Evergreen International, S.A. v. Marinex Construction Co.

477 F. Supp. 2d 690, 2007 U.S. Dist. LEXIS 20640, 2007 WL 744618
Procedural entryThis page is a short order in Evergreen International, S.A. v. Marinex Construction Co.. Read the opinion of the Court — 477 F. Supp. 2d 697
District Court, D. South Carolina·Decided March 3, 2007·No. C.A. 2:04-22351-PMD·Published

Opinion

ORDER

DUFFY, District Judge.

This matter is before the court on Defendant Marinex Construction Company, Inc.’s (“Marinex”) motion for summary judgment. For the following reasons, the court grants this motion.

BACKGROUND

On February 14, 2002, the United States Army Corps of Engineers awarded dredging contract DACW60-02-C-0002 (“the Dredging Contract”) to Defendant Mari-nex. The Dredging Contract was for “new work and maintenance dredging” in the Cooper River between Shipyard Creek and the turning basin ■ above the North Charleston Container • Terminal (“the Dredging Project”). On February 19, 2002, Marinex entered into a subcontract with Norfolk Dredging Company, Inc. *692 (“NDC”) for performance of a portion of the Dredging Project. The subcontract, which took the form of a two-page letter agreement, required NDC to “perform all work in accordance with U.S. Army Corps of Engineers Plans and Specifications.”

On September 19, 2002, NDC laid a submerged pipeline across the marked federal channel at about the upper of the “Daniel Island Bend” section of the Cooper River. In the early morning of September 30, 2002, a 965 foot container vessel owned by Plaintiff Evergreen International, S.A. (“Evergreen”), the M/V EVER REACH, arrived at Charleston Harbor. The M/V EVER REACH continued its transit from Charleston Harbor up the Cooper River toward the North Charleston Container Terminal, which was upstream of NDC’s dredging operation. In the course of this passage, the M/V EVER REACH struck NDC’s submerged dredge pipeline, gashing its outer shell plating and spilling bunker fuel into the Cooper River.

Evergreen alleges numerous causes of action for negligence and various statutory violations against both Marinex and NDC. All of Evergreen’s allegations against Mar-inex are premised on the assumption that Marinex itself was engaged in the dredging operations which caused the damages to the M/V EVER REACH. Marinex contends, however, that the evidence shows that Marinex acted only as a general contractor, and thus did not perform the supposedly negligent dredging operations at issue. Accordingly, with Norfolk acting as an independent contractor performing the dredging activities, Marinex claims it had no duty to Evergreen. In maritime cases, as in land-based negligence cases, the determination of a legal duty is a question of law. Theriot v. United States, 245 F.3d 388 (5th Cir.1998). Accordingly, Marinex asserts that summary judgment should be entered dismissing it from this case.

STANDARD OF REVIEW

Summary judgment is appropriate only “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits show that there is no genuine issue as to any material fact.” Fed.R.Civ.P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). In deciding whether there is a genuine issue of material fact, “[t]he evidence of the non-movant is to be believed, and all justifiable inferences are to be drawn in his favor.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). The judge is not to weigh the evidence but rather to determine if there is a genuine issue for trial. Id. “[Wjhere the record taken as a whole could not lead a rational trier of fact to find for the nonmoving party, disposition by summary judgment is appropriate.” Teamsters Joint Council No. 83 v. Centra, Inc., 947 F.2d 115, 119 (4th Cir.1991).

“[T]he plain language of Rule 56(c) mandates the entry of summary judgment, after adequate time for discovery and upon motion, against a party who fails to make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof at trial.” Celotex, 477 U.S. at 322, 106 S.Ct. 2548. The “obligation of the nonmoving party is ‘particularly strong when the nonmoving party bears the burden of proof.’ ” Hughes v. Bedsole, 48 F.3d 1376, 1381 (4th Cir.1995) (quoting Pachaly v. City of Lynchburg, 897 F.2d 723, 725 (4th Cir.1990)). Summary judgment is not “a disfavored procedural shortcut,” but an important mechanism for weeding out “claims and defenses [that] have no factual bases.” Celotex, 477 U.S. at 327, 106 S.Ct. 2548.

*693 DISCUSSION

There is no dispute that Marinex subcontracted with NDC to perform the Dredging Project, the negligent performance of which allegedly caused the injury to the M/V EVER REACH. Evergreen concedes that NDC is an independent contractor and is not an agent of Marinex. Evergreen also recognizes the general rule that an employer is not liable for the negligence of an independent contractor. However, Evergreen notes that the exceptions to this general rule “are so numerous ... they have eroded the general rule such that it can now be said to be ‘general’ only in the sense that it is applied where no good reason is found for departing from it.” (Response at 10.) Specifically, citing to sections of Restatement (Second) of Torts, Evergreen notes that an employer is liable for the torts of a hired indepen-, dent contractor where (1) the employer provides “plans and specifications” to the independent contractor which are insufficient to maintain the project in a reasonably safe condition; (2) the employer employs an independent contractor to do work which the employer should recognize as likely to create, during its progress, a peculiar unreasonable risk of harm to others unless special precautions are taken, and employer fails to take such “special precautions;” (3) the employer employs an independent contractor to repair a public thoroughfare; (4) the employer has an independent duty pursuant to statute or regulation to provide specific safeguards or precautions for the safety of others; and (5) the employer exercises a degree of supervisory control over the independent contractor and fails to exercise such control with reasonable care. Evergreen asserts that Marinex may be held liable for the tortious conduct of its independent contractor NDC under any of these exceptions. The court discusses the applicability of each of these exceptions in turn:

(1) Insufficient Plans and Specifications

Citing to Section 410 of the Restatement (Second) of Torts,

Free access — add to your briefcase to read the full text and ask questions with AI

Evergreen International, S.A. v. Marinex Construction Co., 477 F. Supp. 2d 690, 2007 U.S. Dist. LEXIS 20640, 2007 WL 744618 (D.S.C. 2007).

477 F. Supp. 2d 690 (Evergreen International, S.A. v. Marinex Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Hughes v. Bedsole
48 F.3d 1376 (Fourth Circuit, 1995)
Ross v. Dae Julie, Inc.
793 N.E.2d 68 (Appellate Court of Illinois, 2003)
In Re Garvey Marine, Inc.
424 F. Supp. 2d 1109 (N.D. Illinois, 2006)
Slater v. . Mersereau
64 N.Y. 138 (New York Court of Appeals, 1876)
Amann v. City of Tacoma
16 P.2d 601 (Washington Supreme Court, 1932)
Langrell v. Harrington
41 A.2d 461 (Superior Court of Delaware, 1945)
South Carolina Natural Gas Co. v. Phillips
289 F.2d 143 (Fourth Circuit, 1961)
Theriot v. United States
245 F.3d 388 (Fifth Circuit, 1998)
James' Adm'r v. McMinimy
20 S.W. 435 (Court of Appeals of Kentucky, 1892)
Powell v. Construction Co.
13 S.W. 691 (Tennessee Supreme Court, 1890)
Salliotte v. King Bridge Co.
122 F. 378 (Sixth Circuit, 1903)
Teamsters Joint Council No. 83 v. Centra, Inc.
947 F.2d 115 (Fourth Circuit, 1991)