Facility Gateway Corp. v. Sovernet, Inc.

Vermont Superior Court·Decided October 31, 2017·No. 273-3-17 Cncv·Published

Opinion

Facility Gateway Corp. v. Sovernet, Inc., No. 273-3-17 Cncv (Mello, J., Oct. 31, 2017).

[The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the accompanying data included in the Vermont trial court opinion database is not guaranteed.]

VERMONT SUPERIOR COURT

CHITTENDEN UNIT

CIVIL DIVISION

Facility Gateway Corporation, │ Plaintiff │ │

v. │ Docket No. 273-3-17 Cncv │

Sovernet, Inc., ATN International, Inc., and OHCP Northeast Fiber Buyer, Inc., │ Defendants │ │

RULING ON PLAINTIFF’S MOTION FOR AN ATTACHMENT ON BUSINESS ASSETS In this civil action, Plaintiff Facility Gateway Corporation seeks to recover from defendants the sum of $2,397,506.30, which Plaintiff claims to be owed for services it provided to Defendant Sovernet, Inc. pursuant to a contact to design and build Sovernet’s datacenter in Williston, Vermont. Presently before the court is Plaintiff’s motion for a non- possessory writ of attachment on Sovernet’s business equipment at the datacenter. Defendants oppose the motion. Plaintiff is represented by Erin Miller Heins, Esq., and Defendants are represented by Christopher D. Roy, Esq. and Steven Cowley, Esq.

The court held evidentiary hearings on Plaintiff’s motion on May 15, June 28 and July 26, 2017.1 Based upon the credible evidence, the court makes the following findings, conclusions and orders.

1 At the conclusion of the hearings, the court orally enjoined Sovernet from transferring or

encumbering the business equipment that is the subject of Plaintiff’s motion, until further order of the court.

Facts

Plaintiff is a Wisconsin corporation engaged in the business of providing facility design and construction services throughout the United States. Defendant Sovernet is a Vermont corporation that provides internet and telecommunication services for residential and business customers throughout Northern New England.

On November 20, 2014, Plaintiff and Sovernet entered into a contract under which Plaintiff agreed to design and build a datacenter for Sovernet at Pioneer Drive in Williston, Vermont for a fixed price of $3,979,900 plus a 2.5% “contingency” (Exhibit 1, Articles 1-4). It was understood that the datacenter was intended to house not only Sovernet’s data equipment but also space that Sovernet could rent to its tenants. The contract did not specify a date by which the project was to be completed but left that “[t]o be mutually determined later” (Id., § 3.3). Under the contract, neither party could unilaterally modify the scope of the work to be performed or the price to be paid for the project, nor could either party unilaterally impose deadlines for the completion of the work; any such changes had to be in writing signed by both parties (Id., § 1.3).

On June 22, 2015, the parties agreed to and signed a change order, in which the parties agreed to amend the scope of the work in various ways and to increase the fixed price of the project to $5,546,369 (Exhibit 2, or “Change Order 1).

The contract required Sovernet to make “progress payments” to the Plaintiff “based upon [Plaintiff’s] achieving project milestones” (Id., § 5.2.1). The “milestones” were listed in the contract as follows: “20% upon execution, 20% upon completion of engineering and permitting, 25% upon delivery to the site of [Plaintiff’s] provided equipment; 20% upon

substantial completion of all major trades, and 15% upon full project completion” (Id.). As each milestone was met, Plaintiff could submit a payment application to Sovernet indicating “the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment” (Id.). Under the contract, Sovernet was required to acknowledge receipt of each application for payment within seven days and to specify any “reasons for withholding payment in whole or in part” (Id., § A.9.4.1). If Sovernet unjustifiably failed to timely pay an invoice, Plaintiff had the right, upon seven days’ notice, to stop work until the payment was made (Id., § A.9.7.1). In addition, overdue payments were to bear interest from the date payment was due at the rate of 1.5% per month (Id., § 7.7.2).

Disputes arose between the parties as the project progressed. For example, at various times during the course of the project, the Plaintiff asked Sovernet to make payments which were not yet due under the contract but which Plaintiff needed in order to pay its contractors. On one or more occasions, Plaintiff indicated that it would have to stop work if Sovernet did not make the requested advance payments. In response to these requests, Sovernet made advance payments to the Plaintiff in order to keep the project moving forward, even though it was not required to do so under the contract. Consequently, between the time the project commenced, and the time when the major trades substantially completed their work, Sovernet made 17 payments to the Plaintiff, instead of the four called for in Section 5.2.1 of the contract (see Exhibit 9 for a list of all the payments Sovernet made to the Plaintiff).

In addition, at various points during the project, the Plaintiff claimed that, at Sovernet’s request, it had performed $1,683,653 worth of work, over and above what had

been agreed to in the contract and in Change Order 1. Plaintiff submitted a series of change orders to Sovernet, listing the alleged additional work and costs (Exhibits 3A-G and 17, the “unsigned change orders”). Sovernet received the proposed change orders but refused to sign them because, according to Sovernet, all of the work listed in the unsigned change orders had been included within the scope of the original contract and Change Order 1, and because it had never agreed to increase the contract price by an additional $1,683,653.

Another dispute related to a claim by Sovernet that the Plaintiff had not complied with all applicable design specifications in its construction of the datacenter and, therefore, that Plaintiff was not entitled to any further payments from Sovernet under the contract. In addition, Sovernet expressed concerns over the amount of time it was taking the Plaintiff to complete construction of the project. This concern became heightened in March 2016, when Sovernet’s largest tenant announced that it would need to occupy the new space by the end of July or find another location to rent from.

In an effort to resolve their disputes, Sovernet and the Plaintiff signed a written agreement on April 27, 2016, in which they made changes to the scope of the work and increased the fixed price of the project by $88,500 to a new total of $5,634,869 (Exhibit 4, or “Change Order 2,” ¶ 4). In paragraph 7 of this change order, Sovernet also agreed to pay the Plaintiff, following substantial completion, another $112,500 to reflect “the full satisfaction of the ‘contingency’ on the Stipulated Sum as described in Section 4.2.5 of the [original contract].” In paragraph 8, Plaintiff agreed “that it will complete all Work to the Specifications and reach Substantial Completion of the project, including recommissioning, no later than June 15, 2016.” In paragraph 10, Plaintiff agreed that “upon Substantial Completion” Sovernet could “retain $100,000 (the ‘Holdback Amount’) of the Stipulated

Free access — add to your briefcase to read the full text and ask questions with AI

Facility Gateway Corp. v. Sovernet, Inc., (Vt. Ct. App. 2017).

Facility Gateway Corp. v. Sovernet, Inc. (Facility Gateway Corp. v. Sovernet, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kellogg v. Shushereba
2013 VT 76 (Supreme Court of Vermont, 2013)
Birchwood Land Company, Inc. v. Ormond Bushey & Sons, Inc.
2013 VT 60 (Supreme Court of Vermont, 2013)
Ferrisburgh Realty Investors v. Schumacher
2010 VT 6 (Supreme Court of Vermont, 2010)
Harsch Properties, Inc. v. Nicholas
2007 VT 70 (Supreme Court of Vermont, 2007)
New England Partnership, Inc. v. Rutland City School District
786 A.2d 408 (Supreme Court of Vermont, 2001)
Carmichael v. Adirondack Bottled Gas Corp.
635 A.2d 1211 (Supreme Court of Vermont, 1993)
Dj Painting, Inc. v. Baraw Enterprises, Inc.
776 A.2d 413 (Supreme Court of Vermont, 2001)
Cushman v. Outwater
159 A.2d 89 (Supreme Court of Vermont, 1960)
Kpc Corporation v. the Book Press, Inc.
636 A.2d 325 (Supreme Court of Vermont, 1993)
Monahan v. GMAC Mortgage Corp.
2005 VT 110 (Supreme Court of Vermont, 2005)
Gallipo v. City of Rutland
2005 VT 83 (Supreme Court of Vermont, 2005)