Allied Erecting & Dismantling Co. v. United States Steel Corp.

CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 23, 2018
Docket15-4182
StatusUnpublished

This text of Allied Erecting & Dismantling Co. v. United States Steel Corp. (Allied Erecting & Dismantling Co. v. United States Steel Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Erecting & Dismantling Co. v. United States Steel Corp., (6th Cir. 2018).

Opinion

NOT RECOMMENDED FOR FULL-TEXT PUBLICATION File Name: 18a0090n.06

No. 15-4182

UNITED STATES COURT OF APPEALS FILED FOR THE SIXTH CIRCUIT Feb 23, 2018 DEBORAH S. HUNT, Clerk ) ALLIED ERECTING AND DISMANTLING CO., ) INC., ) ON APPEAL FROM THE ) UNITED STATES DISTRICT Plaintiff-Appellant, ) COURT FOR THE NORTHERN ) DISTRICT OF OHIO v. ) ) UNITED STATES STEEL CORPORATION, ) OPINION ) Defendant-Appellee. ) )

Before: MERRITT, MOORE, and BUSH, Circuit Judges.

JOHN K. BUSH, Circuit Judge. For decades, Plaintiff Allied Erecting and Dismantling

Co., Inc. (“Allied”), has served Defendant United States Steel Corporation (“U.S. Steel”) by

dismantling U.S. Steel’s defunct steelmaking facilities and salvaging the resulting scrap metal.

And for decades, Allied and U.S. Steel have litigated claims arising from their dismantling-work

agreements. In this action, Allied brought eight claims against U.S. Steel for breach of contract

and one for a declaratory judgment, and U.S. Steel brought three counterclaims against Allied

(the first and third for breach of contract, and the second for return of a $10 million advance

payment). On appeal, Allied argues that the district court erred in (1) granting judgment as a

matter of law for U.S. Steel as to three of Allied’s claims (Counts III, IV, and V) on statute-of-

limitations grounds; (2) granting summary judgment for U.S. Steel as to U.S. Steel’s second

counterclaim (that is, as to the $10 million advance payment); and (3) granting U.S. Steel’s Rule No. 15-4182, Allied Erecting & Dismantling Co. v. U.S. Steel Corp.

59(e) motion to alter or amend the judgment, which reduced Allied’s damages on Count II to

zero. For the reasons that follow, we reverse as to Allied’s Counts IV and V, and we affirm in all

other respects.

I

Allied and U.S. Steel began working together in the 1980s, but this appeal traces its

origins to 1992, when U.S. Steel hired Allied to dismantle its massive Fairless Works

steelmaking facility in Fairless Hills, Pennsylvania. The parties entered into two contracts at that

time: the 1992 Construction Contract and the 1992 Final Conformed Specification (“1992

Specification”). As the Fairless facility began to undergo dismantling, so did the parties’

relationship: Allied sued U.S. Steel for additional compensation and other relief first in 1993 and

then in 2002, resulting in settlement agreements not reached until 2003 and 2004, termed the

2003 and 2004 Agreements in Principle (“2003 AIP” and “2004 AIP”), respectively.

The 2003 AIP granted Allied the exclusive right to further dismantling work at Fairless,

among other things; for its part, Allied agreed to perform certain dismantling work at Fairless at

no cost to U.S. Steel other than that Allied would acquire title to scrap recovered during the

dismantling (which Allied could then sell, subject to U.S. Steel’s right of first refusal, to generate

a profit). The 2004 AIP provided Allied with certain rights to dismantling work at sites other

than Fairless. Among other things, the 2004 AIP also contemplated manufacturing (and not only

dismantling) work, and it provided that U.S. Steel pay Allied a $10 million “non-refundable

advance payment” that U.S. Steel would recoup in the form of discounts applied to invoices for

the manufacturing work to be performed at Allied’s yet-to-be-built manufacturing facility.

The parties entered into several subsequent contracts, bringing the total number of

contracts governing the parties’ relationship to ten, none of which entirely supersedes any other.

2 No. 15-4182, Allied Erecting & Dismantling Co. v. U.S. Steel Corp.

The trial record and the district court’s orders and opinions sufficiently set forth the terms of

these contracts, which we have reviewed but which we will not detail at any greater length in this

opinion. Instead, we turn to Allied’s three questions presented and address each issue in turn.

II

Judgment as a Matter of Law as to Allied’s Counts III, IV, and V

Allied’s Counts I through VI all arise from Allied’s dismantling work at Fairless. The

parties agree that Allied engaged in substantial dismantling work, tearing down out-of-use

buildings and completing other related work at U.S. Steel’s request. In its second amended

complaint filed in June 2012, Allied asserted Counts III, IV, and V as follows:

Count III. Allied sought breach-of-contract damages under Section 3.1 of the 1992

Construction Contract arising from U.S. Steel’s alleged delays in “releasing” facilities at Fairless

to Allied so that Allied could begin dismantling them and salvaging scrap to sell. Allied alleged

numerous sources of delays including, for example, U.S. Steel’s “[f]ailing to complete necessary

predecessor work, including the relocation of necessary utilities and/or the performance of

asbestos removal, hazmat removal and/or environmental work.” 2d Amended. Compl. 18–23.

Count IV. Allied sought breach-of-contract damages under Section 10.3 of the 1992

Specification for U.S. Steel’s allegedly wrongful retention of (or indefinite indecision as to

whether to retain) certain Fairless facilities for itself, without compensation, rather than either

turning them over for Allied to dismantle or paying Allied the scrap value of such facilities. Id. at

23–25.

Count V. Allied sought breach-of-contract damages under Sections 5.2.2 and 5.2.3 of the

1992 Specification and Section III(c) of the 2003 AIP, alleging that U.S. Steel had prevented

Allied from removing certain scrap and railroad track from areas being dismantled but had

wrongly insisted that Allied dispose of creosote-containing railroad ties, when such railroad ties

3 No. 15-4182, Allied Erecting & Dismantling Co. v. U.S. Steel Corp.

were hazardous materials for which U.S. Steel was required to bear the cost of disposal. Id. at

25–27.

On motion by U.S. Steel, the district court granted judgment as a matter of law in favor of

U.S. Steel as to all three of these counts.1 The court held that Allied’s claims in all three counts

accrued in January 2007 at the latest and thus were time-barred under Pennsylvania’s four-year

statute of limitations for contract actions.

A

We review de novo the district court’s grant of judgment as a matter of law, using the

same standard that the district court should have used, i.e., that such a grant is appropriate only

when “no reasonable juror could have found for the nonmoving party.” Kiphart v. Saturn Corp.,

251 F.3d 573, 581 (6th Cir. 2001); see Fed. R. Civ. P. 50(a).

The parties generally do not dispute that Pennsylvania substantive law governs all the

claims in this diversity-jurisdiction action, except that Allied contends that the issue of when its

claims accrued is governed by federal, rather than state, law. But the case Allied cites for its

proposition, Ruff v. Runyon, 258 F.3d 498 (6th Cir. 2001), involved claims under federal law, not

state-law causes of action as here. When claims arise under state law, accrual of such claims is

governed by state law as well. See, e.g., Univ. of Pittsburgh v. Townsend, 542 F.3d 513, 523–24

(6th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. City of Memphis
617 F.3d 864 (Sixth Circuit, 2010)
Ronald Jeffrey Kiphart v. Saturn Corporation
251 F.3d 573 (Sixth Circuit, 2001)
Evergreen Community Power v. Riggs Distiler & Co Inc
513 F. App'x 236 (Third Circuit, 2013)
University of Pittsburgh v. Townsend
542 F.3d 513 (Sixth Circuit, 2008)
Kapil v. Association of Pennsylvania State College & University Faculties
470 A.2d 482 (Supreme Court of Pennsylvania, 1983)
PSC Info Group v. Lason, Inc.
681 F. Supp. 2d 577 (E.D. Pennsylvania, 2010)
Melley v. Pioneer Bank, N.A.
834 A.2d 1191 (Superior Court of Pennsylvania, 2003)
Fine v. Checcio
870 A.2d 850 (Supreme Court of Pennsylvania, 2005)
Sadtler v. Jackson-Cross Co.
587 A.2d 727 (Superior Court of Pennsylvania, 1991)
William F. Mosser Co. v. Cherry River Boom & Lumber Co.
138 A. 85 (Supreme Court of Pennsylvania, 1927)
Susan King v. Todd Harwood
852 F.3d 568 (Sixth Circuit, 2017)
Ruff v. Runyon
258 F.3d 498 (Sixth Circuit, 2001)
Thorpe v. Schoenbrun
195 A.2d 870 (Superior Court of Pennsylvania, 1963)
Soroof Trading Development Co. v. Ge Fuel Cell Systems LLC
842 F. Supp. 2d 502 (S.D. New York, 2012)
Cottman Transmission Systems, Inc. v. Dubinsky
550 F. Supp. 133 (E.D. Pennsylvania, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Allied Erecting & Dismantling Co. v. United States Steel Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-erecting-dismantling-co-v-united-states-steel-corp-ca6-2018.