Exxon Mobile Pipeline Company v. Harrison Interests, Ltd.

CourtCourt of Appeals of Texas
DecidedJuly 3, 2002
Docket14-00-01392-CV
StatusPublished

This text of Exxon Mobile Pipeline Company v. Harrison Interests, Ltd. (Exxon Mobile Pipeline Company v. Harrison Interests, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Exxon Mobile Pipeline Company v. Harrison Interests, Ltd., (Tex. Ct. App. 2002).

Opinion

Reversed and Remanded in Cause No

Reversed and Remanded in Cause No. 14-00-01392-CV; Reversed and Rendered in Cause No. 14-01-01209-CV; and Opinion filed July 3, 2002.

In The

Fourteenth Court of Appeals

____________

NOS. 14-00-01392-CV

                    14-01-01209-CV

EXXONMOBIL PIPELINE COMPANY, Appellant

V.

HARRISON INTERESTS, LTD., Appellee

On Appeal from the County Court at Law No. 2

Fort Bend County, Texas

Trial Court Cause No. 13,616

O P I N I O N

In these consolidated cases, appellant ExxonMobil Pipeline Company (AExxonMobil@) appeals from a dismissal of its condemnation proceeding for lack of jurisdiction and a final judgment for the landowner, appellee Harrison Interests, Ltd. (AHarrison@), awarding damages resulting from ExxonMobil=s possession of the property it sought to condemn.  We reverse the dismissal of the condemnation proceeding and remand for further proceedings, and we reverse and render final judgment on the damages award.


FACTUAL AND PROCEDURAL BACKGROUND

ExxonMobil is a common carrier vested with the power of eminent domain.  In March of 1995, ExxonMobil determined that there was a public necessity to construct a common carrier pipeline from the Katy Gas Plant in Waller County, Texas, through Fort Bend County, Texas, to a location near Damon Junction in Brazoria County, Texas.  In connection with that project, ExxonMobil also determined that there was a public necessity to acquire a permanent right-of-way and easement across a 473-acre tract owned by Harrison in northern Fort Bend County.  The easement was to be fifty feet wide and 8,000 feet long, or 9.19 acres.

ExxonMobil attempted to negotiate with Harrison to acquire a permanent easement and a temporary construction easement.  The negotiations were unsuccessful, however, and on June 20, 1995, ExxonMobil made Harrison a final offer of $45,950.00 for the easements.  Enclosed with ExxonMobil=s final offer letter was a form easement and right-of-way agreement detailing the rights and interests it sought to acquire.  Harrison was given ten days to accept the offer.  ExxonMobil=s letter informed Harrison that in the event Harrison did not accept the final offer, ExxonMobil would initiate eminent domain proceedings.  Although  Harrison received the letter, he did not contact ExxonMobil within the ten-day period or at any time thereafter.

Having received no response to its final offer letter, on August 2, 1995, ExxonMobil filed its Statement and Petition in Condemnation seeking to take the easement.  After a special commissioners= hearing at which Harrison did not appear, ExxonMobil deposited the amount of compensation determined by the commissioners, $7,858.00, into the registry of the court, took possession of the easement, and installed the pipeline.


Prior to trial on the issue of just compensation, ExxonMobil moved for partial summary judgment on its right to condemn, asserting that no disputed facts were before the trial court.  Harrison responded to the motion and filed a cross motion for partial summary judgment, arguing that the trial court had no jurisdiction because ExxonMobil did not conduct good faith negotiations with Harrison prior to the condemnation proceeding.  Harrison contended that, among other things, ExxonMobil failed to negotiate in good faith by requiring Harrison to grant it rights which ExxonMobil was not entitled to obtain in a condemnation proceeding, including (1) the unrestricted right to assign the easement; and (2) the obligation of Harrison to warrant and defend title to the easement. 

Following a hearing on the cross motions for partial summary judgment, the trial court found that ExxonMobil had negotiated in good faith and ruled that ExxonMobil had the power to condemn the property sought in its petition.  Subsequently, however, the First Court of Appeals decided a condemnation case against the condemnor in a factually similar case.  Harrison then moved to dismiss Exxon=s condemnation proceeding for want of jurisdiction on the basis of the new authority.  On August 4, 2000, the trial court granted Harrison=s motion. 

After Exxon=s condemnation case was dismissed, Harrison sought a trial on damages resulting from ExxonMobil=s possession of the property, and attorney=s and expert fees as allowed by the Texas Property Code.  Following the trial, the trial court signed a final judgment on December 21, 2000 awarding Harrison $28,809.80 in professional fees and expenses, $110,000.00 in attorney=s fees through trial and appeal, $151,922.64 in damages through October 20, 2000, $102,534.92 in future damages through October 19, 2003, $75,961.32 in prejudgment interest accruing at the rate of $41.62 per day from October 18, 2000 until judgment, and postjudgment interest.  ExxonMobil was also ordered to pay all costs. 

ANALYSIS


In this consolidated appeal, Exxon appeals the dismissal of its condemnation case for want of jurisdiction and the final judgment in favor of Harrison. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hubenak v. San Jacinto Gas Transmission Co.
65 S.W.3d 791 (Court of Appeals of Texas, 2002)
County of Nueces v. Rankin
303 S.W.2d 455 (Court of Appeals of Texas, 1957)
Cusack Ranch Corp. v. MidTexas Pipeline Co.
71 S.W.3d 395 (Court of Appeals of Texas, 2002)
MidTexas Pipeline Co. v. Dernehl
71 S.W.3d 852 (Court of Appeals of Texas, 2002)
State v. Schmidt
894 S.W.2d 543 (Court of Appeals of Texas, 1995)
Mercier v. MidTexas Pipeline Co.
28 S.W.3d 712 (Court of Appeals of Texas, 2000)
Schlottman v. Wharton County
259 S.W.2d 325 (Court of Appeals of Texas, 1953)
Old Kent Leasing Services Corp. v. McEwan
38 S.W.3d 220 (Court of Appeals of Texas, 2001)
Hubenak v. San Jacinto Gas Transmission Co.
37 S.W.3d 133 (Court of Appeals of Texas, 2001)
State v. Hipp
832 S.W.2d 71 (Court of Appeals of Texas, 1992)
State v. Dowd
867 S.W.2d 781 (Texas Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Exxon Mobile Pipeline Company v. Harrison Interests, Ltd., Counsel Stack Legal Research, https://law.counselstack.com/opinion/exxon-mobile-pipeline-company-v-harrison-interests-texapp-2002.