Evergreen Community Power v. Riggs Distiler & Co Inc

513 F. App'x 236
CourtCourt of Appeals for the Third Circuit
DecidedFebruary 12, 2013
Docket12-2365, 12-2423
StatusUnpublished
Cited by2 cases

This text of 513 F. App'x 236 (Evergreen Community Power v. Riggs Distiler & Co Inc) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evergreen Community Power v. Riggs Distiler & Co Inc, 513 F. App'x 236 (3d Cir. 2013).

Opinion

OPINION OF THE COURT

ALDISERT, Circuit Judge.

Evergreen Community Power LLC (“Evergreen”) and Riggs Distler & Company, Inc. (“Riggs”) appeal from three final orders 1 entered in the United States District Court for the Eastern District of Pennsylvania. Together these orders (1) awarded Evergreen $422,923.83 in damages for breach of contract, (2) awarded Evergreen $539,521.15 in attorneys’ fees, and (3) held in favor of Evergreen on all of Riggs’s counterclaims. We will affirm.

I.

Evergreen filed a complaint against Riggs for breach of contract after Riggs failed to complete pipe installation in an Evergreen power plant by the date specified in the parties’ contract: January 31, 2009. Riggs filed a counterclaim for breach of contract; breach of the covenant of good faith and fair dealing; unjust enrichment; and promissory estoppel.

During the bench trial, Riggs conceded that it did not complete the pipe installation by the date specified in the contract— January 31, 2009 — but argued that this date was not applicable because Evergreen added to Riggs’s scope of work and the contract contained a provision stating that such an addition would render the specified date inapplicable. The District Court accepted this argument. It determined, however, that Riggs nonetheless breached its contract with Evergreen because even if the specified completion date was rendered inapplicable by Evergreen’s additions to the scope of work, Riggs still had a duty to complete the project within a reasonable amount of time. The District Court determined this reasonable amount of time expired no later than April 27, 2009 but that the pipe installation was not finished until May 17, 2009. The Court held, therefore, that Evergreen had proven by a preponderance of the evidence that Riggs was liable for breach of the contract and awarded Evergreen $422,923.83. The Court also awarded Evergreen $539,521.15 for attorneys’ fees, costs and expenses un *238 der the contract’s fee-shifting provision. Four issues are presented for our consideration, and we shall discuss them ad seri-atim. 2

II.

The first issue raised by the parties is whether Riggs breached its contract with Evergreen when it failed to complete its work by January 31, 2009. According to the contract, Riggs was required to complete the pipe installation by January 31, 2009 only if “no additions [were] made to the agreed upon scope of work.” In interpreting this provision, the District Court concluded that “no additions” meant “no gross additions,” and, because Evergreen had made gross additions to Riggs’s scope of work, the January 31, 2009 deadline did not apply. Evergreen argues that “no additions” should have been read to prohibit any net additions to Riggs’s scope of work — that is, the January 31, 2009 deadline should still have applied if Evergreen cancelled out any changes that added to the scope of Riggs’s work with changes that subtracted from the scope of Riggs’s work.

We agree with the District Court that “no additions” means “no gross additions.” We need not, however, dwell on the issue of whether “no additions” should be interpreted to mean “no net additions” or “no gross additions” because it has no bearing on the outcome of this ease. As we shall explain, the District Court did not err when it found that, even if the January 31 deadline did not apply, Riggs failed to complete the pipe installation in a reasonable amount of time, which it determined expired no later than April 27, 2009. Therefore, Riggs breached the contract no later than April 27, 2009. The District Court also found that Riggs’s failure to complete the pipe installation did not begin to cause Evergreen any damages until April 27, 2009. Because Riggs’s delay did not begin causing damages until April 27, it is immaterial whether the contract was breached on January 31 or sometime between January 31 and April 27.

III.

After concluding the January 31, 2009 completion date was inapplicable, the District Court did not err in (a) concluding Riggs was required to complete its work within a “reasonable time,” (b) determining that this “reasonable time” extended no later than April 27, 2009 and (c) finding Riggs could not be held liable for delays that occurred before April 27, 2009, the date the vortex finder was installed.

“[Wjhere no time is specified for performance of a contractual obligation, the courts will require that the obligation be performed within a ‘reasonable’ time.” Hodges v. Pa. Millers Mut. Ins. Co., 449 *239 Pa.Super. 341, 673 A.2d 973, 974 (1996). 3 Although the parties here did not argue directly the issue of what a “reasonable time for performance” would be if the January 31, 2009 completion date was determined to be inapplicable, the District Court’s decision relied upon evidence presented by the parties, including documents that tracked additions and subtractions to Riggs’s scope of work, and testimony regarding critical stages of construction and the roles various subcontractors and events had in ensuring timely completion. 4 It considered also what part Evergreen had in causing delays. See App. 38-39. (“Even assuming that there may have been some delays prior to April 27, 2009 because of the EWAs or RFIs, or because of reasons attributable to Evergreen such as priority changes, these delays did not prevent Riggs from finishing its work by [April 27].”). Additionally, the District Court’s finding that Riggs could not be held liable for delays that occurred before the installation of the vortex finder was not clear error. Even if Riggs was responsible for delays that began accruing before the vortex finder was installed, it does not necessarily follow that these delays caused damages to Evergreen before the vortex finder was installed. Evergreen bore the burden of proof for each element of its claim, see Ware v. Rodale Press, Inc., 322 F.3d 218, 225 (3d Cir.2003) (quoting CoreStates Bank, N.A. v. Cubillo, 723 A.2d 1053, 1058 (Pa.Super.Ct.1999)), and we hold that the District Court’s determination was not “completely devoid of minimum evidentiary support,” nor did it fail to bear any “rational relationship to the supportive evidentiary data,” see Krasnov, 465 F.2d at 1302.

IV.

The District Court did not err in refusing to award Evergreen all of its claimed attorneys’ fees. The contract’s attorneys’ fees provision stated that Riggs would pay Evergreen all “reasonable” attorneys’ fees incurred by Evergreen in the enforcement of any of Evergreen’s “rights or remedies” under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
513 F. App'x 236, Counsel Stack Legal Research, https://law.counselstack.com/opinion/evergreen-community-power-v-riggs-distiler-co-inc-ca3-2013.