Farmville Investment Group, L.L.C v. Prospect Homes of Richmond, Inc.

79 Va. Cir. 69, 2009 Va. Cir. LEXIS 68
CourtHenrico County Circuit Court
DecidedApril 27, 2009
DocketCase No. CL06-2477
StatusPublished

This text of 79 Va. Cir. 69 (Farmville Investment Group, L.L.C v. Prospect Homes of Richmond, Inc.) is published on Counsel Stack Legal Research, covering Henrico County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farmville Investment Group, L.L.C v. Prospect Homes of Richmond, Inc., 79 Va. Cir. 69, 2009 Va. Cir. LEXIS 68 (Va. Super. Ct. 2009).

Opinion

By Judge Catherine C. Hammond

This matter is before the Court following a trial without a jury on March 24,25, and 26, 2009. The case turns on two written contracts and the duties of the parties under those agreements. The parties submitted excellent post-trial memoranda.

The agreements govern the development of residential subdivisions in Farmville, Virginia. The first contract, dated April 29,2005, described 71 lots in neighborhoods named Cabell’s Ridge, Pondview, and Creekview. The second contract, dated November 10,2005, described 99 lots in a subdivision named Jesse’s Ridge. Each party now contends that the other is in breach. Farmville Investment Group, L.L.C. (FIG) argues that it developed the real property and fulfilled its duties, triggering Prospect’s duty to purchase the lots. Prospect admits that it has not purchased all of the lots. It argues that FIG’s earlier breach of contract relieved Prospect of the obligation to purchase additional lots. In addition, Prospect’s counterclaim seeks rescission and demands that FIG buy back 22 lots that were sold to Prospect.

[70]*70From the evidence, this Court draws the following findings of fact and conclusions of law.

In 2005, Prospect began building houses in Cabell’s Ridge. Closing on the lots was scheduled to occur in three phases, on dates when the roads were built. The contract anticipated closing dates in June and July 2005 and in March 2006. Prospect complied with the first two, in July and October 2005, acquiring 3 9 out of 71 lots. Around this time, Prospect wanted even mote lots and asked the local real estate broker, Mr. Brooks, about finding additional property to develop. In response to Prospect’s inquiry and its desire to do a similar deal, FIG found the land for Jesse’s Ridge and obtained financing from the Bank of Goochland. FIG borrowed this money in reliance upon Prospect’s commitment to buy additional building lots. In November 2005, they signed the Jesse’s Ridge contract, which was almost identical to the earlier agreement.

In 2006, when the time came to close on the third and final group of 32 lots in Cabell’s Ridge, problems arose. Prospect’s sales were slowing down. At Prospect’s request, FIG and Prospect agreed to modify the schedule, with Prospect closing on 16 lots in March 2006 and another 16 lots in May 2006. In March, Prospect purchased 16 lots, but, in May, Prospect advised that it would only take 8 of the remaining 16 lots in Cabell’s Ridge. At Prospect’s request, the parties agreed again to change the schedule and set a closing date of September 1, 2006, for the final 8 lots. (PX 68.) In the meantime, FIG undertook expenses to develop the Jesse’s Ridge lots, which were scheduled for delivery to Prospect in June and December of2006 or as soon as the roads were built.

By the end of August 2006, Prospect had built and sold 12 houses in Cabell’s Ridge. Additional houses were built or under construction. However, Prospect faced financial problems. Prospect’s Chief Financial Officer and its owner, Mr. Audi, both testified that Prospect made a decision in the summer of2006 that Prospect would not go through with the Jesse’s Ridge agreement. They did not communicate this decision to FIG. FIG continued to use borrowed funds to complete the site work at Jesse’s Ridge. However, the parties did discuss, in the Summer of 2006, issues respecting the design of certain lots in Cabell’s Ridge, the location of sewer taps, and whether lots would accommodate gravity sewers. Prospect assured FIG that it would buy the 8 remaining lots in Cabell’s Ridge. On August 19,2006 Mr. Audi stated that he “still wanted to stay in the deal.”

On the closing date, September 1, 2006, FIG delivered deeds to the 8 remaining lots in Cabell’s Ridge. Prospect refused to close. Mr. Audi told Mr. Brooks that, unless FIG would let Prospect out of the Jesse’s Ridge contract, [71]*71Prospect would not purchase the 8 lots left in Cabell’s Ridge. FIG gave notice of default on September 1, 2006. This action commenced on September 26, 2006. Soon afterwards, on November 4, Prospect refused to close on the first group of lots that were ready in Jesse’s Ridge.

After receiving notice of default, Prospect hired a consultant to examine environmental and regulatory requirements for the subdivisions. This was in defense of FIG’s claims. Mr. Audi testified that he did not have concerns about wetlands, storm water, flooding, drainage, erosion, or water quality until after September 1, 2006. The Town of Farmville had already approved the subdivisions, roads, and sewer; FIG understood that all of the lots were ready for building. Neither did FIG have any knowledge of regulatory problems before September of 2006. When Mr. Harper found out that Prospect had hired the consultant, Mr. Harper assured Mr. Audi that, if the consultant found a problem, FIG would fix it.

In November 2006, Prospect’s consultant reported that land disturbance in Cabell’s Ridge required wetlands approvals from the Corps of Engineers (COE). The consultant was not asked to examine the property in Jesse’s Ridge. Once his report was delivered to Prospect, their engagement ended. Then FIG engaged the same consultant to look at both Cabell’s Ridge and Jesse’s Ridge and make application to the COE. In early 2007, the COE granted wetlands permits and no wetlands problem remains in either subdivision.

FIG also researched the need for permits respecting storm water, which has been regulated by the Virginia Department of Conservation and Recreation (DCR) since 2005. Virginia regulates the discharge of storm water from construction projects as it can affect both water quality and water quantity. Under DCR’s delegation, the Town of Farmville oversees erosion and sediment control, but does not operate a storm water program. The Town had approved erosion and sediment control plans, but there was some confusion about the Town’s authority during the development project. For example, the Town did not provide land disturbance information to the state. Thus DCR did not have notice of construction in these subdivisions. Neither FIG nor local government officials were aware of DCR’s requirements until 2007. FIG’s call to DCR began the permitting process.

In 2008, DCR issued stormwater permits for a portion of Jesse’s Ridge. DCR has not advised that a permit is required for Cabell’s Ridge. To the contrary, DCR’s enforcement agent has advised that a permit is not required there. FIG would need additional approval from DCR to build in Jesse’s Ridge in the area which remains vacant.

[72]*72The Town of Farmville considers the subdivisions approved with no reservations. The Town would issue building permits for homes on every lot in both Cabell’s Ridge and Jesse’s Ridge. All bonds have been released.

Michael White testified as an expert engineer for Prospect. He was retained by Prospect in 2008 and then performed a detailed floodplain analysis for the Cabell’s Ridge properties. Mr. White determined that certain lots are likely to suffer flooding or serious erosion. In his opinion, the Cabell’s Ridge properties were not designed correctly to consider storm water drainage. In addition, although his study area did not include the Jesse’s Ridge property, Mr. White questioned FIG’s performance with respect to water quality, water storage, and water runoff in Jesse’s Ridge. In his opinion, FIG did not perform consistently with generally accepted engineering practices, in large part because of incomplete or missing information and analysis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little v. Cooke
652 S.E.2d 129 (Supreme Court of Virginia, 2007)
Horton v. Horton
487 S.E.2d 200 (Supreme Court of Virginia, 1997)
Marks v. Sanzo
345 S.E.2d 263 (Supreme Court of Virginia, 1986)
Neely v. White
14 S.E.2d 337 (Supreme Court of Virginia, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
79 Va. Cir. 69, 2009 Va. Cir. LEXIS 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farmville-investment-group-llc-v-prospect-homes-of-richmond-inc-vacchenrico-2009.