Famous Builders, Inc. v. Bolin

264 Cal. App. 2d 37, 70 Cal. Rptr. 17, 1968 Cal. App. LEXIS 2045
CourtCalifornia Court of Appeal
DecidedJuly 15, 1968
DocketCiv. 934
StatusPublished
Cited by7 cases

This text of 264 Cal. App. 2d 37 (Famous Builders, Inc. v. Bolin) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Famous Builders, Inc. v. Bolin, 264 Cal. App. 2d 37, 70 Cal. Rptr. 17, 1968 Cal. App. LEXIS 2045 (Cal. Ct. App. 1968).

Opinion

CONLEY, P. J.

Famous Builders, Inc. initiated this action to foreclose a mechanic’s lien on a house constructed for defendants pursuant to a written contract; the appellant requested payment in the sum of $9,109, and interest from August 29, 1963. The gross amount above mentioned included the fifth installment of the contract going to make up the total consideration of $22,636 (four installments having been paid during the progress of construction); in the litigation, the plaintiff also claimed two amounts for extras: $408 for electrical extras and $469.20 for flat concrete work. An answer was filed by the respondents denying the allegations contained in the complaint and alleging by counterclaim and also by cross-complaint damages of their own in the sum of $12,000; this sum was later reduced by $5,482 by the court in response to a motion to that effect by plaintiff, so that the net damages claimed by cross-complainants were $6,518. The judgment gave plaintiff $408 plus interest at 7 percent per annum from August 29, 1963, for the extra electrical work but denied all other recourse by plaintiff; it was also ordered that plaintiff have a lien on the real property to secure said amount of $408. The findings according to appellant were singularly defective in that nothing was said with respect to the counterclaim or cross-complaint. The court found that the plaintiff had a license to act as contractor up to and including June 30 *39 but not afterwards; in this connection, the complaint alleges that the work done by the contractor continued up to August 1 of the year.

Summarizing, we a.re dealing with a contract for the construction of a house which was grossly finished at least to the point where the construction company filed a notice of completion ; the contract called for a total price of $22,636 of which part had been paid in installments; in addition there were claims for two extras of $408 and $469.20. There are a counterclaim and a cross-complaint as to which no finding was made and by which the defendants claimed extensive damages. The respondents seem satisfied to pay for the extra work of electrical installation in the sum of $408 on the ground that that work was completed prior to June 30; this sum was allowed by the court. While this conclusion may well seem unjustified, as all extras become part of the total contract, defendants have not appealed and, consequently, we cannot disturb this part of the judgment. For the reason that the claim for the other extra for concrete fiat-work in the sum of $469.20 became a part of the main contract it would not be proper to allow its recovery.

The trial court determined that the plaintiff and appellant was not entitled to a judgment for two good and sufficient reasons: (1) the plaintiff did not have a contractors’ license from June 30 to the 1st day of August, although the plaintiff concedes that the entire work of construction was not completed until the end of July; (2) the plaintiff failed in important respects, some of which were wilful, to comply with the terms of its contract; there was no such thing as a substantial performance; there were many details of incorrect and faulty work. For both of these reasons, there could be no recovery.

It will be noted that instead of completely relying as a defense upon these two separate grounds, the defendants also pleaded at length, both by counterclaim and cross-complaint, that the failure of the plaintiff to comply with its contract resulted in damages to cross-complainants of very extensive nature. It was contemplated by the Legislature that when a party, contracting to build a building in a certain way, fails in essential matters to carry out its agreement but thereafter sues for the balance alleged to be due for complete performance under the contract, although, as here, thousands of dollars worth of building material and labor have been incorporated in the building and retained by the landowner, there must be a refusal by the court to accede to the construe *40 tion company’s demand; at the same time, it would be unjust in a case like this to hold that the construction company would be additionally liable on a cross-complaint or counterclaim for the amount of alleged damage so suffered by the person owning the land; such a permissive attitude on the part of the courts might well result in a double recovery. In the present instance, the defendants asserted by counterclaim and cross-complaint specific damages by reason of the failure of the plaintiff to perform as agreed. These allegations of damage were unquestionably indulged in by the owners of the land for the reason that, if, contrary to their denial in their answer of performance by plaintiff in accordance with its contract, a court should nevertheless find substantial compliance, the owners of the land could recover by virtue of the counterclaim or cross-complaint the actual damages suffered by them through failure of the plaintiff to perform as agreed. In the present instance, as has already been noted, the trial court found that for two good reasons there could be no recovery by the plaintiff, and it therefore became unimportant, as moot, that the court should also find in detail on the issues raised by the counterclaim and cross-complaint. No appeal has been taken by the cross-complainants and no ground for reversal could possibly accrue thereby in favor of the plaintiff here in view of the trial court’s legitimate conclusion that no recovery could be made by the plaintiff on the original contract which formed the basis for the action.

Intent upon its resolve to enforce honest and efficient construction standards, the Legislature insisted upon the possession of a license by contractors with a very severe penalty if they should not apply for or obtain such a license. Section 7031 of the Business and Professions Code is as follows: “No person engaged in the business or acting in the capacity of a contractor, may bring or maintain any action in any court of this state for the collection of compensation for the performance of any act or contract for which a license is required by this chapter without alleging and proving that he was a duly licensed contractor at all times during the performance of such act or contract, ...”

The actual implementation of section 7031 of the Business and Professions Code depends upon the selection of a responsible managing officer-employee, and it was obviously the intention of the Legislature to make the section in question in pari materia with section 7068.2 of the Business and Professions Code which provides in part as follows: “If the individual qualifying for the license is a responsible managing *41 officer or responsible managing employee and ceases for any ' reason whatsoever to be connected with the individual or firm to whom the license is issued, the licensee and the responsible managing officer or responsible, managing employee qualifying for such license shall notify the registrar in writing within 30 days from such cessation. If a notice is given the license shall remain in force for a reasonable length of time to be determined by rules of the board. ’’

In the instant case the responsible managing employee of the plaintiff was Walter Eugene Boyd. He gave notice in May 1963 that he would retire from his work, in accordance with the provision of law just quoted, and by action of the board the plaintiff was given until August 22, 1963, to replace Mr. Boyd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Khan Development Co. v. Bral CA2/5
California Court of Appeal, 2014
Buzgheia v. Leasco Sierra Grove
60 Cal. App. 4th 374 (California Court of Appeal, 1997)
Weeks v. Merritt Building & Construction Co.
39 Cal. App. 3d 520 (California Court of Appeal, 1974)
Sumner Development Corporation v. Shivers
517 P.2d 757 (Alaska Supreme Court, 1974)
Lewis v. Arboles Development Co.
8 Cal. App. 3d 812 (California Court of Appeal, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
264 Cal. App. 2d 37, 70 Cal. Rptr. 17, 1968 Cal. App. LEXIS 2045, Counsel Stack Legal Research, https://law.counselstack.com/opinion/famous-builders-inc-v-bolin-calctapp-1968.