s complaint does plead a claim based upon promissory estoppel. Whether the claim can survive summary disposition requires greater consideration and analysis by the trial court. It certainly does not automatically fail merely because the breach of contract claim fails. [Id. at 3]

We thus affirmed the trial court’s order granting summary disposition to defendant on plaintiff’s breach of contract claim but held that, “[t]he grant of summary disposition on the promissory estoppel claim is reversed and remanded for further proceedings consistent with this opinion.”

On remand, the trial court entered a supplemental opinion and order granting DLBA’s motion for summary disposition regarding Farrow’s promissory estoppel claim (hereinafter, the “supplemental opinion”). The trial court found the alleged statements made by DBA or DLBA employees were too vague to have reasonably induced reliance on the part of Farrow and that Farrow had various opportunities to “identify the pendant nature of the contracts.” This appeal ensued. On appeal, Farrow argues the trial court erred on two separate grounds: (1) exceeding the scope of its authority on remand by issuing the supplemental opinion; and (2) granting summary disposition to DLBA on the promissory estoppel claim.

-2- II. AUTHORITY ON REMAND

Farrow argues the trial court erred in issuing the supplemental opinion on remand. Specifically, Farrow contends this Court’s May 21, 2019 opinion did not instruct, direct, or invite the trial court to issue a supplemental opinion and the trial court, and, in issuing a supplemental opinion, the trial court exceeded the scope of the trial court’s authority on remand. Farrow further contends that because neither party requested clarification of the trial court’s summary disposition order or moved for reconsideration of that order, the trial court erred in sua sponte issuing a supplemental opinion.

“Whether a trial court followed an appellate court’s ruling on remand is a question of law that this Court reviews de novo.” Schumacher v Dep’t of Natural Resources, 275 Mich App 121, 127; 737 NW2d 782 (2007). “Generally, this Court’s ruling on an issue in a case will bind a trial court on remand and the appellate court in subsequent appeals.” Id. at 127. “[T]he trial court is bound to strictly comply with the law of the case, as established by the appellate court, according to its true intent and meaning.” Kasben v Hoffman, 278 Mich App 466, 470; 751 NW2d 520 (2008) (citations and quotation marks omitted). The doctrine only applies to questions explicitly or implicitly determined in the previous decision. Grievance Administrator v Lopatin, 462 Mich 235, 260; 612 NW2d 120 (2000). Therefore, the doctrine does not apply to issues that were raised in a previous appeal, but not decided by the appellate court. See Thorin v Bloomfield Hills Bd of Ed, 203 Mich App 692, 697; 513 NW2d 230 (1994).

“The power of the lower court on remand is to take such action as law and justice may require so long as it is not inconsistent with the judgment of the appellate court.” K & K Constr, Inc v Dep’t of Environmental Quality, 267 Mich App 523, 544, 705 NW2d 365 (2005), quoting People v Fisher, 449 Mich 441, 446-447, 537 NW2d 577 (1995). When “an appellate court gives clear instructions in its remand order, it is improper for a lower court to exceed the scope of the order.” K & K Constr, Inc, 267 Mich App at 544 (quotation marks and citations omitted).

Farrow correctly notes this Court did not specifically direct the trial court to consider and discuss whether the promissory estoppel claim survived DLBA’s motion for summary disposition, nor did this Court order the issuance of a supplemental opinion. However, while Farrow argues that trial court was prohibited from issuing the supplemental opinion as a result of the lack of any instruction or direction to the trial court to do so on remand in the May 21, 2019 opinion, a trial court is not so limited on remand. A trial court is not constrained from acting on remand when an appellate court remands without instructions. K & K Constr, Inc, 267 Mich App at 544. Rather, in the absence of instruction on remand, “a lower court has the same power as if it made the ruling itself.” Id.

Here, the trial court issued the supplemental opinion to add reasoning supporting its original order granting summary disposition to DLBA with regard to the promissory estoppel claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Pastoriza
818 N.W.2d 279 (Michigan Supreme Court, 2012)
West v. General Motors Corp.
665 N.W.2d 468 (Michigan Supreme Court, 2003)
People v. Fisher
537 N.W.2d 577 (Michigan Supreme Court, 1995)
Fansler v. Richardson
698 N.W.2d 916 (Michigan Court of Appeals, 2005)
Vargo v. Sauer
576 N.W.2d 656 (Michigan Supreme Court, 1998)
State Bank of Standish v. Curry
500 N.W.2d 104 (Michigan Supreme Court, 1993)
Al-Maliki v. LaGrant
781 N.W.2d 853 (Michigan Court of Appeals, 2009)
Schumacher v. Department of Natural Resources
737 N.W.2d 782 (Michigan Court of Appeals, 2007)
FOREST CITY v. Leemon Oil Co.
577 N.W.2d 150 (Michigan Court of Appeals, 1998)
Grievance Administrator v. Lopatin
612 N.W.2d 120 (Michigan Supreme Court, 2000)
Dalley v. Dykema Gossett PLLC
788 N.W.2d 679 (Michigan Court of Appeals, 2010)
Thorin v. Bloomfield Hills Board of Education
513 N.W.2d 230 (Michigan Court of Appeals, 1994)
Ypsilanti Township v. General Motors Corp.
506 N.W.2d 556 (Michigan Court of Appeals, 1993)
Zaremba Equipment, Inc. v. Harco National Insurance
761 N.W.2d 151 (Michigan Court of Appeals, 2008)
Kasben v. Hoffman
751 N.W.2d 520 (Michigan Court of Appeals, 2008)
Persinger v. Holst
639 N.W.2d 594 (Michigan Court of Appeals, 2002)
K & K Const. Inc. v. Deq
705 N.W.2d 365 (Michigan Court of Appeals, 2005)
Bailey v. Schaaf
835 N.W.2d 413 (Michigan Supreme Court, 2013)
Forest City Enterprises, Inc. v. Leemon Oil Co.
228 Mich. App. 57 (Michigan Court of Appeals, 1998)
K & K Construction, Inc. v. Department of Environmental Quality
267 Mich. App. 523 (Michigan Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Farrow Group Inc v. Detroit Land Bank Authority, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farrow-group-inc-v-detroit-land-bank-authority-michctapp-2021.