Fabek v. City of Youngstown, Unpublished Decision (5-15-2001)

CourtOhio Court of Appeals
DecidedMay 15, 2001
DocketCase No. 99 C.A. 312.
StatusUnpublished

This text of Fabek v. City of Youngstown, Unpublished Decision (5-15-2001) (Fabek v. City of Youngstown, Unpublished Decision (5-15-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fabek v. City of Youngstown, Unpublished Decision (5-15-2001), (Ohio Ct. App. 2001).

Opinions

OPINION
Defendant-appellant, City of Youngstown (City), appeals a decision rendered by the Mahoning County Court of Common Pleas granting summary judgment in favor of defendant-appellee, Western Reserve Construction Company, Inc. (WRC), against City.

A review of the record establishes the following uncontroverted facts. In an effort to correct a section of damaged sewer pipe, the City of Youngstown Waste Water Department contracted with WRC to repair approximately two to three hundred feet of damaged sewer line and two manholes at the intersection of Brunswick Place and Susan Circle, Youngstown, Ohio. WRC began its excavation work on June 25, 1996. Prior to this time, the surrounding underground utilities were marked. The City of Youngstown Water Department (Water Department) marked the location of the surrounding waterlines with blue paint.

WRC attempted to correct the sewer back-up problem by excavating the ground near the damaged sewer pipe. WRC estimated that the proper depth for the excavation would be approximately nineteen feet in depth. WRC recognized that the area's soil conditions were sandy, runny, and unstable, and chose to use a set of interlocking steel shielding plates (sheet pilings). These sheet pilings were used to prevent the ground from caving in and to protect the surrounding utilities, lines, and mains. WRC placed the sheet pilings around three sides of the excavation.

WRC began digging. After digging approximately six feet down from the surface, WRC discovered a pocket of very wet material, which was not native to the excavation area. WRC concluded that the foreign material was a slag-based material used to backfill a hole from a previous waterline break. Testimony also showed that there had been three additional waterline leaks in this area over a thirty-year period. WRC continued its excavation operation.

WRC ceased its excavation operation around 5:00 P.M. that evening and secured the construction site from pedestrians. Around midnight on June 26, 1996, Thomas Mirante (Mirante), Assistant Superintendent at the Waste Water Treatment Plant, arrived at the excavation site to conduct a standard pumping procedure. Mirante observed no signs of a waterline break at this time. Sometime during the night the waterline broke. The parties agree that a shift in the ground occurred. As a result of the waterline break, water flooded the sewers and manholes, and caused water to back-up into numerous homes in nearby areas.

On June 24, 1998, plaintiffs, Elsie Fabek, et al., brought suit against City and WRC to recover for property damage caused by the waterline break and sewer backup. WRC filed its answer to plaintiffs' complaint, and also filed a cross-claim against City alleging that City was the sole and proximate cause of plaintiffs' injuries. WRC also sought contribution against City. On September 14, 1998, City filed its answer to plaintiffs' and WRC's complaint.

WRC filed a motion for summary judgment on August 31, 1999. WRC moved for summary judgment against the plaintiffs and City arguing that: (1) WRC did not breach a duty of care to the plaintiffs as the actions taken by City were the proximate cause of plaintiffs' injuries, and (2) City was strictly liable for the damages sustained from the break in the waterline. The plaintiffs and City each filed motions in opposition to summary judgment.

On October 14, 1999, the trial court granted summary judgment in favor of WRC and found that City had offered no evidence that WRC acted negligently. City filed a motion to modify the trial court's judgment entry on October 25, 1999 to include the requisite Civ.R. 54(B) language. The trial court sustained the motion on December 9, 1999, and added the words "there being no just reason for delay" to its original judgment entry.

City filed a timely notice of appeal on December 10, 1999. In response, WRC filed a motion to dismiss this appeal alleging that the trial court's October 14, 1999 order was not a final appealable order. On February 3, 2000, this court overruled that motion.

City raises two assignments of error on appeal. City's first assignment of error states:

"THE TRIAL COURT ERRED IN GRANTING DEFENDANT-APPELLEE'S MOTION FOR SUMMARY JUDGMENT WHERE DEFENDANT-APPELLANT DEMONSTRATED THE EXISTENCE OF GENUINE ISSUES OF MATERIAL FACTS"

City's second assignment of error states:

"THE TRIAL COURT ERRED IN FINDING THAT THE CITY OF YOUNGSTOWN PRESENTED NO EVIDENCE OF NEGLIGENCE ON THE PART OF WRC AND THAT, CONSEQUENTLY, BECAUSE THE CITY OF YOUNGSTOWN PRESENTED NO SUCH EVIDENCE, THERE WAS NO GENUINE ISSUE OF MATERIAL FACT REQUIRING LITIGATION OF THE CLAIMS AGAINST WRC"

City's assignments of error raise common issues of legal analysis and will be addressed together.

In City's assignments of error, City argues that the trial court erred in granting summary judgment in favor of WRC. City argues that when the evidence is viewed in a light most favorable to it, there is a genuine issue of material fact as to whether or not WRC acted negligently. City has set forth two primary arguments in support of its position. First, City argues that there is a genuine issue of material fact as to whether WRC acted negligently by leaving a void between the sheet pilings and the side of the excavation where the waterline broke. City argues that if there would not have been a void between the sheet piling and the side of the excavation where the waterline broke, then the waterline would have had nowhere to shift, and consequently would not have broke.

Next, City argues that WRC acted negligently by failing to notify the Water Department to "valve down" the intersection. City argues that it was WRC's responsibility to notify the Water Department to valve down the intersection prior to beginning its excavation activity. City argues that, as an experienced contractor, WRC should have known how to properly protect the excavation site.1

In response to City's arguments, WRC asserts that the trial court did not err in granting summary judgment against City. WRC argues that City neither introduced evidence showing negligence on the part of WRC nor evidence establishing genuine issues of material fact that require litigation. WRC argues that City is essentially attempting to fabricate issues of material fact and argues that City cannot use inconsistencies between its own agents to create issues of fact.

The Ohio Supreme Court set out the standard for considering motions for summary judgment in Dresher v. Burt (1996), 75 Ohio St.3d 280 . The court stated:

"We hold that a party seeking summary judgment, on the ground that the nonmoving party cannot prove its case, bears the initial burden of informing the trial court of the basis for the motion, and identifying those portions of the record that demonstrate the absence of a genuine issue of material fact on the essential element(s) of the nonmoving party's claims. The moving party cannot discharge its initial burden under Civ.R. 56 simply by making a conclusory assertion that the nonmoving party has no evidence to prove its case. Rather, the moving party must be able to specifically point to some evidence of the type listed in Civ.R. 56(C) which affirmatively demonstrates that the nonmoving party has no evidence to support the nonmoving party's claims. If the moving party fails to satisfy its initial burden, the motion for summary judgment must be denied. However, if the moving party has satisfied its initial burden, the nonmoving party then has a reciprocal burden outlined in Civ.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Ford Motor Company v. Wallace H. Tomlinson
229 F.2d 873 (Sixth Circuit, 1956)
Cole v. American Industries & Resources Corp.
715 N.E.2d 1179 (Ohio Court of Appeals, 1998)
Hoyt, Inc. v. Gordon & Associates, Inc.
662 N.E.2d 1088 (Ohio Court of Appeals, 1995)
Jennings Buick, Inc. v. City of Cincinnati
384 N.E.2d 303 (Ohio Supreme Court, 1978)
Strother v. Hutchinson
423 N.E.2d 467 (Ohio Supreme Court, 1981)
Menifee v. Ohio Welding Products, Inc.
472 N.E.2d 707 (Ohio Supreme Court, 1984)
Perez v. Scripps-Howard Broadcasting Co.
520 N.E.2d 198 (Ohio Supreme Court, 1988)
Turner v. Turner
617 N.E.2d 1123 (Ohio Supreme Court, 1993)
State ex rel. Parsons v. Fleming
628 N.E.2d 1377 (Ohio Supreme Court, 1994)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Fabek v. City of Youngstown, Unpublished Decision (5-15-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/fabek-v-city-of-youngstown-unpublished-decision-5-15-2001-ohioctapp-2001.