Eustis v. Smith

3 Mass. L. Rptr. 216
CourtMassachusetts Superior Court
DecidedOctober 11, 1994
DocketNo. 92-0636
StatusPublished

This text of 3 Mass. L. Rptr. 216 (Eustis v. Smith) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eustis v. Smith, 3 Mass. L. Rptr. 216 (Mass. Ct. App. 1994).

Opinion

Connon, J.

The plaintiff, Peter Eustis, brings this action pursuant to G.L.c. 249, §4 to appeal the decision of the Conservation Commission of the Town of Bourne (Commission), who refused to grant Eustis permission to extend and maintain a breakwater on his property. On July 25, 1994, the court heard this case. After reviewing the administrative record, and hearing the testimony of the witnesses, the Commission’s decision is affirmed.

FINDINGS OF FACT

1. Eustis owns the property located at 668 Scraggy Neck Road, Cataumet, Bourne, Massachusetts. The property is bounded to the southwest by Megansett Harbor, which is part of Buzzards Bay.

2. The property’s shoreline is currently protected by two stone groins (jetties) extending 80 to 90 feet into the harbor. These jetties currently intercept and trap latteraly moving sediment moving in the direction of adjacent shellfish flats.

3. In 1992, Eustis decided to extend the breakwater facing the harbor in order to provide extra protection to his home during storms. Eustis’s home is approximately 40-45 feet from the edge of the coastal erosion.

4. On March 23, 1992, Eustis submitted a Notice of Intent to the Commission, as required by G.L.c. 131, §40 and the Bourne Wetlands Protection By-Law 3.7 (by-law), seeking a building permit for the project.

5 The area of proposed construction on Eustis’s property falls within two wetlands resource areas — a coastal beach and a coastal dune. The activity is also [217]*217within several tidal velocity zones and within the buffer of land containing abundant shellfish.

6. Under Eustis’s proposed construction plan, lárge stones on the beach would be removed and utilized in extending the breakwater.

7. Eustis’s construction plan also proposes to create “gaps” throughout the breakwater so waters may run seaward and not pool on the upland side of the breakwater. Eustis’s site plan, however, fails to indicate any “gaps” in the breakwater.

8. Eustis’s plan seeks to bring in stone and sand fill to construct the breakwater.

9. The Notice of Intent Eustis submitted requires an applicant to accurately describe the manner in which the proposed project will meet the performance standards in 310 Mass. Code. Reg. 10.00 et seq. and to describe why the presumptions set forth under each resource area2 in the regulations do not apply to the project.

10. On June 8, 1992, the Commission denied Eustis’s request. The Commission denied Eustis’s project for the following reasons:

1. Eustis failed to document that further armoring of this area will not create a negative impact on the benthic community.
2. The property is currently heavily armored by groins and large boulders that trap and deny sediment to the shellfish flats within the buffer and down coast. These structures provide significant protection to the applicant’s property.
3. The proposal will place rocks and fill in an area that contains some vegetation, eliminating the ability of the natural occunring vegetation to be re-established.
4. The placement of a bulkhead upon a coastal dune or beach to contain fill is prohibited.
5. The project does not meet the performance standards for a project such as this upon coastal dunes and beaches.
6. Eustis failed to document the potential negative impact to the adjacent benthic community from the construction of the bulkhead.
7. The negative impacts from altering a coastal wetland have not been documented to the satisfaction of the Commission.
8. The proposed structure poses unacceptable direct threats to the shellfishery and its habitat.

11. On August 13, 1993, the Department of Environmental Protection (DEP) issued a Superseding Order of Conditions.

RULINGS OF LAW

General Laws c. 249, §4 permits an aggrieved party to bring an action in Superior Court to correct errors in proceedings which are not otherwise reviewable by motion or by appeal. Cepulonis v. Commissioner of Correction, 15 Mass.App.Ct. 292, 293 (1983). In a certiorari review the court may correct errors of law committed by a judicial or quasijudicial tribunal that are so substantial and material that, if allowed to stand, would result in manifest injustice to the petitioner who is without any other available remedy.3 Johnson Products, Inc. v. City Council of Medford, 353 Mass. 540, 541 (1968).

In the case at bar, Eustis contends that the DEP's Superseding Order renders the Commission’s decision moot. Additionally, Eustis asserts that if the Commission’s decision denying his application is not moot, the decision is not supported by substantial evidence.

I. Does the DEP’s Superseding Order render the Commission’s decision moot?

Eustis argues that the Commission’s denial on the proposed project was not based on a by-law that provides greater protection than the Wetlands Protection Act, G.L.c. 131, §40, and therefore the Superseding Order of Conditions issued by the DEP is final. Eustis bases his argument on DeGrace v. Conservation Commission of Harwich, 31 Mass.App.Ct. 132 (1991). In DeGrace, the Conservation Commission of Harwich denied the applicants’ project pursuant to a Harwich by-law. Id. at 133. The applicants appealed the Commission’s decision to the Department of Environmental Quality Engineering (DEQE),4 and also appealed to District Court. Id. The DEQE issued a Superseding Order. In examining the appeal to District Court, the Massachusetts Court of Appeals held that the Harwich by-law did not provide greater protection than G.L.c. 131, §40 and therefore the decision of the Commission had become moot when the DEQE issued its Superseding Order. Id. at 136. The court reasoned that the Legislature reserved to the Commonwealth, acting through its agent (the DEQE), the final decision on applications for projects affecting wetland protection and therefore only a decision made pursuant to a by-law with more stringent controls than the minimum statewide standards than those set by the Legislature could be reviewed. Id. at 135.

General Laws c. 131, §40 seeks to protect the following interests: the public and private water supply, ground water supply, flood control, storm damage prevention, prevention of pollution, shellfish and fisheries, and wildlife habitat. See also 310 Code Mass. Regs. 10.01 (1994). The Bourne by-law seeks to protect all the interests enunciated in G.L.c. 131, §40 and 310 Code Mass. Regs. 10.01, but lists additional interests. These interests include erosion and sedimentation control, and recreational uses. The Bourne by-law defines all these interests as “wetland resource values” and if the Commission determines that the applicant’s project may have a adverse impact on any one of these wetland resource values, the project may be denied. (Bourne By-Law, §3.7.2.) In the case at bar, one of the Commission’s focal reasons for denying [218]*218Eustis’s application concerned sediment drift. Unlike G.L.c. 131, §40, the Bourne by-law expressly seeks to protect sediment flow. Accordingly, the Commission based its decision on a by-law which provides greater protection than G.L.c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson Products, Inc. v. City Council of Medford
233 N.E.2d 316 (Massachusetts Supreme Judicial Court, 1968)
Boston Edison Co. v. Boston Redevelopment Authority
371 N.E.2d 728 (Massachusetts Supreme Judicial Court, 1977)
Boston Edison Co. v. Board of Selectmen of Concord
242 N.E.2d 868 (Massachusetts Supreme Judicial Court, 1968)
Lovequist v. Conservation Commission of Dennis
393 N.E.2d 858 (Massachusetts Supreme Judicial Court, 1979)
DeGrace v. Conservation Commission of Harwich
575 N.E.2d 373 (Massachusetts Appeals Court, 1991)
Cepulonis v. Commissioner of Correction
445 N.E.2d 178 (Massachusetts Appeals Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
3 Mass. L. Rptr. 216, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eustis-v-smith-masssuperct-1994.