Evolution Construction, LLC v. Finomus Orange Re Holdings, LLC

CourtNew Jersey Superior Court Appellate Division
DecidedJuly 16, 2025
DocketA-1405-23
StatusUnpublished

This text of Evolution Construction, LLC v. Finomus Orange Re Holdings, LLC (Evolution Construction, LLC v. Finomus Orange Re Holdings, LLC) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evolution Construction, LLC v. Finomus Orange Re Holdings, LLC, (N.J. Ct. App. 2025).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-1405-23

EVOLUTION CONSTRUCTION, LLC,

Plaintiff-Respondent,

v.

FINOMUS ORANGE RE HOLDINGS, LLC, FINOMUS EAST BRUNSWICK RE HOLDINGS, LLC, YUM & CHILL ORANGE TB, LLC, YUM & CHILL MANAGEMENT, LLC, and YUM & CHILL EAST BRUNSWICK, TB, LLC,

Defendants-Appellants. __________________________________

Submitted May 15, 2025 – Decided July 16, 2025

Before Judges Mawla and Natali.

On appeal from the Superior Court of New Jersey, Law Division, Somerset County, Docket No. L-0522-18.

Scarinci & Hollenbeck, LLC, attorneys for appellants (Joel N. Kreizman, of counsel and on the brief).

McHugh and Brancato, LLP, attorneys for respondent (Mark J. Brancato, on the brief). PER CURIAM

On December 14, 2023, after an eight-day bench trial, the court entered

judgment in favor of plaintiff Evolution Construction, LLC, after it determined

defendants Finomus Orange RE Holdings, LLC (Finomus Orange), and Finomus

East Brunswick RE Holdings, LLC (Finomus East Brunswick), breached two

contracts for the construction of fast-food restaurants. It also rejected and

accordingly dismissed defendants Finomus Orange's, Finomus East

Brunswick's, Yum and Chill Orange TB, LLC's, Yum and Chill Management,

LLC's, and Yum and Chill East Brunswick, TB, LLC's (collectively Yum and

Chill Entities) counterclaims sounding in breach of contract. Based upon our

review of the record and applicable legal principles, we affirm in part, reverse

in part, and remand for further proceedings.

I.

This matter concerns a dispute between the parties regarding the delayed

construction of two Taco Bell restaurants in Orange and East Brunswick. In

October 2015, plaintiff entered into two construction contracts with Finomus

Orange and Finomus East Brunswick to build the restaurants. Under both

contracts, plaintiff had ninety days to complete construction and turn the

A-1405-23 2 properties over to defendants. Plaintiff was to be paid $800,000 to construct the

Orange restaurant, and $780,000 for the East Brunswick location.

With respect to the Orange contract, two blank lines appeared where the

date of commencement and "outside date for substantial completion and

turnover" were supposed to be completed. As to the East Brunswick contract,

the date of commencement was designated as October 12, 2015, and "the outside

date for substantial completion and turnover" was January 9, 2016. Save for

these differences and the project locations, the two contracts were otherwise

identical.

As relevant here, Article 9 addressed issues pertaining to timing and

delays. Article 9.1 provided "time [was] of the essence" and stated plaintiff

would be liable to defendants "for all damages resulting from [plaintiff's] failure

to commence or complete the [w]ork in accordance with the" ninety-day

timeframe. Article 9.2 defined certain circumstances that would toll the ninety-

day requirement and grant plaintiff an extension of the contract time:

In the event construction of the [p]roject or completion of any portion of the [w]ork is unavoidably delayed by (i) extraordinary conditions of weather for the area and time of year, in excess of that normally encountered, (ii) war or national conflicts or the arising there from, (iii) strikes or other labor disruptions beyond the control of [plaintiff] (except the first five . . . working days of any strike or labor disruption), (iv) fires,

A-1405-23 3 earthquakes, floods or other natural disasters, the damage from which was beyond the control of [plaintiff], or (v) the acts (including [c]hanges) or omission of [Finomus Orange or Finomus East Brunswick] or its designated representatives, [plaintiff] shall continue to advance the [w]ork as expeditiously as possible. To the extent such unavoidable delays cause a critical delay to the overall completion of the [w]ork, [plaintiff] by [c]hange [o]rder shall be entitled to an extension of the [c]ontract [t]ime in an amount equal to the number of calendar days completion of the [w]ork was actually delayed. However, no extension of the [c]ontract [t]ime shall be granted unless [plaintiff] has delivered to [Finomus Orange or Finomus East Brunswick] a written notice of the cause of the delay with[in] ten . . . days after the commencement of the delay and has demonstrated that such delay was on the critical path of the [c]onstruction [p]rogress [s]chedule.

The contract also provided plaintiff was responsible for obtaining "all

licenses, permits, approvals, and certificates," and Finomus Orange and

Finomus East Brunswick would not be liable to plaintiff "for any delays

in . . . obtaining the building permit." As to payments, Article 17.6.1 required

Finomus Orange and Finomus East Brunswick to "make payment to [plaintiff]

of all undisputed amounts due and owing [plaintiff] not later than twenty[ -]one

. . . days following [Finomus Orange's and Finomus East Brunswick's] receipt

and acceptance of [plaintiff's] application for payment."

To achieve substantial completion, Article 19.1.1 required plaintiff turn

the property over such that it may be fully occupied and "use[d] for the purpose

A-1405-23 4 that the [p]roject was intended." In order to attain final completion, Articles

20.1 and 20.2 required the parties to generate a punch list of work which plaintiff

would have ten calendar days to complete. With respect to final payment, the

contract provided "the release of the ten percent . . . retainage amount . . . shall

be made by [Finomus Orange and Finomus East Brunswick] to [plaintiff] when

the [c]ontract and [w]ork required thereunder have been fully performed."

Additionally, under the contract, Finomus Orange and Finomus East Brunswick

were permitted to "withhold any amounts due [by it] as provided for in th[e

c]ontract or which [they] dispute[d were] due [plaintiff]."

Almost immediately after the parties executed the contracts, as we discuss

in greater detail below, plaintiff encountered numerous delays with both

projects. These delays included, among other things, weather-related issues,

prolonged permit-approval processes, and unanticipated issues with the local

utility company. As a result, plaintiff did not finish construction of either

restaurant within the original ninety-day timeframes.

Due to the delayed construction processes, Finomus Orange and Finomus

East Brunswick withheld multiple progress payments and final payments due

plaintiff. Because it had not received these payments, plaintiff repudiated its

A-1405-23 5 obligation to complete all punch list items and supply defendant with a list of

its subcontractors as well as their contact information.

As a result, on April 23, 2018, plaintiff filed a six-count complaint against

Finomus Orange and Finomus East Brunswick, alleging breach of contract,

unjust enrichment, and money due under a book account. With respect to the

Orange contract, plaintiff alleged Finomus Orange owed $124,852.96, plus

interest. With respect to the East Brunswick contract, plaintiff claimed Finomus

East Brunswick owed $113,916.07, plus interest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chance v. McCann
966 A.2d 29 (New Jersey Superior Court App Division, 2009)
Marioni v. 94 Broadway, Inc.
866 A.2d 208 (New Jersey Superior Court App Division, 2005)
Ross Systems v. Linden Dari-Delite, Inc.
173 A.2d 258 (Supreme Court of New Jersey, 1961)
Bradford v. Kupper Associates
662 A.2d 1004 (New Jersey Superior Court App Division, 1995)
Mountain Hill, LLC v. Tp. of Middletown
945 A.2d 59 (New Jersey Superior Court App Division, 2008)
Highland Lakes Country Club & Community Ass'n v. Franzino
892 A.2d 646 (Supreme Court of New Jersey, 2006)
State v. Brown
573 A.2d 886 (Supreme Court of New Jersey, 1990)
Matter of Trust Created by Agreement Dated December 20, 1961
944 A.2d 588 (Supreme Court of New Jersey, 2008)
Kampf v. Franklin Life Insurance
161 A.2d 717 (Supreme Court of New Jersey, 1960)
Nolan v. Lee Ho
577 A.2d 143 (Supreme Court of New Jersey, 1990)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Borough of Berlin v. Remington & Vernick Engineers
767 A.2d 1030 (New Jersey Superior Court App Division, 2001)
Zacarias v. Allstate Insurance
775 A.2d 1262 (Supreme Court of New Jersey, 2001)
Rova Farms Resort, Inc. v. Investors Insurance Co. of America
323 A.2d 495 (Supreme Court of New Jersey, 1974)
Karl's Sales & Serv., Inc. v. Gimbel Bros., Inc.
592 A.2d 647 (New Jersey Superior Court App Division, 1991)
State v. Barone
689 A.2d 132 (Supreme Court of New Jersey, 1997)
Kieffer v. Best Buy
14 A.3d 737 (Supreme Court of New Jersey, 2011)
Seidman v. Clifton Savings Bank
14 A.3d 36 (Supreme Court of New Jersey, 2011)
Tahir Zaman v. Barbara Felton (072128)
98 A.3d 503 (Supreme Court of New Jersey, 2014)
State of New Jersey v. Scott Robertson
102 A.3d 381 (New Jersey Superior Court App Division, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Evolution Construction, LLC v. Finomus Orange Re Holdings, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/evolution-construction-llc-v-finomus-orange-re-holdings-llc-njsuperctappdiv-2025.