Farrell, to Use v. H. Platt Co.

15 A.2d 718, 142 Pa. Super. 242, 1940 Pa. Super. LEXIS 543
CourtSuperior Court of Pennsylvania
DecidedApril 12, 1940
DocketAppeals, 204 and 205
StatusPublished
Cited by5 cases

This text of 15 A.2d 718 (Farrell, to Use v. H. Platt Co.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farrell, to Use v. H. Platt Co., 15 A.2d 718, 142 Pa. Super. 242, 1940 Pa. Super. LEXIS 543 (Pa. Ct. App. 1940).

Opinion

Cunningham, J.,

Opinion by

*244 On March 12, 1936, the City of Farrell entered into a contract with H. Platt Company, appellant at No. 204 April Term, 1940, and hereinafter referred to as Platt, for the construction of a Sewage Treatment Plant and Raw Sewage Pump Station — including, inter alia, the construction of six buildings and the laying of sewers .along Spearman Avenue and other city streets. Seaboard Surety Company, appellant at No. 205, became the surety upon Platt’s performance and “labor and materialmen’s bond.”

The “Contractor’s Bidding Sheet” attached to the contract contained more than a hundred items, arranged under various headings indicative of the component parts of the system, such as “Outside Piping,” “Control House,” “Sewers and Discharge Mains,” etc. The sheet also contained columns headed “Estimated Quantity,” “Unit Price Bid,” and “Total Price Bid.”

. We are concerned in this case chiefly with the portion of the sheet reading:

“Sewers and Discharge Mains
92. Earth Excavation, including cutting and replacing of street pave
93. Rock Excavation, including cutting and replacing of street pave
94. Black Steel Pipe, 12"
95. Black Steel Pipe, 10"
96. Vitrified Pipe, 18"
97. Vitrified Pipe, 12"
98. Vitrified Pipe, 8" ”

In general, the unit price bid by Platt to the city for “earth excavation” was $1.50 per cu. yd. and $5 per cu. yd. for “rock excavation.”

On June 15, 1936, Platt entered into a subcontract with O. W. Milarr, Inc., (hereinafter referred to as Milarr) use plaintiff below and appellee herein, wherein the latter undertook to “furnish all materials...... and fully construct, perform and in every respect com *245 píete all the Excavation, Backfilling, Tamping pipe and fittings (Items #...... 92, 93, 94, 95, 96, 97, 98......); For the Sewage Treatment Plant......and Sewers, according to the plans and specifications (details thereof to be furnished as needed) of Robert Hall Craig, Engineer, and to the full satisfaction of said Engineer.”

Seventeen additional item numbers were included in the above indicated parenthesis covering earth and rock excavations, various kinds of pipe and pipe fittings. Other material provisions of the subcontract read:

“In consideration whereof, the said contractor agrees that he Avill pay to the said subcontractor in monthly payments, the sum of 75c per cu. yd. for excavation, 25(' per lin. ft. for laying pipe, $4 per eu. yd. for rock as shoAvn and called for, any additional rock at $3.50 per cu. yd. for said materials and Avork,......

*****

“Unit price for excavation includes backfilling and tamping.” (Italics supplied.)

In general the terms of payment to Milarr Avere 90% of the amount due for labor and materials as construction “was placed in position,” upon presentation of bill to Platt, and balance upon completion of Avork and approval by engineer.

Milarr began the work covered by his subcontract Avithin four days after its execution and continued until August 28th when he suspended operations because, as he alleged, the necessary engineering lines had not been run, required shoring material had not been furnished, and the lines of various public utilities had not been removed. On September 11th Milarr applied to Platt for payment for the work done in August. By that date the above complaints had been adjusted and Harold A. Cook, Platt’s representative, agreed to get a check for Milarr within a feAV days.

On September 14th Milarr resumed his work and continued until noon of the day following Avhen he was *246 informed by Platt nothing more would be paid him as Platt claimed Milarr had already been overpaid. The city had paid Platt on September 3d for the work performed by Milarr during the month of August.

Milarr thereupon rescinded his subcontract with Platt by a letter to the latter reading: “This is to advise you that we have this day at 12 noon discontinued our operations on our subcontract at your sewerage disposal plant job at Farrell, Pa. This action is taken because of your failure to pay our current estimate as covered in our contract article #14.”

The reference is to the above quoted provision of the subcontract relative to monthly payments.

On August 27, 1937, Milarr brought his action in assumpsit, as a use plaintiff under the bond of the general contractor to the city, against Platt and the surety thereon, claiming a balance due him of $1955.06 for so much of the work as he had performed under the subcontract, with interest from September 15,1936.

The surety defended upon the ground that Platt “did not owe the use plaintiff any amount whatever.” Platt, in addition to denying he owed Milarr anything, presented a counter-claim in the amount of $4377.49, including an item of $2053, representing the sum he had been obliged to pay other persons for doing the unperformed portion of the work covered by Milarr’s contract over and above the amount “[he] would have been required to pay for the same work and materials if the use plaintiff had completed the same under the subcontract.”

The result of a trial by the court without a jury was a decision by Rowley, P. J., on October 28, 1939, that Platt’s counter-claim was without merit and the entering of a judgment in favor of Milarr and against both defendants in the principal sum of $1589.19, with interest from September 15, 1936, or a total of $1886.37. The principal sum is composed of two items — $1131.06 as the balance due Milarr for the work performed by *247 Mm under the contract and $458.13 for extras. These appeals by the respective defendants followed.

As we view the case, the first and most important question of law involved upon these appeals is whether or not the court below erred in its seventh conclusion of law reading: “C. W. Milarr, Inc. was not bound by the terms of the subcontract to replace the pavement on Spearman Avenue.”

This conclusion must be read in connection with the nineteenth finding of fact, viz: “In performing its work, Milarr necessarily removed 800 feet of the pavement upon Spearman Avenue. The cost of replacement of this pavement was $1555.40.”

When this amount is compared with the principal sum of the judgment in his favor it is clear that, if Milarr was legally bound under the terms of his subcontract to replace this pavement, Platt owed him nothing on September 15, 1936, and Milarr breached his contract by abandoning the work on that date. Assuming all the other findings in Milarr’s favor to be correct, the 90% of the above mentioned $1131.06 then due would be only $1017.95, or plus the $458.13 for extras, only $1476.08. We accordingly take up that issue first.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stardust Inn, Inc. v. Doshi (In Re Stardust Inn, Inc.)
70 B.R. 888 (E.D. Pennsylvania, 1987)
Atlantic Refining Co. v. Continental Casualty Co.
183 F. Supp. 478 (W.D. Pennsylvania, 1960)
Ritz v. Music, Inc.
150 A.2d 160 (Superior Court of Pennsylvania, 1959)
Tudesco Et Ux. v. Wilson
60 A.2d 388 (Superior Court of Pennsylvania, 1948)
Appeal of Gentile
43 Pa. D. & C. 53 (Fayette County Court of Quarter Sessions, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
15 A.2d 718, 142 Pa. Super. 242, 1940 Pa. Super. LEXIS 543, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farrell-to-use-v-h-platt-co-pasuperct-1940.